(F) Reprint permit | | | 8/28/2012 | | DONE |
Barbara Stitt
|
|
|
|
Case Summary (BLD) | | | 8/28/2012 | | |
|
|
|
|
Case Summary (BLD) | | | 8/28/2012 | | |
|
|
|
|
First Notice | | 1/23/2011 | 1/31/2011 | | DONE |
|
|
|
|
BLD-Final | 1/13/2011 | 1/13/2011 | 1/13/2011 | P | PASS |
Mike Jordan
|
|
|
ok for perm occ.
|
BLD-Final | 1/12/2011 | 1/13/2011 | 1/13/2011 | A | PART |
Mike Jordan
|
|
|
Call 30 min prior--Karen Phone #: ###-####. Ok for Temp occ. Need final letter from special inspection agency.
|
FIRE-Final Inspection | 1/12/2011 | 1/13/2011 | 1/13/2011 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Permanent Occupancy UNPAID FEE | | | 1/13/2011 | | DONE |
Tisha Gallop
|
|
|
|
Meeting | | | 1/13/2011 | | DONE |
Tisha Gallop
|
|
|
When General Contractor was in office getting C of O said to send request for final values to applicant Travis Shain/Collister Shopping Center or representative Christophe Guigon/Guigon Olson Studios because GC doesn't know $ for parts he was not involved in.
|
FIRE-Conference | 1/10/2011 | 1/10/2011 | 1/10/2011 | P | DONE |
Troy Cobbley
|
|
|
Carl Westfall is ok with the exit sign that was shown to be installed at the top of the stairs to the mezzanine to be deleted.
|
FIRE-Conference | 1/7/2011 | 1/7/2011 | 1/7/2011 | P | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements prior to the final inspection. This included verifying that the existing exit discharge lights still function, verifying the new exit signs/emergency lights work, tagging the fire exitinguishers and providing the correct occupant load sign for the coffee shop.
|
BLD-Other | 1/5/2011 | 1/6/2011 | 1/7/2011 | A | PART |
Tony Young
|
|
|
Dave Phone #: ###-####,, final walk through conf.
|
BLD-Framing/Rough-in | 12/14/2010 | 12/15/2010 | 12/14/2010 | A | PASS |
Tony Young
|
|
|
dave Phone #: ###-####,, bathroom frame ok
|
BLD-Final | 12/13/2010 | 12/14/2010 | 12/14/2010 | A | NR |
Tony Young
|
|
|
dave Phone #: ###-####,, not a final,, bathroom frame ok
|
BLD-Conference | 11/29/2010 | 11/29/2010 | 12/7/2010 | P | PART |
Tony Young
|
|
|
Mark Phone #: ###-####,, fire blocking in tall wall ok
|
BLD-Framing/Rough-in | 11/23/2010 | 11/24/2010 | 12/2/2010 | A | PART |
Tony Young
|
|
|
Mark Phone #: ###-####,, conf only on framing
|
BLD-Framing/Rough-in | 11/22/2010 | 11/22/2010 | 11/24/2010 | P | PART |
Tony Young
|
|
|
Mark Phone #: ###-####,, last of ceiling ok
|
BLD-Wall cover | 11/17/2010 | 11/18/2010 | 11/18/2010 | A | PART |
Jim Sly
|
|
|
mark Phone #: ###-#### On going Ceiling insp....OK
|
BLD-Framing/Rough-in | 11/16/2010 | 11/17/2010 | 11/17/2010 | A | PART |
Tony Young
|
|
|
mark Phone #: ###-####,, work in progress,, tune sheetrocker up on screw patterns, laps on base and face layer,, contractor is applying a 20 min rating on finished product
|
BLD-Wall cover | 11/12/2010 | 11/15/2010 | 11/15/2010 | A | PASS |
Dave Hannah
|
|
|
Mark,, ###-####,, ceiling layer first and second layers look ok beams also ok crew is about 25 % done with ceiling
|
BLD-Wall cover | 11/9/2010 | 11/10/2010 | 11/15/2010 | P | PART |
Tony Young
|
|
|
###-####,, ceiling layer,, work in progress
|
BLD-Framing/Rough-in | 11/9/2010 | 11/10/2010 | 11/12/2010 | A | PART |
Tony Young
|
|
|
###-####,, working on west side
|
BLD-Wall cover | 11/10/2010 | 11/12/2010 | 11/12/2010 | A | PART |
Tony Young
|
|
|
###-####,, 1st ceiling layer on west/north side ok
|
BLD-Framing/Rough-in | 11/8/2010 | 11/9/2010 | 11/12/2010 | P | PART |
Tony Young
|
|
|
###-####,, work in progress on draft stops,, and first layer,,
|
BLD-Framing/Rough-in | 11/3/2010 | 11/8/2010 | 11/8/2010 | A | PART |
Tony Young
|
|
|
Larry Phone #: ###-####,, hat channel,, work in progress,, I requested contractor to get a conf on mechanical and sprinkler for inspection prior to cover ceiling
|
BLD-Framing/Rough-in | 11/3/2010 | 11/3/2010 | 11/4/2010 | P | PART |
Tony Young
|
|
|
Larry Phone #: ###-####,, ok to put hat channel up on ceiling area
|
Print Occupancy Form | | | 11/2/2010 | | DONE |
|
|
|
|
Telephone call | | | 11/2/2010 | | DONE |
Barbara Stitt
|
|
|
Told Corrin permit is ready, fees due, need ACHD info & GC info on 11-2-10 @ 1:50pm
|
Permit Ready to Issue | | | 11/2/2010 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/2/2010 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 10/29/2010 | | 11/1/2010 | | DONE |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2010 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/16/2010 | | 11/1/2010 | | PASS |
Carl Westfall
|
|
|
1st review done
|
Routing - PLUMBING | 10/28/2010 | | 10/29/2010 | | PASS |
Bill VanDegrift
|
|
|
r.p. required on espresso mechine. additional cross connection protection may be required. verify grease abatement with sewer dist. prior construction.
|
Routing - FIRE | 10/27/2010 | | 10/28/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - Design Review | 10/28/2010 | | 10/28/2010 | | PASS |
Sarah Schafer
|
|
|
Approved per CZC10-00192. SMS
|
Routing - PLANNING | 10/25/2010 | | 10/27/2010 | | FAIL |
Sarah Schafer
|
|
|
New glass overhead door
I called Christophe Gougin and left a message telling him we would need a zoning certificate for the overhead door installation.
|
Routing - PLAN CHECK | 10/12/2010 | | 10/25/2010 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the resubmittal review.
|
Plan resubmittals received | | | 10/18/2010 | | DONE |
Tisha Gallop
|
|
|
received two copies of Plan Review Response 1, Plan Review Response 2, supplemental structural calculations, plan sheets Cover, A0.1, A1.0, A1.2, A2.1, A4.0; taken to Carl Westfall.
|
Routing - FIRE | 10/6/2010 | 10/6/2010 | 10/12/2010 | | FAIL |
Scott Arellano
|
|
|
Emailed resubmittal items to architect.
|
1st review completed | | | 10/12/2010 | | FAIL |
|
|
|
Failed Plumbing, Plan Check, Fire
|
Route to Impact Fee Review | 10/6/2010 | 10/11/2010 | 10/7/2010 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - PLAN CHECK | 9/21/2010 | | 10/6/2010 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on September 30, 2010 and was finished on October 6, 2010. Revised drawings were required. See the plan review report.
|
Plan resubmittals received | | | 9/30/2010 | | |
Barbara Stitt
|
|
|
Received 3 copies of sheet P1.0 & P2.0 and taken to Carl Westfall
|
Routing - PLUMBING | 9/20/2010 | | 9/21/2010 | | FAIL |
Bill VanDegrift
|
|
|
additional cross connection protection may be required. provide a plumbing plan for the cafe.
|
Routing - PUBLIC WORKS | 9/16/2010 | | 9/20/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 9/20/2010 | | 9/20/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 9/17/2010 | | 9/17/2010 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 9/15/2010 | | 9/16/2010 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 9/16/2010 | | DONE |
Jason Blais
|
|
|
Emailed architect Steve Trout. Because this project is a partial change in occupancy, Steve needs to contact ACHD for any requirements or evaluation of any impact fees. Written verification from ACHD will need to be provided to our Permit Counter prior to permit issuance.
|
Plans ACCEPTED BY PLAN TECH | | | 9/15/2010 | | DONE |
|
|
|
ok per Tim Woodard for level 3 intake
|
Application received | | 9/10/2010 | | | |
|
|
|
|