Third Notice | | 12/28/2010 | 1/4/2011 | | DONE |
|
|
|
This permit finaled on the web by Todd Kurns
|
Second Notice | | 12/18/2010 | 12/23/2010 | | DONE |
|
|
|
|
First Notice | | 11/28/2010 | 12/8/2010 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 11/18/2010 | | DONE |
|
|
|
|
Zoning Approval | 10/28/2010 | 10/28/2010 | 10/28/2010 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 10/27/2010 | 10/27/2010 | 10/27/2010 | P | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by Todd Kurns pending zoning and CDHD
|
FIRE-Final Inspection | 10/27/2010 | 10/27/2010 | 10/27/2010 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 10/25/2010 | 10/26/2010 | 10/26/2010 | P | FAIL |
Troy Cobbley
|
|
|
Need the new main exit door installed prior to sign off on life safety.
|
FIRE-Alarm Testing | 10/25/2010 | 10/26/2010 | 10/26/2010 | P | PASS |
Troy Cobbley
|
|
|
Fire alarm testing passed.
|
Case Summary (BLD) | | | 10/22/2010 | | DONE |
|
|
|
|
FIRE-Conference | 10/14/2010 | 10/15/2010 | 10/15/2010 | A | DONE |
Troy Cobbley
|
|
|
I went over emergency light/exit sign placement with Todd and Kevin.
|
BLD-Conference | 10/6/2010 | 10/6/2010 | 10/6/2010 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 9/29/2010 | 9/29/2010 | 9/29/2010 | P | PART |
Tom Arcoraci
|
|
|
Please call me when on your way. Thanks. Phone #: ###-#### >> Inspection requested via web by Todd Kurns tall walls ok
|
Issue PAID IN FULL permit | | | 9/29/2010 | | DONE |
|
|
|
|
OVERRIDE | | | 9/28/2010 | | |
|
|
|
|
Print Occupancy Form | | | 9/28/2010 | | DONE |
|
|
|
|
Telephone call | | | 9/28/2010 | | DONE |
|
|
|
left vm for james at ###-#### - permit ready and fees given - also need rp name
|
Permit Ready to Issue | | | 9/28/2010 | | DONE |
|
|
|
|
Routing - FIRE | | | 9/27/2010 | | PASS |
Tim L. Woodard
|
|
|
Field Verify
|
1st review completed | | | 9/27/2010 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 9/27/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Erosion and Sediment | 9/27/2010 | | 9/27/2010 | | PASS |
Tim L. Woodard
|
|
|
Plan Waiver approved. Applicant is to comply with all attached conditions. TLW
|
Plan assigned to (TLW) | 9/16/2010 | | 9/27/2010 | | PASS |
Tim L. Woodard
|
|
|
9/27/2010 15:41:05 TLW - activity updated through activity BLDA022 from case BLD10-02227.
|
Routing - PLAN CHECK | 9/20/2010 | | 9/27/2010 | | PASS |
Tim L. Woodard
|
|
|
approved with redline. TLW
|
Routing PW Sewer Rating | 9/20/2010 | | 9/20/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 9/16/2010 | | 9/20/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 9/17/2010 | | 9/17/2010 | | PASS |
April Wing
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/16/2010 | | DONE |
|
|
|
ok per Tim Woodard to take in as a level 2
|
Recd Pcfee & Taken To Pln CK | | | 9/16/2010 | | |
|
|
|
|
Application received | | 9/16/2010 | | | |
|
|
|
|