BLD-Final | 2/3/2011 | 2/4/2011 | 2/4/2011 | P | PASS |
Tony Young
|
|
|
corey Phone #: ###-####
|
DOC - Permit Finaled | 2/4/2011 | 2/4/2011 | 2/4/2011 | P | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 11/16/2010 | 11/17/2010 | 11/17/2010 | A | PASS |
Tony Young
|
|
|
DON Phone #: ###-####
|
BLD-Framing/Rough-in | 11/15/2010 | 11/16/2010 | 11/16/2010 | P | PASS |
Tony Young
|
|
|
DON Phone #: ###-####
|
BLD-Framing/Rough-in | 11/10/2010 | 11/12/2010 | 11/12/2010 | A | PART |
Tony Young
|
|
|
corey Phone #: ###-####,, correction notice posted on back of truss calcs,, ok to insulate,, verify seal package
|
BLD-Foundation | 9/27/2010 | 9/27/2010 | 9/28/2010 | P | PASS |
Tony Young
|
|
|
doug - around 1 if possible - coming from caldwell - needs an hour heads up Phone #: ###-####
|
BLD-Foundation | 9/23/2010 | 9/27/2010 | 9/27/2010 | A | PASS |
Tony Young
|
|
|
COREY - early afternoon please - doug at ###-#### Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 9/27/2010 | | DONE |
|
|
|
permit was showing Fee status
|
BLD-Foundation | 9/23/2010 | 9/24/2010 | 9/24/2010 | A | NR |
Tony Young
|
|
|
COREY - early afternoon please - doug at ###-#### Phone #: ###-####,, footongs ok
|
Routing Walk-In (BLD) | 9/24/2010 | 9/24/2010 | 9/24/2010 | A | DONE |
Carl D Madsen
|
|
|
9/24/2010 08:47:02 CDM - activity updated through activity BLDA022 from case BLD10-02243.
|
Case Summary (BLD) | | | 9/24/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2010 | | |
|
|
|
|
(F) Reprint permit | | | 9/24/2010 | | |
|
|
|
|
BLD-Footing | 9/22/2010 | 9/23/2010 | 9/23/2010 | P | PASS |
Tony Young
|
|
|
COREY - early afternoon please - doug at ###-#### Phone #: ###-####
|
OVERRIDE | | | 9/20/2010 | | |
|
|
|
|
Routing Walk-In (BLD) | 9/20/2010 | 9/20/2010 | 9/20/2010 | A | DONE |
Perry Paine
|
|
|
9/20/2010 12:05:17 PEP - activity updated through activity BLDA022 from case BLD10-02243.
|
Plan assigned to (PEP) | 9/20/2010 | 9/20/2010 | 9/20/2010 | | PASS |
Perry Paine
|
|
|
9/20/2010 12:05:17 PEP - activity updated through activity BLDA022 from case BLD10-02243.
|
Plan assigned to (PEP) | 9/17/2010 | 9/17/2010 | 9/20/2010 | | PASS |
Perry Paine
|
|
|
9/20/2010 12:05:17 PEP - activity updated through activity BLDA022 from case BLD10-02243.
|
1st review completed | | | 9/20/2010 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/20/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/20/2010 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 9/20/2010 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/20/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/20/2010 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/20/2010 | | DONE |
Tisha Gallop
|
|
|
|
Routing Walk-In (Zoning) | 9/17/2010 | 9/17/2010 | 9/17/2010 | P | PASS |
Joan Johnson
|
|
|
New driveway access must be paved. Total width of existing and new driveway must not exceed 33 feet.
|
Routing Walk-In (BLD) | 9/17/2010 | 9/17/2010 | 9/17/2010 | P | FAIL |
Perry Paine
|
|
|
need more information
|
Application received | | 9/17/2010 | | | |
|
|
|
|