BLD-Final | 4/26/2011 | 4/26/2011 | 4/26/2011 | P | PASS |
Mike Jordan
|
|
|
Hey Mike, please call 1/2 hr before. also if you have time can we look at our new units.
thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
DOC - Permit Finaled | 4/26/2011 | 4/26/2011 | 4/26/2011 | P | PASS |
Mike Jordan
|
|
|
Residential certificate of occupancy was issued.
|
BLD-Aging Inspection | 2/21/2011 | 2/21/2011 | 2/22/2011 | | PASS |
Mike Jordan
|
|
|
work in progress.
|
BLD-Energy code compliance | 12/20/2010 | 12/20/2010 | 12/20/2010 | A | PASS |
Mike Jordan
|
|
|
please call 1 hour before Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Framing/Rough-in | 12/16/2010 | 12/16/2010 | 12/16/2010 | P | PASS |
Mike Jordan
|
|
|
please call 1 hour before. thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Footing | 11/16/2010 | 11/16/2010 | 11/16/2010 | P | DONE |
Mike Jordan
|
|
|
Footing in slab work. Will be ready this morning, if you are in the area can you please stop by. thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin. CVoncrete already placed when on site.
|
BLD-Foundation | 11/8/2010 | 11/9/2010 | 11/9/2010 | A | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 11/8/2010 | 11/8/2010 | 11/8/2010 | P | PART |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/8/2010 | | |
|
|
|
|
Plan assigned to (CDM) | 9/22/2010 | 9/22/2010 | 11/4/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - Addressing | 9/22/2010 | | 11/4/2010 | | PASS |
Carl D Madsen
|
|
|
Signed off per publick works sheet by Terry Records
|
Routing - PLAN CHECK | 9/24/2010 | | 11/4/2010 | | PASS |
Carl D Madsen
|
|
|
Do not issue until 10/4/10, per CUP appeal period.
|
Routing - PLAN CHECK | 11/3/2010 | | 11/4/2010 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/4/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/4/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/4/2010 | | DONE |
|
|
|
|
Telephone call | | | 11/4/2010 | | DONE |
|
|
|
11-4-10 called left message permit ready and fee given ///dld
|
Routing - PLANNING | 11/3/2010 | | 11/3/2010 | | PASS |
Cody Riddle
|
|
|
Okay per CUP modification.
|
Route to Impact Fee Review | 9/21/2010 | 9/24/2010 | 10/19/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 10/18/2010 | | 10/18/2010 | | FAIL |
Cody Riddle
|
|
|
Three story units were only allowed on lots 104-107. Emailed applicant at 9:00 this morning. An additional modification will be required. CER
|
Plan resubmittals received | | | 10/15/2010 | | DONE |
Tisha Gallop
|
|
|
received revised building permit application, revised esc application, two copies of new ResCheck, two 8 1/2" x 11" site plan, two revised full set of plans; taken to Carl Madsen.
|
1st review completed | | | 10/14/2010 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/14/2010 | | DONE |
|
|
|
|
Telephone call | | | 10/14/2010 | | DONE |
|
|
|
Jim with Paradigm Construction called and switched the dwelling to a new lot and is bringing in a new site plan and cover sheet. CDM
|
Plan resubmittals received | | | 10/4/2010 | | DONE |
Tisha Gallop
|
|
|
received two copies ResCheck, two revised full set of plans, one copy structural calcs; taken to Carl Madsen.
|
Routing - PUBLIC WORKS | 9/23/2010 | | 9/24/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 9/24/2010 | | 9/24/2010 | | PASS |
Cody Riddle
|
|
|
Plans comply with CUP requirements. However, the appeal period on the recent modification does not expire until 10/4/10.
Do not issue permit until 10-4-10
CER
|
Intake Approval | | | 9/22/2010 | | PASS |
|
|
|
|
Application received | | 9/21/2010 | | | |
|
|
|
|