BLD-Final | 2/24/2011 | 2/25/2011 | 2/25/2011 | A | PASS |
Dave Hannah
|
|
|
keypad code is 1968. please call Sam with questions, ###-####.
thanks Phone #: ###-#### >> Inspection requested via web by Tony Luchini
|
DOC - Permit Finaled | 2/25/2011 | 2/25/2011 | 2/25/2011 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 1/6/2011 | 1/7/2011 | 1/7/2011 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Tony Luchini
|
BLD-Framing/Rough-in | 1/4/2011 | 1/5/2011 | 1/5/2011 | P | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Tony Luchini c/n on site ok to insulate
|
BLD-Aging Inspection | 12/30/2010 | 12/30/2010 | 1/3/2011 | | PASS |
Dave Hannah
|
|
|
|
BLD-Foundation | 10/21/2010 | 10/25/2010 | 10/25/2010 | P | PART |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 10/21/2010 | 10/22/2010 | 10/22/2010 | A | PASS |
Tom Arcoraci
|
|
|
Bill Phone #: ###-####
|
OVERRIDE | | | 10/15/2010 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/15/2010 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 10/15/2010 | | DONE |
|
|
|
left vm for leonard at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/15/2010 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/24/2010 | 9/29/2010 | 10/12/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (CDM) | 9/27/2010 | 9/27/2010 | 10/12/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/28/2010 | | 10/12/2010 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 10/12/2010 | | 10/12/2010 | | PASS |
Joshua Johnson
|
|
|
Cannot Issue until 10-14-10 at 5PM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/12/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/12/2010 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/11/2010 | | DONE |
|
|
|
|
1st review completed | | | 10/11/2010 | | FAIL |
|
|
|
Fail per planning sign off of variance
|
Routing - Addressing | 9/27/2010 | | 9/28/2010 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | | | 9/28/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 9/27/2010 | | PASS |
|
|
|
|
Application received | | 9/24/2010 | | | |
|
|
|
|
Routing - PLANNING | 9/28/2010 | | | | FAIL |
|
|
|
Required variance is in process.
|
Routing - PLANNING | 10/11/2010 | | | | |
Joshua Johnson
|
|
|
|