BLD-Final | 3/26/2012 | 3/27/2012 | 3/27/2012 | A | PASS |
Jim Sly
|
|
|
chris Phone #: ###-#### C/C issued
|
DOC - Permit Finaled | 3/27/2012 | 3/27/2012 | 3/27/2012 | P | PASS |
Jim Sly
|
|
|
|
BLD-Aging Inspection | 4/14/2011 | 6/20/2011 | 6/21/2011 | A | PASS |
Mike Jordan
|
|
|
Spoke with builder, should have final by end of week or beginning of next week.
|
BLD-Aging Inspection | 4/12/2011 | 4/12/2011 | 4/14/2011 | | CANC |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 2/8/2011 | 2/8/2011 | 2/8/2011 | | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 12/8/2010 | 12/9/2010 | 12/9/2010 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 12/6/2010 | 12/7/2010 | 12/7/2010 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. All framing issues have been resolved. Airseal completed and exterior house wrap being installed when on site. ok to insulate.
|
BLD-Framing/Rough-in | 12/3/2010 | 12/6/2010 | 12/6/2010 | A | FAIL |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Needs to provide an exterior weather membrane wrap, Complete airseal package, install lateral bracing on F5 trusses, and mecanical connection on CG truss. Correction notice posted. needs to call additional inspection for airseal prior to insulating.
|
BLD-Foundation | 10/20/2010 | 10/20/2010 | 10/20/2010 | P | PASS |
Mike Jordan
|
|
|
dane Phone #: ###-####
|
BLD-Footing | 10/18/2010 | 10/19/2010 | 10/19/2010 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/18/2010 | | DONE |
|
|
|
|
OVERRIDE | | | 10/13/2010 | | |
|
|
|
|
Plan assigned to (CDM) | 9/29/2010 | 9/29/2010 | 10/13/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 10/1/2010 | | 10/13/2010 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 10/13/2010 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/13/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/13/2010 | | DONE |
|
|
|
|
Telephone call | | | 10/13/2010 | | DONE |
|
|
|
left vm for chris at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/13/2010 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/28/2010 | 10/1/2010 | 10/7/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 9/30/2010 | | 10/1/2010 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 9/29/2010 | | 9/30/2010 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | | | 9/30/2010 | | PASS |
|
|
|
|
Intake Approval | | | 9/29/2010 | | PASS |
|
|
|
|
Intake Approval | | | 9/28/2010 | | FAIL |
|
|
|
plan was missing page 5 (electrical)
|
Application received | | 9/28/2010 | | | |
|
|
|
|