Permit Information
Permit NumberBLD10-02356
StatusFinaled
Name VERTICAL CORP
Site Address 2900 W MAIN ST
Project NameEBERLESTOCK USA
Customer Number 
ePlanReviewNo
Description
(EBERLESTOCK USA) New office/warehouse tenant in 13,150 sq. ft. cold shell building constructed under BLD10-01086. Work to include: [construction of interior non-bearing walls to create four office areas on the second floor, two office areas on the first flor,] installation of separate sex single user restrooms, installation of a new elevator, installation of three stairways, installation of new windows and insulation, installation of new mechanical system, installation of new lighting, and finishes in compliance with chapter 8 of the 2006 IBC. Planning approval done under CUP10-00003 and DRH10-00085. NOTE: This building is fully fire sprinklered. Racking that exceeds 8 ft. in height requires a separate Building Permit be submitted and approved before installation. PLAN MODIFICATION 3-18-2011 – Modification submitted to change submitted elevator (non-rated) shaft to a open metal frame enclosure around elevator.**TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 7/3/201110/10/2011 DONE
Second Notice 6/23/20116/28/2011 DONE
First Notice 6/10/20116/13/2011 DONE
DetailsChristina Prado
Faxed 6-13-11
BLD-Final5/31/20115/31/20115/31/2011PPASS
DetailsDave Hannah
Dave Kelly Phone #: ###-#### ok for perm occ
Override - People Holds  5/31/2011  
Permanent Occupancy  5/31/2011 DONE
DetailsBarbara Stitt
BLD-Final5/5/20115/5/20115/5/2011PPART
DetailsDave Hannah
Dave Phone #: ###-#### ok for temp occ ok for perm occ after zoning oks for perm occ
Zoning Approval Temp5/3/20115/3/20115/3/2011 DONE
DetailsJosh Wilson
30 Temp for installation of mechanical screening
BLD-Final4/26/20114/26/20114/26/2011PNR
DetailsDave Hannah
Dave Kelly Phone #: ###-####
FIRE-Final Inspection4/25/20114/25/20114/26/2011PPASS
DetailsForrest France
Fire life safety finaled.
FIRE-Final Inspection4/22/20114/22/20114/22/2011PFAIL
DetailsForrest France
Everything passed life safety except fire panel was not green. Fire panel indicated two trouble conditions.
Remote anunciator was removed and smoke detector was installed at the proper location.

dave Phone #: ###-####
BLD-Framing/Rough-in4/13/20114/14/20114/14/2011APASS
DetailsDave Hannah
Dave-Elevator Shaft Phone #: ###-####
BLD-Aging Inspection4/13/20114/13/20114/14/2011 PASS
DetailsDave Hannah
CHANGE STATUS TO (ISS)  4/11/2011 DONE
DetailsTisha Gallop
approved plan mod paid for and picked up by contractor.
OVERRIDE  3/18/2011  
Telephone call  3/18/2011 DONE
DetailsBarbara Stitt
Called Ward and told him that permit is ready and fees due on 3-18-11 @ 12:05pm//BAS
Routing - PLAN CHECK3/18/2011 3/18/2011 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  3/18/2011 DONE
DetailsTim L. Woodard
Case Summary (BLD)  3/18/2011 DONE
DetailsTim L. Woodard
Print Occupancy Form  3/18/2011 DONE
Permit Ready to Issue  3/18/2011 DONE
DetailsBarbara Stitt
Plan assigned to (TLW)2/9/2011 3/18/2011 PASS
DetailsTim L. Woodard
Plan resubmittals received  3/8/2011 DONE
DetailsTisha Gallop
received three copies of response and plan sheet A5.0B; taken to Tim Woodard.
Routing Off Site - STRUCTURAL2/10/2011 2/25/2011 FAIL
DetailsTim L. Woodard
2-10-11 called Action Couriers for pick up
Routing - PLAN CHECK2/9/2011 2/10/2011 PEND
DetailsTim L. Woodard
All structural. Sent to outsource engineer. TLW
Plan Modification Accepted  2/9/2011 DONE
DetailsTisha Gallop
Plan Modification accepted for Bld10-02356 (Eberlestock USA - TI) to change to steel cage/wire cage elevator enclosure in lieu of one shaft walls; submitted on plan sheet A5.0 and Stuctural Calcs; routed to Tim Woodard.
BLD-Framing/Rough-in1/25/20111/26/20111/26/2011APASS
DetailsJim Storey
dave Phone #: ###-#### engineering straps instaled 2nd floor bearing wal/ a35 and mlb instaled above sheer wall. ok to cover. design copies on site for 425.
BLD-Framing/Rough-in1/20/20111/20/20111/20/2011PPART
DetailsJim Storey
dave Phone #: ###-#### engineer cut sheet addressed mez. deck/ Fc of mlb spacing exterior/--- need to addresss east roof to bearing wall conection/ top of sheer wall at 1st floor bathroom for atchment and duct penatration. ok to cover 2nd floor and 1st floor east end of shell.
FIRE-Conference1/5/20111/5/20111/5/2011PDONE
DetailsForrest France
Discussion with contractor regarding emergency lighting requirements.
Print Occupancy Form  12/27/2010 DONE
Permit Ready to Issue  12/27/2010 DONE
DetailsTisha Gallop
Telephone call  12/27/2010 DONE
DetailsTisha Gallop
called Todd/Vertical Corp and told him permit is ready and fees.
Issue PAID IN FULL permit  12/27/2010 DONE
DetailsTisha Gallop
Routing Off Site - STRUCTURAL12/20/2010 12/23/2010 PASS
DetailsTim L. Woodard
Recieved email from outsource. Ok to issue all issues addressed. 12-20-10 called Action Couriers for pick up
Routing - PLAN CHECK12/23/2010 12/23/2010 PASS
DetailsTim L. Woodard
Approved with attached plan review report.
PLANS/APPL TAKEN TO FRONT DESK  12/23/2010 DONE
DetailsTim L. Woodard
Case Summary (BLD)  12/23/2010 DONE
DetailsTim L. Woodard
Plan assigned to (TLW)10/18/2010 12/23/2010 PASS
DetailsTim L. Woodard
Plan resubmittals received  12/17/2010 DONE
DetailsTisha Gallop
received three copies of response from engineer, structural calcs and plan sheet A5.0; taken to Tim Woodard.
Routing Off Site - STRUCTURAL12/7/2010 12/15/2010 FAIL
DetailsBarbara Stitt
Sent corrections off to architect and engineer. Called Action Courier for pick up 12-7-10 @ 2:30pm
Routing - PLAN CHECK11/18/2010 12/8/2010 FAIL
DetailsTim L. Woodard
Need further information on assembly requested. TLW Sent new plan review report to Ward.
Plan resubmittals received  11/29/2010 DONE
DetailsChristina Prado
RECIEVED 2 COPIES OF A2.1, A2.2, A5.0, M-1, M-2, M-3, STRUCTUAL CALCS AND REVIEW SHEET
Route to Impact Fee Review11/15/201011/18/201011/18/2010 PASS
DetailsCindy M. Gould
Tenant improvement
Routing - FIRE11/15/201011/15/201011/18/2010 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  11/18/2010 FAIL
Failed Plan Check
Routing - PLAN CHECK10/27/2010 11/15/2010 FAIL
DetailsTim L. Woodard
Refer to plan review report. TLW
Routing - PLANNING10/26/2010 10/27/2010 PASS
DetailsDavid Moser
David Moser - CUP10-00003 Josh Wilson- DRH10-00085
Routing - PLUMBING10/20/2010 10/26/2010 PASS
DetailsBill VanDegrift
if a sump pump is required in the elevator pit by the state elevator inspector a resubmitted plan will be required.
Routing - PUBLIC WORKS10/18/2010 10/20/2010 PASS
DetailsConnie Baumgartner
Routing - Addressing10/20/2010 10/20/2010 PASS
DetailsTerry Records
Routing PW Sewer Design10/20/2010 10/20/2010 PASS
DetailsConnie Baumgartner
Application received 9/30/201010/18/2010 DONE
DetailsBarbara Stitt
Recd Pcfee & Taken To Pln CK  10/18/2010 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  10/18/2010 DONE
DetailsBarbara Stitt
Pending Assignment by JCB10/18/2010 10/18/2010 DONE
DetailsJason Blais
Intake Approval  10/18/2010 PASS
DetailsTim L. Woodard
Approved intake.