CDHD Occupancy Approval | 8/29/2011 | 8/29/2011 | 8/29/2011 | | DONE |
Barbara Stitt
|
|
|
Approved on 2-24-11 by Bud with Central Dist Health per Phone call
|
Permanent Occupancy | | | 8/29/2011 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 8/26/2011 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Aging Inspection | 3/14/2011 | 3/14/2011 | 3/14/2011 | | PART |
Tom Arcoraci
|
|
|
|
BLD-Final | 1/10/2011 | 1/11/2011 | 1/11/2011 | A | PASS |
Tom Arcoraci
|
|
|
call when on way//Dalia Phone #: ###-####
|
FIRE-Final Inspection | 1/5/2011 | 1/5/2011 | 1/5/2011 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 1/4/2011 | 1/4/2011 | 1/4/2011 | P | FAIL |
Troy Cobbley
|
|
|
Remove the dead bolt and door knob at the kitchen exit. Provide the correct occupant load sign. Provide revised floor plans to the building plan reviewer.
|
Routing - PLAN CHECK | 1/4/2011 | | 1/4/2011 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/4/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 1/4/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 1/4/2011 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 1/4/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (TLW) | 9/30/2010 | | 1/4/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Permit Ready to Issue | | | 1/4/2011 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/4/2011 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 12/30/2010 | | 12/30/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 12/30/2010 | | 12/30/2010 | | PASS |
Walt Baumgartner
|
|
|
Project approved, new grease interceptor installed and inspected.
|
1st review completed | | | 10/6/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 10/4/2010 | | 10/6/2010 | | FAIL |
Tim L. Woodard
|
|
|
Walt has discussed this project with Bench Sewer District and agreed to not signoff any occupancy until grease trap was permitted. TLW
|
Routing - PUBLIC WORKS | 9/30/2010 | | 10/4/2010 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 10/4/2010 | | 10/4/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 10/4/2010 | | 10/4/2010 | | FAIL |
Walt Baumgartner
|
|
|
Bench Sewer District is requiring a new in ground grease interceptor installation. Contact Rick ###-#### for more information.
|
Routing - Addressing | 10/1/2010 | | 10/1/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 9/30/2010 | 9/30/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/30/2010 | | DONE |
Tisha Gallop
|
|
|
|