First Notice | 8/1/2012 | 8/1/2012 | 8/23/2012 | | DONE |
Jim Storey
|
|
|
old
|
DOC - Permit Finaled | 8/1/2012 | 8/1/2012 | 8/1/2012 | P | PASS |
Jim Storey
|
|
|
|
Zoning Approval | 4/24/2012 | 4/24/2012 | 4/24/2012 | | PASS |
Josh Wilson
|
|
|
Ok with Arborviate substitute for Skyrocket Juniper due to fire hazard. JGW 4-24-12
|
Telephone call | | | 4/20/2012 | | DONE |
|
|
|
Spoke with Kevin (###-####) about substituting Arborvitae for the specified Junipers in same size. OK JGW 4-20-12
|
PubWorks Occupancy Approval | 5/12/2011 | 5/12/2011 | 5/12/2011 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Aging Inspection | 5/2/2011 | 5/2/2011 | 5/2/2011 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 3/2/2011 | 3/2/2011 | 3/2/2011 | | PASS |
Tom Arcoraci
|
|
|
|
Issue & PRINT permit | | | 12/1/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/16/2010 | | DONE |
Tisha Gallop
|
|
|
received e-mailed document of State of Idaho Plan Approval for the modular building; forwarded to John Menard. Printed paper copy and attached to issue set of plans.
|
Telephone call | | | 11/4/2010 | | DONE |
Tisha Gallop
|
|
|
called John Banks again and left voice message permit is ready, fees, need ACHD, GC, RCE/T, RP.
|
Plan assigned to (JCM) | 10/4/2010 | 10/4/2010 | 10/29/2010 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 10/18/2010 | | 10/29/2010 | | PASS |
John Menard
|
|
|
Approved with a deferred submittal of the state of Idaho modular building approval. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/29/2010 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 10/29/2010 | | DONE |
Tisha Gallop
|
|
|
|
Override - Parcel Holds | | | 10/29/2010 | | |
|
|
|
|
Permit Ready to Issue | | | 10/29/2010 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 10/29/2010 | | DONE |
Tisha Gallop
|
|
|
called John Banks and left voicemail that permit is ready, fees, need ACHD, GC, RCE/T, RP.
|
Routing - PUBLIC WORKS | 10/15/2010 | | 10/18/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 10/15/2010 | | 10/18/2010 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 10/12/2010 | | 10/15/2010 | | |
John Menard
|
|
|
|
Plan resubmittals received | | | 10/13/2010 | | |
Barbara Stitt
|
|
|
Received 5 copies of sheet GRD inserted into plans by Briggs Engineering
|
1st review completed | | | 10/12/2010 | | FAIL |
|
|
|
Failed Public Works, Plan Check
|
Routing - FIRE | 10/8/2010 | | 10/12/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 10/7/2010 | | 10/8/2010 | | FAIL |
John Menard
|
|
|
John Menard
|
Plan Reviewer's activity | | | 10/8/2010 | | FAIL |
John Menard
|
|
|
Can approve after verification of state modular building approval. JCM
|
Plan resubmittals requested | | | 10/8/2010 | | DONE |
John Menard
|
|
|
Emailed the architect and requested a copy of the modular building State of Idaho approval. JCM
|
Routing - Erosion and Sediment | 10/6/2010 | | 10/7/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and ESC permit conditions. ESC10-00764
|
Routing - PLANNING | 10/7/2010 | | 10/7/2010 | | PASS |
Josh Wilson
|
|
|
CZC10-00088 Josh Wilson
|
Routing - PUBLIC WORKS | 10/1/2010 | | 10/6/2010 | | FAIL |
Beverly Mountain
|
|
|
Brian Murphy failed
|
Routing PW Drainage | 10/4/2010 | | 10/6/2010 | | FAIL |
Brian Murphy
|
|
|
NEEDS REVISION AND O AND M. BRIAN MURPHY ###-####
|
Routing PW Sewer Rating | 10/4/2010 | | 10/4/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCM | 10/1/2010 | | 10/4/2010 | | DONE |
John Menard
|
|
|
|
Intake Approval | | | 10/2/2010 | | PASS |
|
|
|
|
Application received | | 10/1/2010 | 10/1/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/1/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/1/2010 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLANNING Land Div | 10/1/2010 | | 10/1/2010 | | PASS |
Dave Abo
|
|
|
Parcel 1 on ROS 4897.
|
Routing - Addressing | 10/1/2010 | | 10/1/2010 | | PASS |
April Wing
|
|
|
|