First Notice | 4/18/2013 | 4/18/2013 | 4/22/2013 | | DONE |
Tom Arcoraci
|
|
|
old permit
|
BLD-Aging Inspection | 4/18/2013 | 4/18/2013 | 4/18/2013 | | DONE |
Tom Arcoraci
|
|
|
|
DOC - Permit Finaled | 4/18/2013 | 4/18/2013 | 4/18/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 1/17/2013 | 1/17/2013 | 1/17/2013 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 10/18/2012 | 10/18/2012 | 10/18/2012 | | PASS |
Tom Arcoraci
|
|
|
|
Issue PAID IN FULL permit | | | 8/17/2011 | | DONE |
Christina Prado
|
|
|
|
Received Certificate of Value | | | 6/1/2011 | | DONE |
Barbara Stitt
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/1/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 6/1/2011 | | DONE |
Barbara Stitt
|
|
|
Called Jason with Morgan Construction and told him that permit is ready, fees due, need RCE #, & RP on 6-1-11 @ 10:00am
|
Permit Ready to Issue | | | 6/1/2011 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 4/27/2011 | | 6/1/2011 | | PASS |
Barbara Stitt
|
|
|
|
Routing - PUBLIC WORKS | 4/27/2011 | | 4/27/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Design | 4/27/2011 | | 4/27/2011 | | PASS |
Javier Guzman
|
|
|
Recieved easement for sanitary sewer service line
|
Routing - PUBLIC WORKS | 4/6/2011 | | 4/7/2011 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Jon Gunerson in sewer design
|
Routing - Erosion and Sediment | 4/7/2011 | | 4/7/2011 | | PASS |
Steven Webb
|
|
|
ESC plan was passed on 3/30/11 according to the ESC plan and ESC permit conditions.
|
Routing PW Sewer Design | 4/6/2011 | | 4/7/2011 | | FAIL |
Jon R. Gunnerson
|
|
|
Need sanitary sewer easement
|
Routing PW Street Lights | 4/6/2011 | | 4/6/2011 | | PASS |
Hank Alarcon
|
|
|
Plans passed per Mike and Rob Bousfield. 4-6-11
|
Plan resubmittals received | | | 4/5/2011 | | |
Barbara Stitt
|
|
|
Received 2 copies of 1 of 5, 2 of 5 and 4 of 5 and inserted into plans
|
Telephone call | | | 4/1/2011 | | DONE |
Barbara Stitt
|
|
|
Called and left a voice message for John Carpenter regarding what failed and was needed for resubmittals on 4-1-11 @ 11:05am
|
Routing - FIRE | 3/30/2011 | | 4/1/2011 | | PASS |
Scott Arellano
|
|
|
No Fire Review comments attached.
|
Routing - PLANNING | 3/30/2011 | | 3/30/2011 | | PASS |
David Moser
|
|
|
CUP10-00067 David Moser
DRH10-00243 Andrea Tuning
|
Routing - Erosion and Sediment | 3/30/2011 | | 3/30/2011 | | FAIL |
Steven Webb
|
|
|
Full size drawing are needed in a re-submittal.
|
Routing - PUBLIC WORKS | 3/23/2011 | | 3/29/2011 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Jon Gunnerson in Sewer Design
|
Routing PW Drainage | 3/28/2011 | | 3/29/2011 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Design | 3/29/2011 | | 3/29/2011 | | FAIL |
Jon R. Gunnerson
|
|
|
Engineer to provide easement by seperate document for service line and adjust service line grade to 2 percent.
|
Routing - Addressing | 3/25/2011 | | 3/25/2011 | | PASS |
April Wing
|
|
|
|
Routing - Addressing | 3/25/2011 | | 3/25/2011 | | PASS |
April Wing
|
|
|
|
Plan resubmittals received | | | 3/23/2011 | | DONE |
Tisha Gallop
|
|
|
received five copies of plan sheets 1, 2, 3, 4 (ESC plan), 5 and ESC Narrative; inserted into plans by LEG. Need to reroute to PW, Planning, Fire, and ESC. Routed to PW
|
Routing - PLAN CHECK | 10/25/2010 | | 3/23/2011 | | PEND |
Barbara Stitt
|
|
|
BARB STITT; received full new set of plans on 3/23/11 due to ACHD's requirements they had to move the project because it was on an easment. Route to PW, Planning, Fire, ESC.
|
Telephone call | | | 2/16/2011 | | DONE |
Barbara Stitt
|
|
|
Phone call from John Carpenter- they are going to resubmit due to changes required from ACHD- he also left a message for Brian Murphy a message regarding this information. Still wants this permit.
|
Telephone call | | | 1/21/2011 | | DONE |
Barbara Stitt
|
|
|
Spoke with John Carpenter he will or should be sending resubmitals mon or tues on next//1-21-11 @ 3:20pm
|
Telephone call | | | 11/24/2010 | | DONE |
Barbara Stitt
|
|
|
Spoke with John Carpenter told him what still needs to be resubmitted for plan approvals
|
Routing - PLANNING | 10/26/2010 | | 10/26/2010 | | PASS |
David Moser
|
|
|
CUP10-00027-David Moser
|
Routing - FIRE | 10/22/2010 | | 10/25/2010 | | PASS |
Scott Arellano
|
|
|
No Fire Review comments attached.
|
1st review completed | | | 10/25/2010 | | FAIL |
|
|
|
Failed Public Works, Erosion & Soil Control
|
Routing - PLANNING | 10/22/2010 | | 10/22/2010 | | PASS |
Andrea Tuning
|
|
|
DRH10-00091-Andrea Tunning
|
Routing - PLUMBING | 10/19/2010 | | 10/22/2010 | | PASS |
Bill VanDegrift
|
|
|
no plumbing
|
Routing PW Street Lights | 10/20/2010 | | 10/21/2010 | | PASS |
Hank Alarcon
|
|
|
Called John Carpenter advised will have to resubmit plans with notes that call for Boise city street lights to IWCP requirement.
|
Routing - Erosion and Sediment | 10/18/2010 | | 10/19/2010 | | FAIL |
Steven Webb
|
|
|
ESC plan (narrative and blueprint) was not included in the routed package to the ESC Workgroup, no review could be performed. Refer to ESC activity for further details, ESC10-00778.
|
Routing PW Sewer Design | 10/15/2010 | | 10/18/2010 | | FAIL |
Jon R. Gunnerson
|
|
|
Adjust sanitary sewer manhole to match roadway grade.
|
Routing PW Street Lights | 10/18/2010 | | 10/18/2010 | | FAIL |
Hank Alarcon
|
|
|
Contact Hank Alarcon at ###-####
|
Routing PW Flood Plain | 10/18/2010 | | 10/18/2010 | | PASS |
Jim Wyllie
|
|
|
|
Routing - PUBLIC WORKS | 10/7/2010 | | 10/18/2010 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 10/11/2010 | | 10/15/2010 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals received | | | 10/14/2010 | | DONE |
Tisha Gallop
|
|
|
received five copies of plan sheets 1 & 3; inserted by engineer rep. and taken back to Brian Murphy
|
Routing - PLANNING Land Div | 10/6/2010 | | 10/7/2010 | | PASS |
Todd Tucker
|
|
|
|
Application received | | 10/6/2010 | 10/6/2010 | | DONE |
Barbara Stitt
|
|
|
Application and plans were recieved from Brian Murphy. They were originally droped off for him somewhere in Public Works. And were just now brought over to our office for submital without a check for submital fees.
|
Plans ACCEPTED BY PLAN TECH | | | 10/6/2010 | | DONE |
Barbara Stitt
|
|
|
Per Brian Murphy we allowed to come in without the cert of value as they are still working on this//10-6-10 BAS
|
Intake Approval | | | 10/6/2010 | | PASS |
Barbara Stitt
|
|
|
Per Brian Murphy we allowed to come in without the cert of value as they are still working on this//10-6-10 BAS
|
Plan assigned to (B_S) Barb | 10/6/2010 | | | | |
Barbara Stitt
|
|
|
|