First Notice | | 2/21/2011 | 3/3/2011 | | DONE |
|
|
|
|
BLD-Final | 2/11/2011 | 2/11/2011 | 2/11/2011 | A | PASS |
Jim Storey
|
|
|
Please call 1/2 hour prior, thanks! Phone #: ###-#### >> Inspection requested via web by Darren Gossett
|
Permanent Occupancy UNPAID FEE | | | 2/11/2011 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/9/2011 | 2/10/2011 | 2/10/2011 | P | PASS |
Forrest France
|
|
|
Fire life safety passed. Note: door hardware at the reception desk to be reversed for compliance with egress req.- prior to structrual inspection.
|
FIRE-Conference | 2/4/2011 | 2/5/2011 | 2/4/2011 | P | DONE |
Forrest France
|
|
|
Regarding project finish schedule.
|
FIRE-Conference | 1/11/2011 | 1/12/2011 | 1/12/2011 | A | DONE |
Forrest France
|
|
|
Regarding copy of notice on site -Maintain ceiling at the existing tenant space where modified to accomodate new wall construction. Required fire protection systems to be maintained per IFC 2006 901.4 and meet installation guidelines per NFPA 13 2007 8.1(3) regarding activation time, distribution, and area separation.
|
BLD-Other | 1/11/2011 | 1/12/2011 | 1/12/2011 | A | PASS |
Jim Storey
|
|
|
Please call 1/2 hour prior to arrival, thanks! Phone #: ###-#### >> Inspection requested via web by Darren Gossett ceilling ok for cover.
|
FIRE-Conference | 12/1/2010 | 12/2/2010 | 12/6/2010 | A | DONE |
Forrest France
|
|
|
Site visit regarding door hardware at the east side exit path.
|
BLD-Framing/Rough-in | 12/2/2010 | 12/3/2010 | 12/3/2010 | A | PASS |
Jim Storey
|
|
|
Darren Phone #: ###-####
|
BLD-Framing/Rough-in | 12/2/2010 | 12/2/2010 | 12/2/2010 | P | NR |
Jim Storey
|
|
|
Darren Phone #: ###-####
|
BLD-Framing/Rough-in | 12/1/2010 | 12/2/2010 | 12/2/2010 | A | NR |
Jim Storey
|
|
|
Darren Phone #: ###-#### fire stop/ plm insp.
|
FIRE-Conference | 11/30/2010 | 12/1/2010 | 12/1/2010 | A | CANC |
Forrest France
|
|
|
Please call 1/2 hour prior upon arrival, thanks. Phone #: ###-#### >> Inspection requested via web by Darren Gossett Inspection cancelled from web by: Darren Gossett
|
Issue PAID IN FULL permit | | | 11/12/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/9/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/9/2010 | | DONE |
|
|
|
|
Telephone call | | | 11/9/2010 | | DONE |
|
|
|
left vm for jeff - permit ready and fees given
|
Permit Ready to Issue | | | 11/9/2010 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 10/15/2010 | | 11/8/2010 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 11/5/2010 | | 11/8/2010 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2010 | | DONE |
Sam Zahorka
|
|
|
|
Routing - FIRE | 11/2/2010 | | 11/5/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 11/5/2010 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 11/1/2010 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 10/21/2010 | | 11/1/2010 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PUBLIC WORKS | 10/15/2010 | | 10/21/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 10/21/2010 | | 10/21/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 10/20/2010 | | 10/20/2010 | | PASS |
Terry Records
|
|
|
|
Pending Assignment by JCB | 10/14/2010 | | 10/15/2010 | | DONE |
Jason Blais
|
|
|
|
Application received | | 10/14/2010 | 10/14/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 10/14/2010 | | PASS |
|
|
|
OK to submit
|
Plans ACCEPTED BY PLAN TECH | | | 10/14/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/14/2010 | | DONE |
Tisha Gallop
|
|
|
|