First Notice | | 2/18/2011 | 3/3/2011 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/8/2011 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 1/27/2011 | 1/28/2011 | 1/28/2011 | A | PASS |
Tom Arcoraci
|
|
|
Please call 30 min in advance Thanks junior Phone #: ###-#### >> Inspection requested via web by Les Seal
|
Zoning Approval | 1/28/2011 | 1/28/2011 | 1/28/2011 | | DONE |
Sarah Schafer
|
|
|
|
FIRE-Final Inspection | 1/25/2011 | 1/26/2011 | 1/26/2011 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 1/21/2011 | 1/24/2011 | 1/24/2011 | A | FAIL |
Troy Cobbley
|
|
|
Provide final for the project related fire sprinkler permit and repair all of the exit signs and emergency lights.
|
BLD-Other | 1/4/2011 | 1/5/2011 | 1/5/2011 | P | PASS |
Tom Arcoraci
|
|
|
junior - grid inspection Phone #: ###-####
|
BLD-Wall cover | 12/21/2010 | 12/21/2010 | 12/21/2010 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 12/20/2010 | 12/20/2010 | 12/20/2010 | P | PASS |
Tom Arcoraci
|
|
|
junior Phone #: ###-####
|
OVERRIDE | | | 12/1/2010 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/1/2010 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 12/1/2010 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 11/22/2010 | | 12/1/2010 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/1/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 12/1/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Erosion and Sediment | 12/1/2010 | | 12/1/2010 | | PASS |
Tim L. Woodard
|
|
|
Waiver approved... Applicant must comply with attached conditions. TLW
|
Print Occupancy Form | | | 12/1/2010 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 12/1/2010 | | DONE |
Barbara Stitt
|
|
|
Left message for Doug Bagley that permit is ready, fees due and that we need a revised cert of value to reflect a MEC value due to the installation of new mechanical system throughout the warehouse and new customer service area on 12-1-10 @ 3:20pm
|
Permit Ready to Issue | | | 12/1/2010 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (TLW) | 11/2/2010 | | 12/1/2010 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 11/18/2010 | | 11/22/2010 | | PASS |
Scott Arellano
|
|
|
Attached updated IFC comments to plans
|
Routing - PLAN CHECK | 11/16/2010 | | 11/18/2010 | | PASS |
Tim L. Woodard
|
|
|
approved with redlines and plan review report comments. TLW
|
1st review completed | | | 11/16/2010 | | FAIL |
|
|
|
Failed Plan Check, Fire
|
Routing - FIRE | 11/8/2010 | | 11/16/2010 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
Plan resubmittals received | | | 11/12/2010 | | DONE |
Tisha Gallop
|
|
|
received one copy response letter and Ceiling Span Table Notes, two copies of structural calculations and plan sheet A4.1; taken to Tim Woodard
|
Routing - PLAN CHECK | 11/2/2010 | | 11/8/2010 | | FAIL |
Tim L. Woodard
|
|
|
Refer to plan review report. Tim Woodard
|
Application received | | 10/25/2010 | 11/2/2010 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/2/2010 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/2/2010 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 11/2/2010 | | PASS |
Tim L. Woodard
|
|
|
|