Third Notice | | 5/31/2011 | 5/20/2011 | | DONE |
|
|
|
|
Third Notice | | 5/2/2011 | 5/17/2011 | | DONE |
|
|
|
faxed to GC and J.Crew rep
|
Second Notice | | 4/10/2011 | 4/27/2011 | | DONE |
Christina Prado
|
|
|
Faxed 4/27/11
|
First Notice | | 3/28/2011 | 3/31/2011 | | DONE |
|
|
|
|
BLD-Final | 3/17/2011 | 3/18/2011 | 3/18/2011 | A | PASS |
Mike Jordan
|
|
|
Late Am pending Fire life saftey---Mike Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 3/17/2011 | 3/18/2011 | 3/18/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Permanent Occupancy | | | 3/18/2011 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Other | 3/9/2011 | 3/9/2011 | 3/9/2011 | P | PART |
Mike Jordan
|
|
|
acoustic ceiling insp//Mike Phone #: ###-####. Provide ceiling wire for diffusers. Will check on file.
|
BLD-Framing/Rough-in | 3/8/2011 | 3/8/2011 | 3/8/2011 | P | NR |
Mike Jordan
|
|
|
mike Phone #: ###-####. Electrical rough in inspection failed.
|
BLD-Framing/Rough-in | 2/2/2011 | 2/3/2011 | 2/3/2011 | A | PASS |
Mike Jordan
|
|
|
All non treated wood was removed and replaced with fire treated wood, All patches are complete.
|
BLD-Framing/Rough-in | 2/2/2011 | 2/3/2011 | 2/2/2011 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 1/28/2011 | 1/31/2011 | 1/31/2011 | P | PART |
Mike Jordan
|
|
|
Ceiling & Wall-- MIke Chase Phone #: ###-####. Walls and hardlids only. Needs to remove all non FRP wood and provide FRP wood, repair smioke bulkhead and provide blow patches at existing 1hr. fire partitions. ok to start sheet rocking.
|
Issue PAID IN FULL permit | | | 1/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 12/13/2010 | | 12/20/2010 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
Plan assigned to (CJW) | 11/19/2010 | | 12/20/2010 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/20/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/20/2010 | | DONE |
|
|
|
|
Telephone call | | | 12/20/2010 | | |
|
|
|
12-20-10 called left message for Rex permit ready and fee given
|
Plan resubmittals received | | | 12/16/2010 | | |
Barbara Stitt
|
|
|
Received 1 cover transmittal, 1 letter from Dennis Mitchell dated 12-10-10, 2 copies of Calcs, 2 copies of sheets A-0.0, A-0.4, A-4.1, A-8.0 and taken to Carl Westfall on 12-16-10 @ 1:30pm
|
Routing - FIRE | 12/7/2010 | 12/7/2010 | 12/13/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 12/13/2010 | | FAIL |
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 12/7/2010 | 12/10/2010 | 12/7/2010 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - PLAN CHECK | 11/23/2010 | | 12/7/2010 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on December 1, 2010 and was finished on December 7, 2010. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 11/19/2010 | | 11/23/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 11/23/2010 | | 11/23/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 11/22/2010 | | 11/22/2010 | | PASS |
Terry Records
|
|
|
|
Application received | | 11/18/2010 | 11/19/2010 | | DONE |
Tisha Gallop
|
|
|
|
Pending Assignment by JCB | 11/19/2010 | | 11/19/2010 | | DONE |
Jason Blais
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/19/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/18/2010 | | DONE |
Tisha Gallop
|
|
|
routed plans, architect is going to overnight plan check fee 11/19/10.
|