Second Notice | | 5/21/2011 | 5/11/2011 | | DONE |
|
|
|
|
Third Notice | | 5/16/2011 | 5/11/2011 | | DONE |
|
|
|
|
First Notice | | 5/8/2011 | 5/11/2011 | | DONE |
|
|
|
|
BLD-Final | 4/27/2011 | 4/28/2011 | 4/28/2011 | A | PASS |
Mike Jordan
|
|
|
dante Phone #: ###-####. ok for perm occ.
|
Permanent Occupancy | | | 4/28/2011 | | DONE |
|
|
|
|
BLD-Final | 4/26/2011 | 4/27/2011 | 4/27/2011 | P | PART |
Mike Jordan
|
|
|
Dante Phone #: ###-####. Temp occ. granted. Needs specs on light transmitting panels in roof.
|
Zoning Approval | 4/27/2011 | 4/27/2011 | 4/27/2011 | | PASS |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 4/25/2011 | 4/26/2011 | 4/26/2011 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 4/25/2011 | 4/25/2011 | 4/25/2011 | P | FAIL |
Troy Cobbley
|
|
|
Provide indicator at the main exit and provide the fire dept access designation as discussed.
|
FIRE-Final Inspection | 4/22/2011 | 4/22/2011 | 4/25/2011 | P | DEFR |
Forrest France
|
|
|
dante Phone #: ###-####
|
BLD-Energy code compliance | 4/1/2011 | 4/4/2011 | 4/4/2011 | A | PASS |
Mike Jordan
|
|
|
DANTE Phone #: ###-####
|
BLD-Framing/Rough-in | 3/31/2011 | 4/1/2011 | 4/1/2011 | P | PASS |
Mike Jordan
|
|
|
Dante Phone #: ###-####
|
BLD-Other | 2/23/2011 | 2/28/2011 | 2/28/2011 | P | PASS |
Mike Jordan
|
|
|
re-bar tension tie//Dante Phone #: ###-####
|
BLD-Foundation | 2/11/2011 | 2/14/2011 | 2/14/2011 | A | PASS |
Mike Jordan
|
|
|
Dante Phone #: ###-####
|
BLD-Footing | 2/8/2011 | 2/9/2011 | 2/9/2011 | P | PART |
Mike Jordan
|
|
|
dante Phone #: ###-####. Work in progress on vertical reinforcement install. Special inspector was on site.
|
Issue PAID IN FULL permit | | | 1/28/2011 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JCM) | 12/2/2010 | | 1/3/2011 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 12/29/2010 | | 1/3/2011 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 1/3/2011 | | PASS |
John Menard
|
|
|
Reviewed and approved structural and nonstructural revisions. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/3/2011 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 1/3/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/3/2011 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 12/23/2010 | | 12/29/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 12/27/2010 | | 12/29/2010 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 12/21/2010 | 12/21/2010 | 12/23/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 12/23/2010 | | FAIL |
|
|
|
Failed Public Works, Structural, Plan Check
|
Plan resubmittals received | | | 12/22/2010 | | DONE |
Tisha Gallop
|
|
|
received response to comments, SunSky specs and installation guide, three coipes of plan sheets A3.1, A4.1, EN.1; inserted by arch. rep. and taken back to Fire Review.
|
Route to Impact Fee Review | 12/21/2010 | 12/27/2010 | 12/21/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals received | | | 12/21/2010 | | DONE |
Tisha Gallop
|
|
|
received transmittal, letter addressed to Brian Murphy, one copy of Geotech report, two copies of Pond Calcs, O & M, five copies of plan sheets C1, C2, C3, C4; inserted by Jim Coslett and taken back to Fire review. Also received three copies Supplemental Calcs and Building calcs with one cover letter in responce to E-mail from JCM
|
Plan resubmittals requested | | | 12/21/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing - PLAN CHECK | 12/20/2010 | | 12/21/2010 | | FAIL |
John Menard
|
|
|
John Menard
|
Routing - PLANNING | 12/17/2010 | | 12/20/2010 | | PASS |
Josh Wilson
|
|
|
DRH10-00206 Josh Wilson
|
Routing - PLUMBING | 12/16/2010 | | 12/17/2010 | | PASS |
Bill VanDegrift
|
|
|
pipe building drain out the front of the building to match the building sewer location.
|
Routing - Erosion and Sediment | 12/15/2010 | | 12/16/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and ESC permit conditions. ESC10-00879
|
Plan resubmittals requested | | | 12/16/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
Routing PW Solid Waste | 12/15/2010 | | 12/15/2010 | | PASS |
|
|
|
|
Routing PW Sewer Design | 12/13/2010 | | 12/15/2010 | | PASS |
Jon R. Gunnerson
|
|
|
Connect onto existing sanitary sewer service provided.
|
Routing - PUBLIC WORKS | 12/3/2010 | | 12/15/2010 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Brian Murphy for drainage issues. contact at ###-####
|
Routing Off Site - STRUCTURAL | 12/2/2010 | | 12/13/2010 | | FAIL |
John Menard
|
|
|
Received comment list from consulting structural engineer requesting revisions. JCM
|
Routing PW Drainage | 12/6/2010 | | 12/13/2010 | | FAIL |
Brian Murphy
|
|
|
needs 3 to 1 slopes
|
Routing PW Environmental | 12/6/2010 | | 12/6/2010 | | PASS |
Walt Baumgartner
|
|
|
OK to pass, called owner to discuss no floor drains and dry shop operations, stormwater regulations.
|
Routing PW Sewer Rating | 12/6/2010 | | 12/6/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 12/3/2010 | | 12/3/2010 | | PASS |
Terry Records
|
|
|
|
Routing - PLANNING Land Div | 12/2/2010 | | 12/3/2010 | | PASS |
Todd Tucker
|
|
|
|
Application received | | 12/2/2010 | 12/2/2010 | | DONE |
Christina Prado
|
|
|
|
Pending Assignment by JCM | 12/2/2010 | | 12/2/2010 | | DONE |
John Menard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/2/2010 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/2/2010 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/2/2010 | | PASS |
John Menard
|
|
|
|
Telephone call | | | 12/2/2010 | | DONE |
Christina Prado
|
|
|
Called Actin Couriers for pick up
|