Third Notice | | 4/18/2011 | 4/13/2011 | | DONE |
|
|
|
|
Second Notice | | 4/10/2011 | 4/13/2011 | | DONE |
|
|
|
|
First Notice | | 3/28/2011 | 3/31/2011 | | DONE |
|
|
|
|
BLD-Final | 3/17/2011 | 3/18/2011 | 3/18/2011 | P | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####. ok for perm. occ.
|
FIRE-Final Inspection | 3/17/2011 | 3/18/2011 | 3/18/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Permanent Occupancy | | | 3/18/2011 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Other | 3/10/2011 | 3/11/2011 | 3/14/2011 | P | PASS |
Mike Jordan
|
|
|
Ceiling Inspection---Dan Phone #: ###-####
|
BLD-Other | 3/7/2011 | 3/8/2011 | 3/8/2011 | A | NR |
Mike Jordan
|
|
|
Ceiling t-grid inspection please-Dan Phone #: ###-####. Needs other trades rough in inspections first. Dan was contacted and informed.
|
BLD-Framing/Rough-in | 2/15/2011 | 2/16/2011 | 2/16/2011 | P | PART |
Mike Jordan
|
|
|
Dan-PLease call at least 30 mins prior to inspection Phone #: ###-####4. Interior steel stud walls, hardlids and soffits. Did note that back soffit (bridal area) is suspended by the 2nd flor joist. Contractor needs to attach soffit to floor deck or provide engineering showjng that floor joist are capable of suporting the additional load.
|
BLD-Framing/Rough-in | 2/14/2011 | 2/15/2011 | 2/15/2011 | A | NR |
Mike Jordan
|
|
|
DAN Phone #: ###-####. Needs electrical rough in inspections.
|
Issue PAID IN FULL permit | | | 1/13/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (TLW) | 12/17/2010 | | 1/12/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/12/2011 | | 1/12/2011 | | PASS |
Tim L. Woodard
|
|
|
Approved with redlines and attached engineering / attached mechanical compliance / attached electrical compliance. TLW
|
1st review completed | | | 1/12/2011 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 1/12/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 1/12/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/12/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 1/12/2011 | | DONE |
Tisha Gallop
|
|
|
called Laura Baker at Klover Architects and told her permit is ready, fees and need GC to sign form.
|
Plan resubmittals received | | | 1/11/2011 | | DONE |
Tisha Gallop
|
|
|
received revised certificate of value, three copies of structural calcs and plan sheets A100, A400, A420; taken to Tim Woodard
|
Plan resubmittals received | | | 12/28/2010 | | DONE |
Tisha Gallop
|
|
|
received by mail the original copy of Contractor registration Form signed by architect Henry Klover; taken to Tim Woodard
|
Plan resubmittals received | | | 12/22/2010 | | |
Barbara Stitt
|
|
|
Received 1 cover transmital, 3 copies of sheet M1 and taken to Tim Woodard on 12-22-10 @ 9:35am
|
1st review completed | | | 12/22/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Telephone call | | | 12/22/2010 | | DONE |
Tim L. Woodard
|
|
|
Left message with Greg from HFA engineers that smoke evacuation system is not fully addressed. TLW
|
Routing - PLAN CHECK | 12/21/2010 | | 12/22/2010 | | FAIL |
Tim L. Woodard
|
|
|
Still need engineering for storefront system. Tim Woodard
|
Routing - PUBLIC WORKS | 12/17/2010 | | 12/21/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 12/21/2010 | | 12/21/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 12/20/2010 | | 12/20/2010 | | PASS |
Terry Records
|
|
|
|
Intake Approval | | | 12/17/2010 | | PASS |
Tim L. Woodard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/17/2010 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/17/2010 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | 12/16/2010 | 12/16/2010 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 12/16/2010 | | FAIL |
Barbara Stitt
|
|
|
|