Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD10-02932
StatusFinaled
Name BERMENSOLO CONSTRUCTION
Site Address 8055 W GODDARD RD
Project NameCAPITOL HIGH RESTROOM UPGRADE
Customer Number 
ePlanReviewNo
Description
(CAPITOL HIGH SCHOOL – Restroom Upgrade) Permit is to upgrade existing non-compliant restrooms to fully accessible restrooms. Approval contingent upon adhering to the approved plans on file. Work to include: installation of new accessible plumbing fixtures, installation of new toilet partitions, reducing / removing one toilet fixture in each restroom to allow for accessible stall, and interior finishes in accordance with chapter 8 of the 2006 IBC. This building is partially Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference8/19/20118/19/20118/19/2011ACANC
DetailsJim Sly
Tom phone ###-####
BLD-Final8/16/20118/16/20118/19/2011PCANC
DetailsJim Sly
Tom Phone #: ###-####
BLD-Final8/17/20118/18/20118/18/2011APASS
DetailsJim Sly
Tom phone ###-####
C/C issued
DOC - Permit Finaled8/18/20118/18/20118/18/2011PPASS
DetailsJim Sly
FIRE-Final Inspection8/17/20118/18/20118/17/2011APASS
DetailsTroy Cobbley
life safety passed. Door hardware to be verified by building inspector.
FIRE-Final Inspection8/17/20118/17/20118/17/2011PPASS
DetailsTroy Cobbley
life safety passed. Door hardware to be verified by building inspector.
BLD-Final8/8/20118/9/20118/9/2011ANR
DetailsJim Sly
tom Phone #: ###-####
Need trade finals and fire final.
BLD-Framing/Rough-in7/26/20117/27/20117/27/2011APASS
DetailsJim Sly
Jerry bermensolo phone
BLD-Framing/Rough-in7/26/20117/26/20117/26/2011PCANC
DetailsJim Sly
Tom ###-####
Re-sched for Wed am.
BLD-Final5/9/20115/10/20115/10/2011APART
DetailsJim Sly
Tom-2 bathrooms Phone #: ###-####
Partial....OK to occupy 1boy and 1 girl bathroom....2nd floor East.
Plan Reviewer's activity  3/11/2011 DONE
DetailsTim L. Woodard
Approved modification to sheet A2.1. Allowing 7 inches on hinge side of accessible stall. This decision was made by Jason Blais that the existing situations on site as documented in attached emails made it technically infeasible to fully comply. TLW
Issue PAID IN FULL permit  2/3/2011 DONE
DetailsTisha Gallop
Plan assigned to (TLW)12/22/2010 1/5/2011 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK12/23/2010 1/5/2011 PASS
DetailsTim L. Woodard
Tim Woodard
Routing - FIRE  1/5/2011 PASS
DetailsTim L. Woodard
Field Verify
Case Summary (BLD)  1/5/2011 DONE
DetailsTim L. Woodard
1st review completed  1/5/2011 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  1/5/2011 DONE
DetailsTim L. Woodard
Inspection Record Card- Bld  1/5/2011 DONE
Permit Ready to Issue  1/5/2011 DONE
DetailsTisha Gallop
Telephone call  1/5/2011 DONE
DetailsTisha Gallop
called and left vm for Scott Henson/LCA Arch. that permit is ready, fees and need GC and form, and RCE#
Routing - PUBLIC WORKS12/22/2010 12/23/2010 PASS
DetailsConnie Baumgartner
Application received 12/22/201012/22/2010 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  12/22/2010 DONE
DetailsBarbara Stitt
Recd Pcfee & Taken To Pln CK  12/22/2010 DONE
DetailsBarbara Stitt