BLD-Final | 4/20/2011 | 4/21/2011 | 4/21/2011 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Todd Blackwell
|
DOC - Permit Finaled | 4/21/2011 | 4/21/2011 | 4/21/2011 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Grading Inspection | 4/15/2011 | 4/15/2011 | 4/15/2011 | P | DONE |
Terry Records
|
|
|
Final grading and drainage approved
|
BLD-Energy code compliance | 3/7/2011 | 3/9/2011 | 3/9/2011 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Todd Blackwell
|
BLD-Framing/Rough-in | 3/7/2011 | 3/8/2011 | 3/8/2011 | P | PART |
Tony Young
|
|
|
pat nolan Phone #: ###-#### >> Inspection requested via web by Todd Blackwell,, correction posted on back of truss engineering.. ok to insulate after mech pass
|
BLD-Foundation | 1/27/2011 | 1/28/2011 | 1/28/2011 | A | PASS |
Tom Arcoraci
|
|
|
late am please//foundation wall insp//David ###-####
|
BLD-Footing | 1/25/2011 | 1/26/2011 | 1/26/2011 | A | PART |
Tony Young
|
|
|
David Hangartner Phone #: ###-#### >> Inspection requested via web by Todd Blackwell,, work in progress
|
PubWorks Subgrade Approval | 1/25/2011 | 1/25/2011 | 1/25/2011 | | DONE |
Terry Records
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Permit Ready to Issue | | | 1/25/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 1/25/2011 | | DONE |
Tisha Gallop
|
|
|
Todd called in, told him permit would be ready in 1/2 hr.
|
Issue PAID IN FULL permit | | | 1/25/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 1/24/2011 | | 1/25/2011 | | PASS |
Perry Paine
|
|
|
|
Case Summary (BLD) | | | 1/25/2011 | | |
|
|
|
|
1st review completed | | | 1/25/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2011 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/25/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | | | 1/25/2011 | | PASS |
Perry Paine
|
|
|
Carl Madsen
|
Routing - PLAN CHECK | 1/21/2011 | | 1/25/2011 | | PASS |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 1/24/2011 | | 1/25/2011 | | PASS |
Perry Paine
|
|
|
|
Routing - MECHANICAL | 1/24/2011 | | 1/24/2011 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 1/20/2011 | | DONE |
Tisha Gallop
|
|
|
received two copies of mechanical manuals, J, D & S; taken to Troy James.
|
Routing - MECHANICAL | 1/14/2011 | | 1/14/2011 | | FAIL |
Dixie Fellows
|
|
|
customer needs manual j & d material; plans taken to PEP
|
Plan assigned to (CDM) | 1/3/2011 | 1/3/2011 | 1/13/2011 | | DEFR |
Carl D Madsen
|
|
|
|
Routing - FIRE | 1/5/2011 | | 1/7/2011 | | PASS |
Scott Arellano
|
|
|
No comments
|
Route to Impact Fee Review | 1/3/2011 | 1/6/2011 | 1/6/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Erosion and Sediment | 1/4/2011 | | 1/5/2011 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and ESC permit conditions. ESC11-00001
|
Routing - Addressing | 1/3/2011 | | 1/4/2011 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS GRADING | | | 1/4/2011 | | PASS |
Terry Records
|
|
|
Approved as category 3
|
Routing - PUBLIC WORKS | | | 1/4/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 1/4/2011 | | 1/4/2011 | | PASS |
David Moser
|
|
|
|
Application received | | 1/3/2011 | 1/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 1/3/2011 | | PASS |
Barbara Stitt
|
|
|
|
Routing - MECHANICAL | 1/20/2011 | | | | FAIL |
|
|
|
called contractor, he was aware that he needed to provide manual J, D, S calcs, calcs will be here today.
|
Routing - MECHANICAL | 1/20/2011 | | | | FAIL |
Troy James
|
|
|
1. Building Analysis Entire House BTU load too high for heating and cooling.
2. Component Construction:
Shows Knee wall design
SHGC at .60
Orientation for door does not match plans.
Ceilings shows 28 square feet with r31 roof insulation, r-30 ceiling.
No ceiling partitions shown on plans.
Floors 22 square feet should be shown as garage over.
3. Provide manufacturers data sheets for equipment.
4. Static pressure at .50.
|