Permit Information
Permit NumberBLD11-00037
StatusFinaled
Name BENITON CONSTRUCTION
Site Address 300 S 23RD ST
Project NameTERRY REILLY HEALTH SERVICES
Customer Number 
ePlanReviewNo
Description
(TERRY REILLY HEALTH SERVICES) (DRH10-00277) This building is NOT fire sprinklered. To remodel an existing 15,195 square foot building (7,101 square foot basement, 7,613 square foot 1st story, 481 square foot 2nd story) and convert it to a medical outpatient clinic. This facility is NOT classified as an ambulatory health care facility because no one will be rendered incapable of self-preservation. Work is to include 6 toilet rooms accessible to the disabled, 2 toilet/shower rooms accessible to the disabled, exterior concrete ramp accessible to the disabled, exterior concrete stairway, exterior steel canopy over the new ramp and stairway, new concrete lintel and jambs at new exterior wall openings, exterior windows and doors, masonry elevator shaft, elevator, interior nonbearing walls, interior windows and doors, new roof covering with insulation installed on top of the roof deck, new roof top HVAC units, gypsum board ceilings, suspended acoustical ceilings, millwork, 1-hr corridors, and interior finishes. The work is required to comply with the approved drawings, the plan review report, and with all applicable codes and ordinances. The fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 7/23/20118/11/2011 DONE
Permanent Occupancy  7/13/2011 DONE
DetailsTisha Gallop
BLD-Final7/5/20117/6/20117/6/2011APASS
DetailsJim Storey
ryan Phone #: ###-#### final ok
Temporary Occupancy6/27/20119/25/20116/27/2011 DONE
DetailsDarla L Downs
BLD-Final6/23/20116/24/20116/24/2011APART
DetailsDave Hannah
Brian Phone #: ###-#### ok for temp occ ok for perm occ after mec gos perm
FIRE-Final Inspection6/22/20116/23/20116/23/2011APASS
DetailsForrest France
Fire life safety inspection completed acceptable. One EM light repaired while on site, signage at the electrical room and elevator lobbies to be posted as discussed.
FIRE-Final Inspection6/21/20116/22/20116/22/2011PNR
DetailsForrest France
Final pending project related FIR permit.
PubWorks Occupancy Approval6/17/20116/17/20116/17/2011 DONE
DetailsTiffany Lowery
Zoning Approval6/15/20116/15/20116/15/2011 DONE
DetailsAndrea Tuning
BLD-Other6/3/20116/6/20116/6/2011APART
DetailsDave Hannah
RYAN Phone #: ###-#### ceiling in basement ok to cover
BLD-Wall cover5/20/20115/20/20115/23/2011PPASS
DetailsDave Hannah
Ceiling cover--Ryan Phone #: ###-#### ok to cover first floor
Case Summary (BLD)  5/10/2011 DONE
DetailsTisha Gallop
BLD-Framing/Rough-in5/5/20115/6/20115/6/2011APASS
DetailsDave Hannah
Ryan Phone #: ###-#### ext canopy
BLD-Wall cover4/7/20114/8/20114/11/2011PPASS
DetailsDave Hannah
ryan Phone #: ###-#### ok to cover the rest of first floor and all of the basement
BLD-Energy code compliance4/1/20114/4/20114/5/2011PPART
DetailsDave Hannah
ryan - as soon as possible after lunch please Phone #: ###-#### ok to cover first floor
BLD-Framing/Rough-in3/30/20113/31/20113/31/2011APART
DetailsDave Hannah
ryan Phone #: ###-#### ok to insulate ext wall basement and first floor
BLD-Other3/18/20113/21/20113/22/2011PPART
DetailsDave Hannah
rebar in masonry//Ryan Smith Phone #: ###-#### elevator cmu walls ok to grout
BLD-Concrete3/17/20113/18/20113/18/2011PPART
DetailsJim Sly
late pm//Ryan (or Matt @ ###-####) Phone #: ###-####
Looked at Stairway wall East side.....walls for Ramp and stairway- South side......2500 PSI design strength...Contractor says he is ordering 3500 mud.....Eng. only required 3000. Looked at CMU elevator shaft...Rebar in place and appears OK up to 6' high. They should call daily for inspection of CMU. Need test samples on Mortar. Supervisor for Benington was just filling in for today...his name was Matt. I let him know all this.
BLD-Foundation3/9/20113/10/20113/11/2011APASS
DetailsDave Hannah
late A.M. call before arrival--Ryan Phone #: ###-#### ftgs for stairs into basement and ada ramp
BLD-Concrete3/3/20113/4/20113/4/2011APASS
DetailsMike Jordan
ryan - pouring at 10 Phone #: ###-####. Reinforcement for elevator pit ok. Also noted to contracotr that design professional as required special inspection as per table 1704 that has been submitted.
Issue PAID IN FULL permit  2/28/2011 DONE
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  2/25/2011 DONE
Print Occupancy Form  2/25/2011 DONE
Telephone call  2/25/2011 DONE
t/c w tom - permit ready and fees given - also need gc name, rce# and ACHD receipt
Permit Ready to Issue  2/25/2011 DONE
Details
Routing - PLAN CHECK2/24/2011 2/25/2011 PASS
DetailsCarl Westfall
Drawings approved after insertion of revised drawings.
Plan assigned to (CJW)1/11/2011 2/25/2011 PASS
DetailsCarl Westfall
Plan resubmittals received  2/24/2011  
DetailsBarbara Stitt
Received a cover transmittal and 2 copies of sheets F-1.0 & F-1.1 then taken to Carl Westfall
Routing - PLUMBING2/24/2011 2/24/2011 PASS
DetailsBill VanDegrift
per plans and 2003 upc
Routing - PLAN CHECK2/16/2011 2/24/2011 FAIL
DetailsCarl Westfall
Waiting for revised fire alarm sheet.
Plan resubmittals received  2/18/2011 DONE
DetailsTisha Gallop
received transmittal, response, memo addressed to Jason Blais, Alternate request addressed to Jason Blais, copy of e-mail from Nick Schmit to Carl Westfall, and two copies of plan sheets G2.0 A2.1, A3.0, A3.1, A3.3, A5.2, A5.3, A8.0 A8.1, E0.1, E2.0, E2.1, E2.2, E3.0, E3.1, E4.0, M2.0, M2.1, M3.0, P2.0, P2.1, P3.0; taken to Carl Westfall
Route to Impact Fee Review2/15/20112/18/20112/17/2011 PASS
DetailsCindy M. Gould
Tenant improvement no impact fees
Routing - FIRE2/15/20112/15/20112/16/2011 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  2/16/2011 FAIL
Failed Plumbing, Plan Check
Telephone call  2/15/2011 DONE
Called Ryan with the GC (###-####). Explained that after Plumbing approves the drawings then we could issue an early start maybe by Wednesday 2-23-11. If the resubmittal is submitted this week and the all is OK, full permit could be ready by Friday 2-25-11.
Routing - PLAN CHECK1/28/2011 2/15/2011 FAIL
DetailsCarl Westfall
The IBC plan review report was started on January 31, 2011 and was finished on February 15, 2011. Revised drawings were required. See the plan review report.
Routing - Design Review1/27/2011 1/28/2011 PASS
DetailsAndrea Tuning
Andrea Tuning - DRH10-00277
Routing - PLUMBING1/21/2011 1/27/2011 FAIL
DetailsBill VanDegrift
(1) due to the elevation of the sewer and the ceiling heights with in the building, the 1st floor waste piping is approved to combine with the basement piping and rout to the ejectors. (2) isolate the water in the lab with hot and cold r.p.s installed over a drain to handle full discharge. (3) replace the 2 1/2" r.p. on the premise with a 2 1/2" dcva. (4) addres items 1 and 2 and resubmit.
Routing - Erosion and Sediment1/20/2011 1/21/2011 PASS
DetailsSteven Webb
ESC plan is approved according to the ESC plan and ESC permit conditions. ESC11-00018
Routing - PUBLIC WORKS1/13/2011 1/20/2011 PASS
DetailsBeverly Mountain
Routing PW Drainage1/13/2011 1/19/2011 PASS
DetailsBrian Murphy
Routing PW Street Lights1/19/2011 1/19/2011 PASS
DetailsHank Alarcon
Routing - Addressing1/13/2011 1/13/2011 PASS
DetailsTerry Records
Routing PW Sewer Rating1/13/2011 1/13/2011 PASS
DetailsConnie Baumgartner
Pending Assignment by JCB1/10/2011 1/11/2011 DONE
DetailsJason Blais
Plan Reviewer's activity  1/11/2011 DONE
DetailsJason Blais
Sent email to architect representative for them to contact ACHD and submit needed documents for evaluation of any impact fees due. Our Permit Counter will need a verification letter from ACHD prior to the building permit being issued.
Application received 1/7/20111/10/2011 DONE
DetailsChristina Prado
Intake Approval  1/10/2011 PASS
Plans ACCEPTED BY PLAN TECH  1/10/2011 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  1/10/2011 DONE
DetailsChristina Prado
Intake Approval  1/7/2011 FAIL
Structural sheets are required to be stamped by the engineer CDM