Third Notice | | 6/1/2011 | 5/27/2011 | | DONE |
|
|
|
|
Second Notice | | 5/20/2011 | 5/25/2011 | | DONE |
|
|
|
|
First Notice | | 5/2/2011 | 5/10/2011 | | DONE |
|
|
|
|
Permanent Occupancy | | | 4/22/2011 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 4/20/2011 | 4/21/2011 | 4/21/2011 | A | PASS |
Mike Jordan
|
|
|
eddie Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 4/20/2011 | 4/21/2011 | 4/21/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 4/20/2011 | 4/20/2011 | 4/20/2011 | P | CANC |
Troy Cobbley
|
|
|
canceled due to time constraints. rescheduled for tomorrow.
|
BLD-Framing/Rough-in | 4/4/2011 | 4/5/2011 | 4/5/2011 | A | PART |
Mike Jordan
|
|
|
eddy - as early as possible please Phone #: ###-####. Interior steel stud framed walls ok. Hardlid ok pending electrical rough in.
|
BLD-Framing/Rough-in | 3/22/2011 | 3/22/2011 | 3/22/2011 | P | PART |
Mike Jordan
|
|
|
Eddy Phone #: ###-####. Interior steel stud framing for hardlid in restroom, restroom walls and stockroom demissing wall. Also ok to rock exterior side of storefront framing.
|
Issue PAID IN FULL permit | | | 2/22/2011 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 2/17/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/17/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 2/17/2011 | | DONE |
Tisha Gallop
|
|
|
called and left vm for Scott Daves that permit is ready, fees and need initial values for ele, mech, plm.
|
Routing - PLAN CHECK | 2/16/2011 | | 2/16/2011 | | PASS |
Tim L. Woodard
|
|
|
Approved with redline. Redline indicates do not install fire dampers on smoke evacuation ducts. Counter productive to have on there. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/16/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 2/16/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | | | 2/16/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 2/11/2011 | | |
Barbara Stitt
|
|
|
Received letter to Tim Woodard form Carla Street dated 2-9-11, response letter to Tim Woodard from Connie Bowen dated 2-8-11, copy of Tim Woodard's plan review report dated 1-31-11, 2 copies of strucural calculations, 3 copies of sheets A1, A3, A4, M1 and taken to Tim Woodard's desk
|
Routing - PLAN CHECK | 1/20/2011 | | 1/31/2011 | | FAIL |
Tim L. Woodard
|
|
|
Plans were missing required structural engineering and details for the existing smoke evacuation system. Sent plan review report off to applicant also called applicant as well as engineering company at time of intake as well as when the plan review report was sent off. TLW
|
1st review completed | | | 1/31/2011 | | DONE |
Tim L. Woodard
|
|
|
|
CHANGE STATUS TO (REV) | | | 1/31/2011 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 1/13/2011 | | 1/20/2011 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 1/19/2011 | | 1/19/2011 | | PASS |
Terry Records
|
|
|
|
Routing PW Sewer Rating | 1/19/2011 | | 1/19/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 1/12/2011 | 1/13/2011 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/13/2011 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/13/2011 | | DONE |
Christina Prado
|
|
|
|