First Notice | | 12/26/2011 | 1/3/2012 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/16/2011 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 12/16/2011 | | DONE |
Barbara Stitt
|
|
|
|
Temporary Occupancy UNPAID FEE | | | 11/16/2011 | | DONE |
Barbara Stitt
|
|
|
Per request of Christy Little with ACHD the temp occupancy has been extended another 45 days as they are still working out an agreent regarding impact fees between the school board and ACHD commission in another 30 days. See email in the scanned documents dated 11-16-11//BAS
|
CHANGE STATUS TO (TMP) | | | 11/3/2011 | | DONE |
|
|
|
|
First Notice | 10/14/2011 | 10/14/2011 | 10/19/2011 | | DONE |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 10/14/2011 | 10/14/2011 | 10/14/2011 | P | PASS |
Jim Sly
|
|
|
|
Temporary Occupancy UNPAID FEE | | | 8/23/2011 | | |
|
|
|
|
BLD-Final | 8/4/2011 | 8/5/2011 | 8/5/2011 | P | PART |
Tony Young
|
|
|
ok for final pending all others,, paperwork from engineer is in the mailbox
|
FIRE-Final Inspection | 8/3/2011 | 8/5/2011 | 8/5/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Other | 8/3/2011 | 8/4/2011 | 8/4/2011 | A | NR |
Tom Arcoraci
|
|
|
Jim, this is a call for the final structural inspection for occupancy. If any questions please feel free to call. Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald
|
Zoning Approval | 8/2/2011 | 8/2/2011 | 8/2/2011 | | DONE |
Cody Riddle
|
|
|
|
PubWorks Occupancy Approval | 8/2/2011 | 8/2/2011 | 8/2/2011 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Framing/Rough-in | 7/25/2011 | 7/25/2011 | 7/25/2011 | A | PASS |
Jim Sly
|
|
|
We are ready to start flooding the ceiling grid. A late AM inspection would be very much appreciated. Phone #: ###-#### >> Inspection requested via web by Ron Oswald
|
BLD-Framing/Rough-in | 7/19/2011 | 7/19/2011 | 7/19/2011 | P | DONE |
Mike Jordan
|
|
|
Please provide a cursory inspection on suspended ceiling grid. Entrance to site has change to school parking lot, east entrance. Phone #: ###-#### >> Inspection requested via web by Ron Oswald. Cisca 3-4 system to be used, grid exceeds nthe 2.5 lbs. per square foot.
|
BLD-Framing/Rough-in | 7/7/2011 | 7/8/2011 | 7/8/2011 | A | PART |
Jim Sly
|
|
|
Please provide a late morning hard lid inspection for the project restrooms. We have a am Electrical and have passed the HVAC and Plumbing roughs for this area. Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald Hard lids in restrooms and restroom walls OK to cover. Trusses OK.
|
BLD-Framing/Rough-in | 6/29/2011 | 6/29/2011 | 6/29/2011 | P | PART |
Tom Arcoraci
|
|
|
Please provide a interior wall framing inspection for cover. I have the main classrooms electrical inspections signed off for this area by the state. The restroom areas will be inspected for plumbing this afternoon. Thanks you Phone #: ###-#### >> Inspection requested via web by Ron Oswald classrooms ok for cover tom
|
BLD-Framing/Rough-in | 6/20/2011 | 6/21/2011 | 6/21/2011 | A | PART |
Jim Sly
|
|
|
We are currently installing the sheeting and If possible I would like to schedule my roofing crew in late morning. If able please schedule for the first of the morning. Thanks Ron Oswald Phone #: ###-#### >> Inspection requested via web by Ron Oswald Roof sheathing and trusses OK
|
BLD-Concrete | 5/6/2011 | 5/9/2011 | 5/9/2011 | P | PART |
Jim Sly
|
|
|
Changing inspection due to weather, we will pour on Tuesday AM. Afternoon inspection is prefered. Strata providing Special inspections also in afternoon. Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald OK pending STRATA special insp, tests and approvals.
|
BLD-Concrete | 5/6/2011 | 5/9/2011 | 5/6/2011 | A | CANC |
Jim Sly
|
|
|
This inspection is for slab pour, We are Scheduled for concrete to arrive at 7:30 am. Don Hill with Strata is Handling the special inspections, Rebar, Wire mesh and pour observations. Underslab Plumbing has been inspected and logged with Sticker attached. Any Questions feel free to call me at anytime.
Thanks
Ron Oswald Phone #: ###-#### >> Inspection requested via web by Ron Oswald Inspection cancelled from web by: Ron Oswald
|
BLD-Foundation | 4/21/2011 | 4/22/2011 | 4/22/2011 | P | PASS |
Tom Arcoraci
|
|
|
wip ok spec insp
|
BLD-Foundation | 4/21/2011 | 4/21/2011 | 4/21/2011 | P | NR |
Tom Arcoraci
|
|
|
Stem wall, Scheduled for 2:00 pm. Thanks Phone #: ###-#### >> Inspection requested via web by Ron Oswald
|
BLD-Footing | 4/19/2011 | 4/21/2011 | 4/21/2011 | A | PART |
Mike Jordan
|
|
|
Good afternoon, We have a specific access road to get to project site. It is East of the school proper at our Company sign. If possible please schedule for as early as we can near 8:30 am. Thanks and have a great day Ron Oswald Site Superintendent Phone #: ###-#### >> Inspection requested via web by Ron Oswald. Permiter and interior footings. Special inspector on site.
|
Issue PAID IN FULL permit | | | 3/29/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 3/14/2011 | | DONE |
|
|
|
left vm for ed - permit ready and fees given - also need gc, rce#, rp and ACHD receipt
|
Permit Ready to Issue | | | 3/14/2011 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 3/9/2011 | | 3/11/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 3/11/2011 | | 3/11/2011 | | PASS |
Cody Riddle
|
|
|
|
Routing - PLAN CHECK | 3/11/2011 | | 3/11/2011 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2011 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 3/11/2011 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 1/19/2011 | | 3/11/2011 | | PASS |
John Menard
|
|
|
|
Routing PW Drainage | 3/9/2011 | | 3/10/2011 | | PASS |
Brian Murphy
|
|
|
FOR PLAYGOUNDS SEEPAGE BEDS
|
Plan resubmittals received | | | 3/10/2011 | | |
Barbara Stitt
|
|
|
Received 5 copies of sheet C2.10 inserted into plans and returned back to Brian Murphy's desk
|
Routing - PLAN CHECK | 2/18/2011 | | 3/9/2011 | | PASS |
John Menard
|
|
|
|
Plan resubmittals received | | | 3/9/2011 | | DONE |
Tisha Gallop
|
|
|
received two copies of o & m manual, five copies of plan sheets A1.01, C2.00, C3.00, C3.50; inserted by arch. rep. and taken back to John Menard.
|
Plan Reviewer's activity | | | 2/28/2011 | | PASS |
John Menard
|
|
|
Reviewed and approved structural and nonstructural revisions. JCM
|
Plan resubmittals received | | | 2/22/2011 | | |
Barbara Stitt
|
|
|
Received cover transmital, response letter from Ed Daniels dated 2-18-11, 2 copies of response letter from Jonny Knopp dated 2-16-11, 3 copies of structural calculations, 2 copies of sheets A-2.01, A-2.10, A-7.01, 3 copies sheets S-0., S-1.01, S-1.02, S-1.03, S-2.01, S-3.01, S-3.02, S-3.03, S-4.01, S-5.01, S-6.01, S-6.02, S-7.01 all inserted by architects office then plans taken back to John Menards desk
|
Routing - FIRE | 2/11/2011 | 2/11/2011 | 2/18/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 2/18/2011 | | FAIL |
|
|
|
Failed Planning
|
Route to Impact Fee Review | 2/11/2011 | 2/16/2011 | 2/14/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals requested | | | 2/11/2011 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing - PLAN CHECK | 1/31/2011 | | 2/11/2011 | | FAIL |
John Menard
|
|
|
John Menard
|
Routing Off Site - STRUCTURAL | 1/19/2011 | | 2/3/2011 | | PASS |
John Menard
|
|
|
Received comment list from consulting structural engineer requesting revisions. JCM
|
Plan resubmittals requested | | | 2/3/2011 | | DONE |
John Menard
|
|
|
Emailed the architect a copy of the structural review requesting revisions. JCM
|
Routing - PLANNING | 1/28/2011 | | 1/31/2011 | | FAIL |
Cody Riddle
|
|
|
Expansion requires approval of a conditional use permit modification (staff level). Left message with architect this morning. CER 1/31/11
|
Routing - MECHANICAL | 1/31/2011 | | 1/31/2011 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/24/2011 | | 1/28/2011 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing - Erosion and Sediment | 1/21/2011 | | 1/24/2011 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and ESC permit conditions. ESC11-00028
|
Routing - PUBLIC WORKS | 1/19/2011 | | 1/21/2011 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 1/20/2011 | | 1/21/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 1/20/2011 | | 1/21/2011 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 1/20/2011 | | 1/20/2011 | | PASS |
Terry Records
|
|
|
|
Application received | | 1/14/2011 | 1/19/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 1/19/2011 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
Routing - PLANNING Land Div | 1/19/2011 | | 1/19/2011 | | PASS |
Dave Abo
|
|
|
Parcel over 5 acres in size.
|
Pending Assignment by JCM | 1/18/2011 | | 1/19/2011 | | DONE |
John Menard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/18/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/18/2011 | | DONE |
Tisha Gallop
|
|
|
|