Permanent Occupancy UNPAID FEE | | | 3/8/2011 | | DONE |
|
|
|
|
BLD-Final | 2/23/2011 | 2/23/2011 | 2/23/2011 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####. Will be ok for perm occ. once life/safety has finaled.
|
FIRE-Final Inspection | 2/23/2011 | 2/23/2011 | 2/23/2011 | P | PASS |
Forrest France
|
|
|
Correction notice items field verified for completion. Fire life safety passed.
|
FIRE-Final Inspection | 1/31/2011 | 1/31/2011 | 2/1/2011 | P | FAIL |
Troy Cobbley
|
|
|
Provide sticker at the main exit as discussed, provide correct address, provide single action hardware and remove the deadbolt on the rear exit door, provide annual inspection for the sprinkler system, provide sprinkler protection in areas where it is missing and/or sprinklers are overspace, provide permit for the AES panel and provide a fire alarm system.
|
Issue PAID IN FULL permit | | | 1/26/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (TLW) | 1/20/2011 | | 1/24/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/20/2011 | | 1/24/2011 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 1/24/2011 | | T |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 1/24/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 1/24/2011 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 1/24/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 1/24/2011 | | DONE |
Barbara Stitt
|
|
|
Left voice message for Matt Crane that permit is ready on 1-24-11 @ 9:50am
|
Application received | | 1/20/2011 | 1/20/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/20/2011 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/20/2011 | | DONE |
Barbara Stitt
|
|
|
|
First Notice | | 3/18/2011 | | | |
|
|
|
|