First Notice | 4/11/2011 | 4/11/2011 | 4/27/2011 | | DONE |
Mike Jordan
|
|
|
|
BLD-Final | 4/8/2011 | 4/11/2011 | 4/11/2011 | A | PASS |
Mike Jordan
|
|
|
Andy Phone #: ###-####
|
DOC - Permit Finaled | 4/11/2011 | 4/11/2011 | 4/11/2011 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 4/7/2011 | 4/8/2011 | 4/8/2011 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Scott is ok with the flu spaces
|
FIRE-Final Inspection | 4/7/2011 | 4/7/2011 | 4/7/2011 | P | FAIL |
Troy Cobbley
|
|
|
Per the review notes longitudinal and transverse flu spacing is required. The current racking arrangement does not provide for this.
|
Issue PAID IN FULL permit | | | 2/11/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (SRZ) | 2/3/2011 | | 2/10/2011 | | PASS |
Sam Zahorka
|
|
|
Level 2 TI (Racking)
|
Routing - PLAN CHECK | 2/9/2011 | | 2/10/2011 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/10/2011 | | DONE |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 2/10/2011 | | DONE |
Sam Zahorka
|
|
|
|
Inspection Record Card- Bld | | | 2/10/2011 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 2/10/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 2/10/2011 | | DONE |
Tisha Gallop
|
|
|
called Pat Walsh/ZGA Arch. and left voice messgae permit is ready, fees and need GC, RCE and GC form.
|
Routing - FIRE | 2/7/2011 | | 2/9/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 2/9/2011 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/3/2011 | | 2/7/2011 | | PASS |
Sam Zahorka
|
|
|
|
Pending Assignment by JCB | 2/2/2011 | | 2/3/2011 | | DONE |
Jason Blais
|
|
|
|
Application received | | 2/2/2011 | 2/2/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/2/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/2/2011 | | DONE |
Tisha Gallop
|
|
|
|