DOC - Permit Expired | 2/28/2012 | 2/28/2012 | 2/28/2012 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 2/28/2012 | 2/28/2012 | 2/28/2012 | A | FAIL |
Dave Hannah
|
|
|
out of busness tenant moved out
|
BLD-Conference | 11/30/2011 | 11/30/2011 | 12/2/2011 | P | PART |
Dave Hannah
|
|
|
talked with owner he said he has the parts and will start today
|
Meeting | | | 11/8/2011 | | DONE |
Jason Blais
|
|
|
Jason Blais and Dave Hannah visited the site with the tenant. Some interior walls still need lateral bracing. Bracing options were discussed and now need to be implemented.
|
BLD-Other | 10/28/2011 | 10/28/2011 | 11/2/2011 | P | DEFR |
Dave Hannah
|
|
|
Check status. Inform permit holder that improvements must be performed or legal action may be pursued. Talked with both the bldg manager and the tenant no luck talked with jason and bob jason and I will work on this 11/4
|
BLD-Conference | 8/23/2011 | 8/24/2011 | 8/24/2011 | A | PART |
Dave Hannah
|
|
|
James Hurst Phone #: ###-#### the plans that have been aproved call out for large metal unastrut and metal bracing told owner if they didnt want to install what has been aproved theyed need new plans
|
MISC ACTIONS | | | 8/23/2011 | | DONE |
Tisha Gallop
|
|
|
Received GC form and notice from Hurst Construction that they are the GC on this project.
|
Print Occupancy Form | | | 7/28/2011 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/28/2011 | | DONE |
|
|
|
|
Telephone call | | | 7/28/2011 | | DONE |
Tisha Gallop
|
|
|
call from Lisa w/RA Schults, they are not the GC on this permit. See scanned letter document. They are the GC on Bld11-00761 but not this one, so please remove them.--called Randal Brown and told him this project put on hold for no work allowed until he provides us with Contractors Form with actual GC and registration number or parcel owner can sign exempt and act as their own GC. He said will get it asap.
|
Expiration Notice | 7/22/2011 | 8/12/2011 | 7/22/2011 | | DONE |
Patricia Smith
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2011 | | |
|
|
|
|
Telephone call | | | 7/5/2011 | | DONE |
|
|
|
t/c w tegan - permit ready and fees given
|
Override - Parcel Holds | | | 7/5/2011 | | |
|
|
|
|
Permit Ready to Issue | | | 7/5/2011 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/21/2011 | | 7/1/2011 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 7/1/2011 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 6/21/2011 | | DONE |
Christina Prado
|
|
|
PLAN MOD---affecting shets A0.01 & A1.00. Adding $1500 to value
|
Plan assigned to (CDM) | 2/10/2011 | 2/10/2011 | 4/19/2011 | | DONE |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 4/19/2011 | | DONE |
|
|
|
|
Routing - FIRE | | | 4/19/2011 | | PASS |
|
|
|
Verify in field CDM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2011 | | |
|
|
|
|
Print Occupancy Form | | | 4/19/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/19/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 4/19/2011 | | DONE |
Barbara Stitt
|
|
|
Called and left a message for Teagan that permit is ready, fees due, and we also need contractor registration # on 4-19-11 @ 2:25pm
|
Routing - PLAN CHECK | 2/17/2011 | | 4/19/2011 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 4/6/2011 | | DONE |
Tisha Gallop
|
|
|
received revised buiding permit application (includes revised cert of value) and two copies of plan sheets a0.01, a1.00, a1.01; taken to Carl Madsen.
|
Routing - PLAN CHECK | 2/10/2011 | | 2/17/2011 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 2/17/2011 | | FAIL |
|
|
|
Waiting for a reply from the architect about changes to the plan 2-17-11 CDM
|
Plans ACCEPTED BY PLAN TECH | | | 2/10/2011 | | DONE |
|
|
|
ok per Carl Madsen for level 1 intake
|
Recd Pcfee & Taken To Pln CK | | | 2/10/2011 | | DONE |
|
|
|
|
Application received | | 2/10/2011 | | | |
|
|
|
|