Telephone call | | | 8/2/2011 | | DONE |
Tisha Gallop
|
|
|
per Matt Smith/HC Company send bill for final value fees to Owner Trinity Property Consultants, 834 E. 9400 S. Suite 54, Sandy, UT 84094.
|
First Notice | | 6/16/2011 | 6/27/2011 | | DONE |
|
|
|
|
BLD-Final | 6/6/2011 | 6/6/2011 | 6/6/2011 | A | PASS |
Tom Arcoraci
|
|
|
Please call 1/2 hour upon arrival, thanks! Phone #: ###-#### >> Inspection requested via web by Darren Gossett
|
Zoning Approval | 6/6/2011 | 6/6/2011 | 6/6/2011 | | DONE |
Susan Riggs
|
|
|
|
Permanent Occupancy | | | 6/6/2011 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 5/27/2011 | 6/1/2011 | 6/1/2011 | P | NR |
Jim Sly
|
|
|
darrin Phone #: ###-#### NR..... See previous note. Verified that fire life, fire sprinkler, and zoning has signed off for final on the bld-10 shell permit that is required to be signed off prior to th T I final. Public works (the only final left) has a correction for some grading etc which will be re-inspected on Fri. june3 at 2:00 if everything goes as planned.
|
FIRE-Final Inspection | 6/1/2011 | 6/1/2011 | 6/1/2011 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 5/27/2011 | 5/31/2011 | 5/31/2011 | A | PART |
Forrest France
|
|
|
Fire life safety inspection passed after two EM lights repaired while on site. Final approval pending project related fire alarm permit final as noted.
|
Telephone call | | | 5/19/2011 | | DONE |
Sam Zahorka
|
|
|
Agency Sign-offs identified as: Public Works, Planning & Zoning?, Fire Life Safety to obtain Final for BLD10-00109. Spoke with Tom Arcoraci the structural inspector. Building owner needs to complete outstanding shell permits prior to T.I. C of O.
|
BLD-Other | 5/12/2011 | 5/13/2011 | 5/13/2011 | A | PASS |
Tom Arcoraci
|
|
|
Please call 1/2 hour prior upon arrival, thanks! Phone #: ###-#### >> Inspection requested via web by Darren Gossett
|
BLD-Conference | 5/9/2011 | 5/9/2011 | 5/9/2011 | P | PASS |
Tom Arcoraci
|
|
|
Please call 1/2 hour upon arrival, thanks! Phone #: ###-#### >> Inspection requested via web by Darren Gossett
|
BLD-Other | 5/5/2011 | 5/6/2011 | 5/6/2011 | A | PASS |
Tom Arcoraci
|
|
|
darren - ceiling grid Phone #: ###-#### ok in outside area
|
BLD-Framing/Rough-in | 4/21/2011 | 4/22/2011 | 4/22/2011 | A | PASS |
Tom Arcoraci
|
|
|
Darren Phone #: ###-#### wip ok
|
BLD-Energy code compliance | 4/14/2011 | 4/15/2011 | 4/15/2011 | P | PART |
Tom Arcoraci
|
|
|
Please call 1/2 hour upon arrival, thanks! Phone #: ###-#### >> Inspection requested via web by Darren Gossett
|
BLD-Framing/Rough-in | 4/13/2011 | 4/13/2011 | 4/13/2011 | P | PART |
Tom Arcoraci
|
|
|
darrin Phone #: ###-#### ext wall parts of others ok
|
Issue PAID IN FULL permit | | | 4/13/2011 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (SRZ) | 2/23/2011 | 2/23/2011 | 4/12/2011 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 4/4/2011 | | 4/12/2011 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2011 | | DONE |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 4/12/2011 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 4/12/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/12/2011 | | DONE |
|
|
|
|
Telephone call | | | 4/12/2011 | | DONE |
|
|
|
4-12-11 called Joe permit ready and fee given ///dld
|
Plan resubmittals received | | | 4/7/2011 | | DONE |
Tisha Gallop
|
|
|
received transmittal and two copies of plan sheets G1.1, A1.1, A3.1, M1.0; taken to Sam Zahorka.
|
Route to Impact Fee Review | 4/1/2011 | 4/6/2011 | 4/4/2011 | | PASS |
Cindy M. Gould
|
|
|
Change of use to a Mercantile Retail Business. No impact fees
|
Routing - FIRE | 4/1/2011 | 4/1/2011 | 4/4/2011 | | PASS |
Scott Arellano
|
|
|
Please, see attached review.
|
1st review completed | | | 4/4/2011 | | DONE |
|
|
|
Failed - ESC
|
Case Summary (BLD) | | | 4/1/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/29/2011 | | 4/1/2011 | | FAIL |
Sam Zahorka
|
|
|
Routed to Fire. Corrections have been requested.
|
Routing - Erosion and Sediment | 3/29/2011 | | 3/29/2011 | | PASS |
Steven Webb
|
|
|
ESC plan waiver request is approved according to the ESC Plan Review Conditions. ESC11-00089
|
Routing - PLANNING | 3/28/2011 | | 3/28/2011 | | PASS |
Susan Riggs
|
|
|
|
Routing - PLAN CHECK | 3/9/2011 | | 3/28/2011 | | PEND |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 3/24/2011 | | |
Barbara Stitt
|
|
|
Received 1 cover transmittal, 2 copies of structural calcs, 2 copies sheets S5.2, S1.2, A3.1, A1.1, G1.1, E-3, E-2, E-1, E-0, P-1.0, M-3.0, M-2.0, M-1.0 inserted into plans by architects office and returned to Sam Zahorka's desk.
|
1st review completed | | | 3/9/2011 | | DONE |
Sam Zahorka
|
|
|
Plan review will recommence once resubmittals are received. 1st review has been completed and the architect Mr. Joe Thompson has been notified. SRZ
|
Routing - PLAN CHECK | 3/1/2011 | | 3/9/2011 | | FAIL |
Sam Zahorka
|
|
|
Plan review pending updated construction documents per the design professional. Plan review will recommence once resubmittals are received. 1st review has been completed and the architect Mr. Joe Thompson has been notified. SRZ
|
Routing - FIRE | | | 3/9/2011 | | FAIL |
Scott Arellano
|
|
|
Failed building plan review due to significant changes to construction documents per the registered design professional. Plan review will recommence once resubmittals are received. 1st review has been completed and the architect Mr. Joe Thompson has been notified. SRZ
|
Telephone call | | | 3/1/2011 | | DONE |
Sam Zahorka
|
|
|
The architect Joe Thomson called me and requested a time frame status. I explained his plans are still routing through the departments and I have not yet recieved them. He stated the owners have added some mechanical changes and some structural issues have been identified after the initial submittals. I requested plan modifications for these items. I let him know I would contact him ounce his plans are routed to me to discuss further.
|
Routing - Design Review | 3/1/2011 | | 3/1/2011 | | PASS |
Andrea Tuning
|
|
|
The applicant obtained a Zoniing Certificate (CZC11-00013) to install an overhead door in the rear elevation.
|
Routing - Erosion and Sediment | 2/25/2011 | | 3/1/2011 | | FAIL |
Steven Webb
|
|
|
Documents did not include an ESC plan or plan waiver which is required by BMC 8-17. Re-submittal is required.
|
Routing - PLANNING | 3/1/2011 | | 3/1/2011 | | FAIL |
Scott Spjute
|
|
|
Susan Riggs - CUP11-00002 P&Z hearing on March 7th plus 10 day appeal period
|
Routing PW Sewer Rating | 2/25/2011 | | 2/25/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 2/23/2011 | | 2/25/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Plan resubmittals received | | | 2/24/2011 | | |
|
|
|
received 2 copies of sheets G1.1,A1.1,A2.1,A8.1 inserted and sent to Sam Z
|
Routing - Addressing | 2/24/2011 | | 2/24/2011 | | PASS |
Terry Records
|
|
|
Changed Address from 5100 as submitted to 5326.
|
Application received | | 2/10/2011 | 2/23/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/23/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 2/23/2011 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/23/2011 | | DONE |
Barbara Stitt
|
|
|
|
Pending Assignment by JCB | 2/23/2011 | | 2/23/2011 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 2/23/2011 | | DONE |
Jason Blais
|
|
|
Contacted architect represtentative Joe Thompson to have him contact ACHD to verify if any additional impact fees are due. Verification from ACHD will need to be provided to our Permit Counter prior to permit issuance.
|