BLD-Final | 8/12/2011 | 8/15/2011 | 8/15/2011 | A | PASS |
Jim Sly
|
|
|
Hank Bothman Phone #: ###-#### C/C issued.
|
DOC - Permit Finaled | 8/15/2011 | 8/15/2011 | 8/15/2011 | P | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 8/5/2011 | 8/5/2011 | 8/5/2011 | P | NR |
Tony Young
|
|
|
devon Phone #: ###-####,, need trades 1st,,, wanted a final,,, no inspection made
|
BLD-Conference | 7/25/2011 | 7/25/2011 | 7/25/2011 | P | PASS |
Jim Sly
|
|
|
Devin ###-#### insp of ceiling grid and 1 hr wall (exterior) above front soffit at entry.
|
BLD-Conference | 7/19/2011 | 7/19/2011 | 7/19/2011 | P | DONE |
Mike Jordan
|
|
|
deven Phone #: ###-####. Must maintain continuity at 2hr. firewall.
|
BLD-Framing/Rough-in | 6/30/2011 | 7/1/2011 | 7/1/2011 | A | PART |
Jim Sly
|
|
|
Devon Phone #: ###-#### Interior walls and double sheetrock above ceiling between joists OK... Main floor.
|
BLD-Framing/Rough-in | 6/20/2011 | 6/21/2011 | 6/21/2011 | A | PART |
Jim Sly
|
|
|
Devon Phone #: ###-#### Framing and modified 2hr wall OK at 2nd floor.....and framing OK at bottom of stairway area 1st floor.
|
BLD-Conference | 6/6/2011 | 6/7/2011 | 6/7/2011 | A | PASS |
Jim Sly
|
|
|
Devon Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/2/2011 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 5/25/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/25/2011 | | DONE |
|
|
|
|
Telephone call | | | 5/25/2011 | | DONE |
|
|
|
5-25-11 called left message for Nicole permit ready and fee given. Also need GC ///dld
|
Plan assigned to (DRS) | 2/22/2011 | | 5/24/2011 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLANNING Land Div | 5/11/2011 | | 5/24/2011 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLAN CHECK | 5/24/2011 | | 5/24/2011 | | PASS |
Dan Stuart
|
|
|
Plans approved by Planning Land Division. Routing to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2011 | | PASS |
|
|
|
|
Telephone call | | | 5/11/2011 | | DONE |
|
|
|
Nicole called to say that the lot line adjustment had been completed per her understanding and ask status of the permit.I took the plans to Todd in Planning Land Division to see if all was complete and plans could be approved.
|
Routing - PLAN CHECK | 3/14/2011 | | 5/11/2011 | | PEND |
Dan Stuart
|
|
|
Plans routed to Planning Land Div. for re-review.
|
1st review completed | | | 3/14/2011 | | FAIL |
|
|
|
Failed Planning, Plan Check
|
Routing - FIRE | 3/10/2011 | | 3/14/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 2/24/2011 | | 3/10/2011 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Copy of plan review report e-mailed to architect. Plans routing to fire code analyst.
|
Plan resubmittals requested | | | 3/10/2011 | | DONE |
|
|
|
Copy of plan review report to architect requesting resubmittals.
|
Routing - PLANNING Land Div | 2/22/2011 | | 2/24/2011 | | FAIL |
Todd Tucker
|
|
|
The existing church and several out buildings are built over existing property lines. Prior to issuance of a Building Permit the following parcels must be consolidated into one buildable parcel:
R4767440031
R4767440041
S1101223315
This requires a Record of Survey application to be reviewed and approved by Boise City Subdivision Staff.
|
Application received | | 2/14/2011 | 2/22/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 2/22/2011 | | DONE |
|
|
|
Called and left a message for Nicole concerning the property line that extends through a portion of the Cole Community Church based on the current aerial view availalbe. Plans were routed to Planning Land Div to see if property line modification may be required.
|
Routing - Erosion and Sediment | 2/22/2011 | | 2/22/2011 | | CANC |
Steven Webb
|
|
|
No ESC permit Required due to the scope of work.
|
Pending Assignment by JCB | 2/22/2011 | | 2/22/2011 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/18/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/18/2011 | | DONE |
Tisha Gallop
|
|
|
|