(BOISE - 2ND FLR REMODEL) Minor remodel to split a large office into two smaller offices in a 54,000 square foot tenant space. A vanilla finish permit was done on this area under BLD06-00865 and a minor TI to occupy the space and to expand the conference room was issued under BLD09-01452. Work to include: construction of one non-combustible full height partition wall, new light switching, new accessible door / hardware, relocate duct and diffuser, and finishes in compliance with chapter 8 of the 2006 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. PLAN MODIFICATION Sumitted 2-23-11: plan mod is to add an additional 8ft. long interior non bearing wall. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 3/27/20113/31/2011 DONE
First Notice3/4/20113/4/20113/17/2011 DONE
DetailsTony Young
FIRE-Final Inspection3/3/20113/4/20113/4/2011APASS
DetailsForrest France
Fire life safety inspection passed.
BLD-Final3/3/20113/4/20113/4/2011PPASS
DetailsTony Young
mike Phone #: ###-####
DOC - Permit Finaled3/4/20113/4/20113/4/2011PPASS
DetailsTony Young
done
Plan Reviewer's activity  2/23/2011 DONE
DetailsTim L. Woodard
Plan Modification submitted and approved to add an additional 8ft. Wall. TLW
Case Summary (BLD)  2/23/2011 DONE
DetailsTim L. Woodard
BLD-Framing/Rough-in2/17/20112/18/20112/18/2011APART
DetailsTony Young
MIKE Phone #: ###-####,, need updated plans, to match work , ok to cover
Issue PAID IN FULL permit  2/17/2011 DONE
Plan assigned to (TLW)2/14/2011 2/16/2011 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK2/14/2011 2/16/2011 PASS
DetailsTim L. Woodard
Approved as submitted. TLW
1st review completed  2/16/2011 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  2/16/2011 DONE
DetailsTim L. Woodard
Case Summary (BLD)  2/16/2011 DONE
DetailsTim L. Woodard
Inspection Record Card- Bld  2/16/2011 DONE
Permit Ready to Issue  2/16/2011 DONE
Telephone call  2/16/2011 DONE
2-16-11 called Sam left message permit ready and fee given Also need GC ///DLD
Recd Pcfee & Taken To Pln CK  2/14/2011  
Plans ACCEPTED BY PLAN TECH  2/14/2011 DONE
2-14-11 ok per Tim Woodard for level 1 intake.
Application received 2/14/2011