Third Notice | | 5/30/2011 | 6/28/2011 | | DONE |
|
|
|
|
Second Notice | | 5/21/2011 | 5/25/2011 | | DONE |
Christina Prado
|
|
|
Faxed 5-25-2011
|
First Notice | | 5/8/2011 | 5/11/2011 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 4/28/2011 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 4/26/2011 | 4/27/2011 | 4/27/2011 | A | PASS |
Dave Hannah
|
|
|
Doug Phone #: ###-####
|
FIRE-Final Inspection | 4/25/2011 | 4/26/2011 | 4/26/2011 | A | PASS |
Forrest France
|
|
|
Fire life safety okay for final. Contractor to post fire extinguisher as discussed.
|
FIRE-Conference | 4/25/2011 | 4/25/2011 | 4/26/2011 | P | DONE |
Forrest France
|
|
|
Regarding final inspection items.
|
BLD-Framing/Rough-in | 4/20/2011 | 4/20/2011 | 4/20/2011 | P | PASS |
Dave Hannah
|
|
|
Ceiling grid inspection please-Doug Karnol Phone #: ###-####
|
FIRE-Conference | 4/14/2011 | 4/14/2011 | 4/14/2011 | A | DONE |
Forrest France
|
|
|
|
FIRE-Conference | 4/4/2011 | 4/4/2011 | 4/4/2011 | A | DONE |
Forrest France
|
|
|
Regarding existing fire alarm system and location of notification appliances at the tenant area.
|
FIRE-Sprinkler Rough-in | 3/30/2011 | 3/30/2011 | 3/30/2011 | A | PART |
Forrest France
|
|
|
Ref. FIR11-00136
|
BLD-Framing/Rough-in | 3/16/2011 | 3/18/2011 | 3/18/2011 | A | PART |
Tony Young
|
|
|
doug Phone #: ###-####,, walls ok
|
Issue PAID IN FULL permit | | | 2/28/2011 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 2/24/2011 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/24/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 2/24/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 2/24/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 2/24/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/24/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 2/24/2011 | | DONE |
Tisha Gallop
|
|
|
called and left vm for Doug Simpson that permit is ready, fees, and need GC/Form/RCE
|
Plan assigned to (TLW) | 2/17/2011 | | 2/24/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 2/18/2011 | | 2/24/2011 | | PASS |
Beverly Mountain
|
|
|
Signed off approved on attachd PW Routing sheet. TLW
|
Routing - PLAN CHECK | 2/22/2011 | | 2/24/2011 | | PASS |
Tim L. Woodard
|
|
|
Approved as descriped in scope of work. Tim Woodard
|
Routing PW Sewer Rating | 2/22/2011 | | 2/22/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 2/18/2011 | | 2/18/2011 | | PASS |
Terry Records
|
|
|
|
Application received | | 2/17/2011 | 2/17/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/17/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 2/17/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/17/2011 | | PASS |
Barbara Stitt
|
|
|
|