Case Summary (BLD) | | | 3/30/2012 | | |
|
|
|
|
Second Notice | | 5/21/2011 | 5/25/2011 | | DONE |
Christina Prado
|
|
|
mailed 5/26/2011. Received by fax 5/26/11
|
First Notice | | 5/9/2011 | 5/11/2011 | | DONE |
|
|
|
|
BLD-Final | 4/29/2011 | 4/29/2011 | 4/29/2011 | A | PASS |
Jim Storey
|
|
|
final ok
|
Permanent Occupancy | | | 4/29/2011 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 4/26/2011 | 4/26/2011 | 4/27/2011 | P | CANC |
Jim Storey
|
|
|
call 1 hr prior//Doug Phone #: ###-####
|
FIRE-Final Inspection | 4/26/2011 | 4/26/2011 | 4/26/2011 | P | PASS |
Forrest France
|
|
|
Verified site conditions meet resubmital plan modifications per sheet A2.1. Life safety okayed pending approved hardware at the south exit door from the dog lounge room is provided prior to structural final.
|
FIRE-Final Inspection | 4/14/2011 | 4/14/2011 | 4/14/2011 | A | PART |
Forrest France
|
|
|
Work in progress, partial C/N items finished.
|
Plan assigned to (TLW) | 3/23/2011 | | 4/4/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 3/23/2011 | | 4/4/2011 | | PASS |
Tim L. Woodard
|
|
|
Plan modification approved. TLW
|
Case Summary (BLD) | | | 4/4/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 4/4/2011 | | DONE |
|
|
|
|
Telephone call | | | 4/4/2011 | | DONE |
|
|
|
4-4-11 called John permit ready and fee given ///dld
|
CHANGE STATUS TO (ISS) | | | 4/4/2011 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 3/23/2011 | | DONE |
|
|
|
3-23-11 Plan modification excepted for BLD11-00321 to clarify exit signs & means of egress ,add wall between food prep supply room & washing-supply room, remove existing wall in dog kennel area. Sheet affected A2.1
|
BLD-Conference | 3/15/2011 | 3/15/2011 | 3/16/2011 | P | CANC |
Jim Storey
|
|
|
Doug ###-#### arck to submit back to 301 for aproval.
|
FIRE-Conference | 3/10/2011 | 3/10/2011 | 3/15/2011 | P | DONE |
Forrest France
|
|
|
On site meeting with property manager and structural inspector regarding conditions for occupancy approvals,
|
FIRE-Final Inspection | 3/4/2011 | 3/7/2011 | 3/10/2011 | P | NR |
Forrest France
|
|
|
Mandi ###-####- Reinspection with structural on site-
|
BLD-Final | 3/3/2011 | 3/7/2011 | 3/7/2011 | P | DONE |
Mike Jordan
|
|
|
Mandi Phone #: ###-#### or Doug at ###-####. On site conferance with Forest and tenant. Tenant wants to have occupant load reduced to reduce number of exits, building is not have fire sprinklers, thus 75ft. travel distance making the doors in back required exits, door hardware needs to comply, also will need to be able to exit the dog run in back out of the back required exits.
|
FIRE-Final Inspection | 3/3/2011 | 3/4/2011 | 3/4/2011 | A | FAIL |
Forrest France
|
|
|
On site discussion with tenant regarding several items including door hardware, exit signs, EM lighting, occupant load, plan review, etc.
|
Permit Ready to Issue | | | 3/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 3/3/2011 | | DONE |
Barbara Stitt
|
|
|
Called John Price and told him that permit is ready, fees due and need GC and GC registration #, on 3-3-11 @ 9:30am//BAS
|
Issue PAID IN FULL permit | | | 3/3/2011 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 2/18/2011 | | 3/2/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 2/18/2011 | | 3/2/2011 | | PASS |
Tim L. Woodard
|
|
|
Approved as redlined. TLW
|
Routing - FIRE | | | 3/2/2011 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 3/2/2011 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/2/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 3/2/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 3/2/2011 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/18/2011 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/18/2011 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 2/18/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | 2/18/2011 | | | |
|
|
|
|