Print Statement | | | 1/6/2012 | | DONE |
|
|
|
|
Third Notice | | 12/21/2011 | 12/12/2011 | | DONE |
|
|
|
|
Third Notice | | 11/26/2011 | 12/7/2011 | | DONE |
|
|
|
faxed
|
Second Notice | | 11/17/2011 | 11/21/2011 | | DONE |
|
|
|
|
First Notice | | 10/22/2011 | 11/7/2011 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 10/14/2011 | 10/14/2011 | 10/14/2011 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 10/12/2011 | | DONE |
|
|
|
|
BLD-Final | 9/13/2011 | 9/14/2011 | 9/13/2011 | A | PASS |
Tom Arcoraci
|
|
|
mark please call before going out as he needs to be there. Phone #: ###-#### ok for perm occ when others sign perm
|
FIRE-Final Inspection | 9/9/2011 | 9/9/2011 | 9/9/2011 | A | PASS |
Forrest France
|
|
|
|
BLD-Final | 9/9/2011 | 9/9/2011 | 9/9/2011 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mark Bowen
|
BLD-Framing/Rough-in | 7/18/2011 | 7/18/2011 | 7/18/2011 | P | PASS |
Tom Arcoraci
|
|
|
Approved Plans on site in greenhouse. Insulation and drywall due to start Tuesday morning. Call me with any questions or concerns. Phone #: ###-#### >> Inspection requested via web by Mark Bowen
|
BLD-Conference | 6/14/2011 | 6/14/2011 | 6/14/2011 | P | PASS |
Tom Arcoraci
|
|
|
Ask for Kevin. The subject is the methodology of installing the roof panels, liner panels and insulation so as to not circumvent the energy code inspection process. Phone #: ###-#### >> Inspection requested via web by Mark Bowen
|
BLD-Foundation | 5/25/2011 | 5/26/2011 | 5/26/2011 | A | PASS |
Tom Arcoraci
|
|
|
We would prefer late morning around 11:00 if that is possible.
Thank you Phone #: ###-#### >> Inspection requested via web by Mark Bowen
|
BLD-Footing | 5/17/2011 | 5/18/2011 | 5/18/2011 | P | PART |
Mike Jordan
|
|
|
>> Inspection requested via web by Mark Bowen. inspected by 408.
|
BLD-Footing | 5/13/2011 | 5/16/2011 | 5/16/2011 | A | CANC |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mark Bowen Inspection cancelled from web by: Mark Bowen
|
Issue PAID IN FULL permit | | | 5/13/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 5/12/2011 | | 5/12/2011 | | PASS |
Scott Arellano
|
|
|
Attached revised IFC comments to plans
|
Routing - PLAN CHECK | 5/12/2011 | | 5/12/2011 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/12/2011 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 5/12/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/12/2011 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 5/12/2011 | | DONE |
Christina Prado
|
|
|
Called and spoke with Dana from insight Architects. Advised he needed Rp and ACHD letter prior to issuance. Also gave fees due
|
Routing - PLAN CHECK | 4/29/2011 | | 5/12/2011 | | |
John Menard
|
|
|
|
Plan assigned to (JCM) | 3/2/2011 | | 5/12/2011 | | PASS |
John Menard
|
|
|
|
Plan resubmittals received | | | 5/11/2011 | | DONE |
|
|
|
Received 1 transmittal, and 2 copies of sheet AS.1 sent to John M.
|
Meeting | | | 5/6/2011 | | DONE |
Scott Arellano
|
|
|
*5/5//11* The Fire Marshal has evaluated the location for the proposed building and concurs that the requirements of IFC section 503.1.1 will be required for this building. The architect has been in contact with the Fire Marshal and has indicated his intention of submitting a revised site plan which will meet this requirement; by extending FD roadways to within 150 feet of all exterior portions of the proposed commercial building.
|
Telephone call | | | 5/3/2011 | | DONE |
Scott Arellano
|
|
|
Spoke with Dana Kaufman regarding remaining resubmittal item pertaining to the required FD access roadway extending to within 150 feet of the furthest exterior portion of this unsprinklered building.
|
Telephone call | | | 5/3/2011 | | DONE |
|
|
|
Requested onsite evaluation by the Boise City Fire Marshal.
|
Plan Reviewer's activity | | | 4/29/2011 | | PASS |
John Menard
|
|
|
Reviewed and approved structural and nonstructural revisions and resubmittals. JCM
|
Routing - FIRE | 4/29/2011 | | 4/29/2011 | | FAIL |
Scott Arellano
|
|
|
Not all resubmittal items addressed by Architect. Faxed and emailed remaining resubmittal item to architect for plan correction.
|
Routing - PLAN CHECK | 3/30/2011 | | 4/29/2011 | | PASS |
John Menard
|
|
|
|
Plan resubmittals received | | | 4/26/2011 | | |
Barbara Stitt
|
|
|
Received 1 copy of transmital letter, 1 copy of letter to Scott Arellano dated 4-18-11 from Dana Kaufman, 1 copy of letter to John Menard dated 4-18-11 from Dana Kaufman, 1 copy of letter to Jason Blais dated 4-18-11 from Dana Kaufman, 2 copies of supplemental structural Calcs, suplemental truss calcs, Structural review response comments, thermaglas calcs, thermaglas report, 2 copies of sheets A0.1, C1.0, AS.1, A2.0, A2.1, A3.0, A5.0, A7.1, A7.2 inserted by architects office and taken back to John Menards desk.
|
Routing - FIRE | 3/28/2011 | 3/28/2011 | 3/30/2011 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 3/30/2011 | | FAIL |
|
|
|
Failed Structural, Plan Check, Fire
|
Route to Impact Fee Review | 3/28/2011 | 3/31/2011 | 3/28/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals requested | | | 3/28/2011 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing - PLAN CHECK | 3/10/2011 | | 3/28/2011 | | FAIL |
John Menard
|
|
|
|
Route to Impact Fee Review | 3/2/2011 | 3/7/2011 | 3/16/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 3/2/2011 | | 3/10/2011 | | FAIL |
John Menard
|
|
|
Called Action Couriers for pick up on 3-2-11 @ 2:10pm - Received comment list from consulting structural engineer requesting revisions. JCM
|
Routing - PLANNING | 3/9/2011 | | 3/10/2011 | | PASS |
Josh Wilson
|
|
|
DRH10-006268-Josh Wilson
|
Plan resubmittals requested | | | 3/10/2011 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
Routing - PLUMBING | 3/4/2011 | | 3/9/2011 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 3/2/2011 | | 3/4/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 3/4/2011 | | 3/4/2011 | | PASS |
Steven Webb
|
|
|
ESC11-00097 plan approved per the attached conditions.
|
Routing PW Drainage | 3/3/2011 | | 3/4/2011 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Rating | 3/4/2011 | | 3/4/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 3/3/2011 | | 3/3/2011 | | PASS |
Terry Records
|
|
|
Address was changed from 5369 to 5305
|
Application received | | 3/2/2011 | 3/2/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/2/2011 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/2/2011 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLANNING Land Div | 3/2/2011 | | 3/2/2011 | | PASS |
Dave Abo
|
|
|
Parcel over 5 acres in size.
|
Pending Assignment by JCM | 3/2/2011 | | 3/2/2011 | | DONE |
John Menard
|
|
|
|