Permit Information
Permit NumberBLD11-00397
StatusFinaled
Name LYDIA MERRILL
Site Address 615 S 9TH ST
Project NameMARDI GRAS
Customer Number 
ePlanReviewNo
Description
(MARDI GRAS BALLROOM - NEW NORTHEAST ENTRANCE - STRUCTURAL AND SAFETY UPGRADES - CZC11-00023) This building is not fire sprinklered. To perform structural and safety upgrades in the Northeast corner of an existing 11,686 square foot assembly building. Work is to include a concrete footing to stabilize an existing footing and foundation, compacted fill, concrete slab on grade, wood stud parapets, wood beams, wood column and trimmers, re-built wood joist floor system, roof cricket, double leaf exterior door with sidelights, masonry infill wall, concrete infill foundation, a masonry shear wall, a new 2 riser interior stairway, exterior finishes, and interior finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. Concrete, masonry, welding, soil compaction, and epoxy anchors all require Special Inspection. This permit does NOT establish a Certificate of Occupancy for this building. The Certificate of Occupancy will be established under permit BLD09-01470 after the work authorized under that permit and this permit is completed and approved. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  3/11/2013 DONE
BLD-Final12/3/201212/4/201212/4/2012APASS
DetailsDave Hannah
per your request
FIRE-Final Inspection12/3/201212/3/201212/3/2012PPASS
DetailsForrest France
Scope of work completed. Correction items verified for compliance. Fire life safety passed.
FIRE-Conference10/3/201210/3/201210/3/2012PDONE
DetailsForrest France
On site meeting with building owner and Capt. Goldsmith regarding project status and items needed for final. Approved plan set not available on site.
BLD-Final9/11/20129/12/20129/12/2012APART
DetailsDave Hannah
Tim Phone #: ###-#### walked project with tim ever close needs to get a fire life saftey inspection.
BLD-Conference8/24/20128/24/20128/24/2012PPEND
DetailsDave Hannah
Status? talked with tim today he is working on hand rails hopes to get finals some time next week?
BLD-Final8/6/20128/15/20128/16/2012PPEND
DetailsDave Hannah
Status? see history
BLD-Conference8/1/20128/1/20128/1/2012APEND
DetailsDave Hannah
Dave and I reviewed current status with owner. Lacking handrail and hardwired exit sign for final inspection (about 2 weeks).
BLD-Framing/Rough-in12/6/201112/6/201112/7/2011PPASS
DetailsDave Hannah
Don or Tim Phone #: ###-####
Case Summary (BLD)  11/25/2011 DONE
DetailsTisha Gallop
BLD-Framing/Rough-in9/27/20119/28/20119/28/2011APASS
DetailsDave Hannah
Tim Phone #: ###-#### last grouting of cmu wall ok
BLD-Framing/Rough-in9/23/20119/26/20119/26/2011APASS
DetailsDave Hannah
ken Phone #: ###-#### cmu 3rd lift ok to grout
BLD-Framing/Rough-in9/22/20119/23/20119/23/2011APART
DetailsDave Hannah
IN fill--Tim Phone #: ###-#### cmu ok to grout second lift
BLD-Framing/Rough-in9/21/20119/22/20119/22/2011APART
DetailsDave Hannah
Brick Wall-Tim Phone #: ###-#### ok to grout first lift
BLD-Footing8/18/20118/19/20118/19/2011APART
DetailsDave Hannah
kim Phone #: ###-#### ok to pour floor slab ,stem wall and column pad
Received Certificate of Value  7/29/2011 DONE
DetailsTisha Gallop
received revised cert of value with electrical value on it, see scanned document.
Issue PAID IN FULL permit  7/29/2011 DONE
DetailsTisha Gallop
Routing - PLAN CHECK6/20/2011 7/27/2011 PASS
DetailsCarl Westfall
Drawings approved after the resubmittal review.
Plan assigned to (CJW)5/27/2011 7/27/2011 PASS
DetailsCarl Westfall
PLANS/APPL TAKEN TO FRONT DESK  7/27/2011 DONE
Inspection Record Card- Bld  7/27/2011 DONE
Permit Ready to Issue  7/27/2011 DONE
DetailsTisha Gallop
Telephone call  7/27/2011 DONE
DetailsTisha Gallop
called Tim Merrill and left vm permit is ready, fees, need GC/RCE/form and need electrical initial value.
Plan resubmittals received  7/19/2011 DONE
DetailsTisha Gallop
received two copies of plan sheets 4 & 8; put on Carl Westfall's desk.
Route to Impact Fee Review6/17/20116/22/20116/21/2011 PASS
DetailsCindy M. Gould
Improvement of existing building no new sq footage
Routing - FIRE6/17/20116/17/20116/20/2011 PASS
DetailsTim Frost
Please, see attached review
1st review completed  6/20/2011 DONE
Failed - Plan Check
Routing - PLAN CHECK5/31/2011 6/17/2011 FAIL
DetailsCarl Westfall
The IBC plan review was started on June 13 and was finished on June 17 (5 days). Revised drawings were required. See the plan review report.
Routing - Erosion and Sediment5/27/2011 5/31/2011 PASS
DetailsSteven Webb
ESC plan waiver request is approved according to the ESC Permit conditions. ESC11-00320
Routing - Design Review5/31/2011 5/31/2011 PASS
DetailsJosh Wilson
Josh Wilson - CZC11-00023
Pending Assignment by JCB5/27/2011 5/27/2011 DONE
DetailsJason Blais
Application received 3/2/20115/26/2011 DONE
DetailsTisha Gallop
Intake Approval  5/26/2011 PASS
DetailsTim L. Woodard
Plans ACCEPTED BY PLAN TECH  5/26/2011 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  5/26/2011 DONE
DetailsTisha Gallop
Intake Approval  3/16/2011 FAIL
Intake Approval  3/8/2011 FAIL
DetailsTim L. Woodard
Applicant wasn't ready. Didn't have anything filled out. I looked over the plans and also sent him to planning. He needed a CZC due to creating new arches in previously solid walls. Collen Carroll gave him apps and discussed plan submittal to planning. TLW
BLD-Conference10/31/201211/1/2012 P 
DetailsDave Hannah
Status? Remaining requirements and time frame for completion?
BLD-Conference6/29/20127/2/2012 P 
DetailsDave Hannah
Status?