(1617 & 1619 N BLUFF ST) Permit for the construction of a new 2,534 sq. ft., two story (first story 1,936 sq. ft., second story 598 sq. ft.) Duplex. Unit 1617 is 1,346 sq. ft. and consists of 2 bedrooms, 2 bathrooms, approximately 35 sq. ft. of covered patio/porch and a 294 sq. ft. attached garage. Unit 1619 is 1,188 sq. ft. and consists of 2 bedrooms, 2 bathrooms, approximately 115 sq. ft. of covered patio/porch and a 294 sq. ft. attached garage. All work per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/8/201111/8/201111/8/2011APASS
DetailsTom Arcoraci
DOC - Permit Finaled11/8/201111/8/201111/8/2011PPASS
DetailsTom Arcoraci
BLD-Final11/7/201111/8/201111/8/2011ACANC
DetailsTom Arcoraci
jared Phone #: ###-####
BLD-Energy code compliance7/13/20117/13/20117/13/2011PPASS
DetailsTom Arcoraci
jared Phone #: ###-####
BLD-Framing/Rough-in7/8/20117/8/20117/8/2011PPASS
DetailsTom Arcoraci
jared Phone #: ###-####
BLD-Framing/Rough-in5/18/20115/18/20115/18/2011PPART
DetailsTom Arcoraci
Sheet rock-- Jarrod Phone #: ###-####
BLD-Footing4/19/20114/19/20114/20/2011PPASS
DetailsTom Arcoraci
Early afternoon--Bart Phone #: ###-####
Issue PAID IN FULL permit  4/14/2011 DONE
DetailsChristina Prado
Route to Impact Fee Review3/11/20113/16/20114/13/2011 PASS
DetailsCindy M. Gould
Inspection Record Card- Bld  4/13/2011 DONE
Permit Ready to Issue  4/13/2011 DONE
Telephone call  4/13/2011 DONE
4-13-11 called Clive permit ready and fee given ///dld
Plan assigned to (CDM) 3/11/20114/12/2011 PASS
DetailsCarl D Madsen
Case Summary (BLD)  4/12/2011 DONE
PLANS/APPL TAKEN TO FRONT DESK  4/12/2011  
Routing - PLAN CHECK4/11/2011 4/11/2011 PASS
DetailsCarl D Madsen
Hanger attached through the sheetrock at the second story requires a letter from the engineer for the reduction in carrying capacity for confirmation that the proposed hanger is sufficient. 4-11-11 CDM
Routing - PLANNING4/11/2011 4/11/2011 PASS
DetailsSusan Riggs
Plan resubmittals received  3/29/2011  
DetailsCarl D Madsen
Received 2 copies of sheet A1 and taken to Carl Madsen
1st review completed  3/25/2011 FAIL
Failed pending planning CDM
Routing - PLAN CHECK3/17/2011 3/25/2011 FAIL
DetailsCarl D Madsen
fail pending planning CDM
Plan resubmittals received  3/21/2011 DONE
DetailsChristina Prado
Received two new complete sets of plans showing changes in set backs, foundation plan and floor framing plans. Routed to Planning for review
Routing - MECHANICAL3/14/2011 3/17/2011 PASS
DetailsTroy James
Routing - PLANNING3/14/2011 3/14/2011 FAIL
DetailsColleen T Carroll
Needs Duplex Approval
Routing - Addressing3/11/2011 3/14/2011 PASS
DetailsTerry Records
Assigned new number of 1617 N. Bluff St to unit on south side.
Routing - PUBLIC WORKS3/14/2011 3/14/2011 PASS
DetailsConnie Baumgartner
Intake Approval  3/14/2011 FAIL
DetailsTisha Gallop
Initial intake should have failed due to no zoning approval for duplex, per JCB continue routing plans.
Plans ACCEPTED BY PLAN TECH  3/11/2011 DONE
DetailsChristina Prado
Intake Approval  3/11/2011 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  3/11/2011 DONE
DetailsChristina Prado
Application received 3/11/2011