BLD-Final | 5/12/2011 | 5/13/2011 | 5/13/2011 | P | PASS |
Tony Young
|
|
|
Please call Dan Appel for garage access code ###-#### >> Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 5/13/2011 | 5/13/2011 | 5/13/2011 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 5/11/2011 | 5/12/2011 | 5/12/2011 | P | NR |
Tony Young
|
|
|
Please call Dan Appel for garage access code ###-#### >> Inspection requested via web by Daniel Appel
|
BLD-Energy code compliance | 4/12/2011 | 4/13/2011 | 4/14/2011 | P | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 4/11/2011 | 4/12/2011 | 4/13/2011 | P | PASS |
Tony Young
|
|
|
Plumbing and electrical rough-ins signed off. Mechanical rough-in reinspection in the AM.
Dan Appel Phone #: ###-#### >> Inspection requested via web by Daniel Appel
|
Routing - MECHANICAL | 4/6/2011 | | 4/6/2011 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 4/6/2011 | | |
Troy James
|
|
|
Recieved Manual J
|
Telephone call | | | 4/6/2011 | | DONE |
|
|
|
emailed report back to rick with diamond heating
|
BLD-Other | 4/1/2011 | 4/4/2011 | 4/4/2011 | A | PART |
Tony Young
|
|
|
Dan Phone #: ###-####,, ext shear ok
|
BLD-Foundation | 3/23/2011 | 3/24/2011 | 3/25/2011 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 3/23/2011 | 3/23/2011 | 3/23/2011 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/17/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing Walk-In (BLD) | 3/14/2011 | 3/14/2011 | 3/16/2011 | P | DONE |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 3/14/2011 | 3/14/2011 | 3/16/2011 | | PASS |
Perry Paine
|
|
|
|
Routing - MECHANICAL | 3/14/2011 | | 3/16/2011 | | PASS |
Troy James
|
|
|
for mechanical m-J & D.....return to Perry after approval
|
Routing - PLAN CHECK | 3/16/2011 | | 3/16/2011 | | PASS |
Perry Paine
|
|
|
|
1st review completed | | | 3/16/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2011 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/16/2011 | | |
|
|
|
|
Case Summary (BLD) | | | 3/16/2011 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/16/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/16/2011 | | DONE |
|
|
|
|
Telephone call | | | 3/16/2011 | | DONE |
|
|
|
3-16-11 called Daniel permit ready and fee given Also informed Daniel that our records show that RP expires on 3-26-11.
|
Routing Walk-In (PW Hillside) | 3/14/2011 | 3/14/2011 | 3/14/2011 | P | PASS |
Terry Records
|
|
|
Due to existing slab no footing subgrade approval is required.
|
Routing Walk-In (Zoning) | 3/14/2011 | 3/14/2011 | 3/14/2011 | P | PASS |
Colleen T Carroll
|
|
|
|
Application received | | 3/14/2011 | | | |
|
|
|
|