Permit Information
Permit NumberBLD11-00519
StatusFinaled
Name BOISE CITY PUBLIC WORKS
Site Address 11818 W JOPLIN RD
Project Name 
Customer Number 
ePlanReviewNo
Description
City Of Boise Public Works - Struvite Production Building -To construct a new 2,315 square foot, multilevel one story building with a 1,520 square foot basement and related site improvements. This building will be constructed of masonry exterior walls with steel roof structure and metal roof decking. The basement contains a storage area and structural support for the five struvite reactors. The main level contains a Product Storage Area, a Chemical Storage Area, an Electrical Room and an Entry/Walkway Area. There is a 190 sq. ft. Separator Platform mezzanine with a roof access walkway. There is also approximately 470 sq. ft. of steel bar-grate equipment inspection walkways at 20 feet above the main entry floor level. The chemical storage room contain corrosive and toxic hazardous materials that exceed the maximum allowable quantities and requires compliance with all applicable H-4 Occupancy requirements. The H-4 Occupancy portion of this building is separated into a separate fire area by a three-hour fire-resistive fire barrier wall. The H-4 Occupancy portion of this building will be fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 12/2/201312/5/2013 DONE
working with Hal on final
Second Notice 11/10/201311/27/2013 DONE
e-mailed to William Benko in PW
First Notice 10/13/201310/31/2013 DONE
BLD-Final10/2/201310/3/201310/3/2013APASS
DetailsJim Sly
Jim Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection10/2/201310/3/201310/3/2013APASS
DetailsTroy Cobbley
life safety passed
Application received 3/21/201110/3/2013 DONE
Permanent Occupancy  10/3/2013 DONE
DetailsTisha Gallop
PubWorks Occupancy Approval9/9/20139/9/20139/9/2013 DONE
DetailsTiffany Lowery
Issue PAID IN FULL permit  9/6/2013 DONE
Payment received via Govolutions
FIRE-Final Inspection9/5/20139/6/20139/6/2013AFAIL
DetailsTroy Cobbley
Provide city approved plans, provide fire extinguishers, repaire the exit signs, provide NFPA signage on the H occupancy doors, provide signage on the FACP/Electrical room doors and it appears that notes 1 - 7 have not been addressed for the ventilation.
Zoning Approval9/6/20139/6/20139/6/2013 PASS
DetailsCody Riddle
Print Occupancy Form  9/6/2013 DONE
DetailsChristina Prado
Case Summary (BLD)  7/23/2013 DONE
FIRE-Final Inspection6/10/20136/11/20136/11/2013AFAIL
DetailsTroy Cobbley
Todays inspection was a cover for the underground supply line. Everything can be covered except for the locations of the thrust blocks which are not complete. Treasure valley fire is supervising the underground installation.
FIRE-Final Inspection6/10/20136/10/20136/10/2013PCANC
DetailsTroy Cobbley
Per Jeremiah the project is not ready for inspection. Will be rescheduled for inspection on underground supply piping to the fire sprinkler system.
FIRE-Final Inspection5/30/20136/4/20136/4/2013AFAIL
DetailsTroy Cobbley
The project related fire sprinkler permit needs to be addressed which includes all aspects of the underground supply piping to the fire sprinkler system. Also no city approved plans/notes were on site for an inspection.
BLD-Other9/25/20129/26/20129/26/2012APART
DetailsJim Sly
Roof inspection-Dave Jenkins Phone #: ###-####
Not quite complete .....but what is done is OK.
BLD-Framing/Rough-in8/1/20128/2/20128/2/2012PPART
DetailsJim Sly
Dave Phone #: ###-####
Looked at ceiling joist connections to ledger and to top of wall at pop out rooms from main bldg.....West and North ends. Reviewed letter from Engineer of record as to how to make these connections........ which is different from appr. plan. Engineer has also physically inspected the connections.
BLD-Final1/25/20121/26/20121/26/2012PNR
DetailsJim Sly
dave Phone #: ###-####
Looked at roof panels prior to installation.
BLD-Foundation11/8/201111/8/201111/8/2011PPART
DetailsJim Sly
Dave Phone #: ###-####
CMU grouting North Bldg section.
BLD-Footing10/21/201110/21/201110/21/2011PPART
DetailsJim Sly
Dave Phone #: ###-####
Footing and pad North side OK pending MTI special inspection tests and approvals.
BLD-Foundation10/7/201110/10/201110/10/2011APART
DetailsJim Sly
dave Phone #: ###-####
MTI on site......
BLD-Foundation10/4/201110/4/201110/4/2011PPART
DetailsJim Sly
Dave Phone #: ###-####
BLD-Concrete9/8/20119/8/20119/8/2011PPART
DetailsJim Sly
CMU-grout rebar inspection please-Dave Jenkins Phone #: ###-####
MTI on site.
BLD-Concrete9/1/20119/1/20119/1/2011PPART
DetailsJim Sly
CMU-rebar --Dave Jenkins Phone #: ###-####
Select wall OK pending MTI special insp, tests and approvals.
BLD-Footing8/25/20118/25/20118/25/2011PPART
DetailsJim Sly
dave - rebar Phone #: ###-####
OK pending MTI insp, tests and approvals.
BLD-Other8/17/20118/18/20118/18/2011APART
DetailsJim Sly
dave - CMU walls Phone #: ###-####
OK pend MTI special insp, tests and approvals.
BLD-Framing/Rough-in8/16/20118/16/20118/16/2011PPEND
DetailsJim Sly
Dave Jenkins-CMU inspection please Phone #: ###-####
OK pending MTI special insp tests and approvals.
BLD-Other8/8/20118/9/20118/9/2011ACANC
DetailsJim Sly
cmu block insp//Dave Jenkins Phone #: ###-####
OK pending MTI inspections, tests and approvals.
BLD-Foundation8/3/20118/4/20118/4/2011APASS
DetailsTom Arcoraci
dave Phone #: ###-#### spec insp
BLD-Foundation7/25/20117/26/20117/26/2011APART
DetailsJim Sly
dave Phone #: ###-####
Portion of North wall OK pending MTI special insp, tests and approvals.
BLD-Foundation7/20/20117/21/20117/21/2011APASS
DetailsTom Arcoraci
dave Phone #: ###-#### spec insp
BLD-Foundation7/15/20117/18/20117/19/2011PPART
DetailsTony Young
Dave Phone #: ###-####,, engineer will also inspect,, walls on tank and west wall on east structure
BLD-Foundation7/13/20117/13/20117/13/2011PPART
DetailsTom Arcoraci
dave Phone #: ###-####
BLD-Foundation7/11/20117/12/20117/12/2011APART
DetailsJim Sly
DAVE Phone #: ###-####East wall......OK Pendig MTI insp, tests & approvals
BLD-Foundation7/5/20117/6/20117/6/2011APART
DetailsJim Sly
Dave Phone #: ###-####
East wall ..4' high H occupancy....and South wall Main Bldg 8' high....OK pending MTI special insp, tests and approvals. Structural Engineer and Rick Cummings (City employee) have done visual inspections with pictures.
BLD-Foundation6/27/20116/28/20116/28/2011APART
DetailsJim Sly
dave Phone #: ###-####
Wall...OK pending MTI special insp, tests and approvals. Engineer has done a visual inspection on this wall.
BLD-Footing6/13/20116/13/20116/13/2011PPART
DetailsJim Sly
dave Phone #: ###-####
OK pending MTI special inspections, tests and approvals. Footing pads for main bldg and H occupancy .
Issue PAID IN FULL permit  6/13/2011 DONE
Routing - PLAN CHECK6/9/2011 6/10/2011 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  6/10/2011 DONE
DetailsJohn Menard
Print Occupancy Form  6/10/2011 DONE
Print Occupancy Form  6/10/2011  
Print Occupancy Form  6/10/2011  
Permit Ready to Issue  6/10/2011 DONE
DetailsTisha Gallop
Telephone call  6/10/2011 DONE
DetailsTisha Gallop
called Peter Rockwell and left mssg permit is ready, fees and need ACHD.
Plan assigned to (JCM)3/28/2011 6/10/2011 PASS
DetailsJohn Menard
Routing - PLAN CHECK4/26/2011 6/9/2011 PASS
DetailsJohn Menard
Plan Reviewer's activity  6/9/2011 PASS
DetailsJohn Menard
Reviewed and approved changes to show compliance with H-4 Occupancy requirements. JCM
Routing - FIRE6/9/2011 6/9/2011 PASS
DetailsScott Arellano
Attached revised IFC comments to plans. E-mailed revised Fire Code comments to architect.
Plan resubmittals received  6/8/2011 DONE
DetailsChristina Prado
Received one copy of resubmittal letter, and two copies of plans A-0.1, A-1.1, A-1.2, A-1.3 and A-6.1. Plans inserted by Arch rep and taken back to John Menard for further review
Plan Reviewer's activity  6/2/2011 DONE
DetailsJohn Menard
E-mailed the project architect informing them that, because of the proposed quantities of hazardous materials, a portion of this building must be classified as an H-4 Occupancy. JCM
Plan resubmittals received  5/31/2011 DONE
DetailsJohn Menard
Received e-mailed copy of hazardous material inventory from the project archtect. JCM
Routing Off Site - STRUCTURAL5/20/2011 5/27/2011 PASS
DetailsJohn Menard
Called Action Courier for pick up@ 8:40am - Received letter from consulting structural engineer requesting revisions. JCM
Plan resubmittals received  5/19/2011  
DetailsBarbara Stitt
Received 3 copies of responce letter from Brian Sielaff dated 5-18-11, 3 copies of supplemental structural calcs, 3 copies of sheets S1.1, S2.1, SD1.3, SD1.4 and inserted into plans by architects office then returned to John Menards desk
Plan resubmittals requested  5/12/2011 DONE
DetailsJohn Menard
E-mailed the architect a copy of the second structural review requesting revisions. JCM
Routing Off Site - STRUCTURAL4/29/2011 5/11/2011 FAIL
DetailsJohn Menard
Called action couriers for pick up 4/29/11 - Received second comment list from the consulting engineer requesting additional revisions. JCM
Plan resubmittals received  4/29/2011 DONE
DetailsChristina Prado
Received 3 copies of response letter; three copies of stuctural calcs; and three copies of plans S0.1, S0.2, S1.0, S1.1, S1.2, S1.3, S1.4, S2.1, S2.2, S2.3, SD1.1, SD1.2, SD1.3, SD1.4, SD1.5, SD1.6. Inserted by Architect Rep. Taken to John Menard for review
Telephone call  4/29/2011 DONE
DetailsChristina Prado
Called action couriers for pick up
Routing - PLANNING4/25/2011 4/26/2011 PASS
DetailsDavid Moser
Routing - FIRE4/21/20114/21/20114/25/2011 FAIL
DetailsScott Arellano
*6/7/11* In lieu of submitted Hazardous Material informaiton addtional plan revisions will be required.
1st review completed  4/25/2011 FAIL
Failed Structural,Plan Check
Routing - PLAN CHECK4/25/2011 4/25/2011  
DetailsJohn Menard
Route to Impact Fee Review4/21/20114/26/20114/21/2011 PASS
DetailsCindy M. Gould
Plan resubmittals requested  4/21/2011 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting resubmittals. JCM
Routing - PLAN CHECK4/1/2011 4/21/2011 FAIL
DetailsJohn Menard
Plan resubmittals requested  4/19/2011 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural review requesting revisions. JCM
Routing Off Site - STRUCTURAL3/28/2011 4/19/2011 FAIL
DetailsJohn Menard
3-28-11 called Action Couriers for pick up. - Received comment list from consulting structural engineer requesting revisions. JCM
Routing - PLANNING4/1/2011 4/1/2011 FAIL
DetailsDavid Moser
CUP11-00020. Failed the plans beacuse the 10 day appeal period ends on 4-4-11. (David Moser 4-1-11)
Routing - PLUMBING3/31/2011 4/1/2011 PASS
DetailsBill VanDegrift
domestic water is piped from utilidor per plans and 2003 upc
Routing - PUBLIC WORKS3/29/2011 3/31/2011 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment3/31/2011 3/31/2011 PASS
DetailsSteven Webb
Steve ref ESC11-00059: ESC plan approved under ESC11-00059
Routing PW Sewer Rating3/30/2011 3/30/2011 PASS
DetailsConnie Baumgartner
Routing PW Drainage  3/30/2011 PASS
DetailsBrian Murphy
Plan resubmittals received  3/30/2011 DONE
DetailsTisha Gallop
received three extra copies of Civil sheets CD1.0, CD1.1; taken to Brian Murphy.
Routing - PLANNING Land Div3/28/2011 3/29/2011 PASS
DetailsDave Abo
Parcel over 5 acres in size.
Routing - Addressing3/29/2011 3/29/2011 PASS
DetailsTerry Records
CHANGE STATUS TO (REV)  3/28/2011 DONE
Recd Pcfee & Taken To Pln CK  3/28/2011 DONE
Pending Assignment by JCM3/28/2011 3/28/2011 DONE
DetailsJohn Menard