Second Notice | | 6/4/2011 | 6/13/2011 | | DONE |
Christina Prado
|
|
|
Faxed 6-13-11
|
First Notice | 5/10/2011 | 5/10/2011 | 5/25/2011 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 5/9/2011 | 5/10/2011 | 5/10/2011 | P | PASS |
Jim Storey
|
|
|
Brad Phone #: ###-####
|
DOC - Permit Finaled | 5/10/2011 | 5/10/2011 | 5/10/2011 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 5/9/2011 | 5/10/2011 | 5/10/2011 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 5/3/2011 | 5/4/2011 | 5/4/2011 | A | PART |
Jim Storey
|
|
|
Joe Phone #: ###-#### pending fire cabnet on fire sign off/ final ok on bld.
|
FIRE-Final Inspection | 5/3/2011 | 5/3/2011 | 5/3/2011 | P | PART |
Troy Cobbley
|
|
|
Joe Phone #: ###-#### A temporary occupancy was given with Scott's permission until the hazardous material cabinet, which is on order, has arrived and been placed.
|
Telephone call | | | 5/3/2011 | | DONE |
|
|
|
I told Joe that the new letter provided by Greg Patrick at TVFP was acceptable. That the building would be OK for Class III commodities but not Class IV commodities. I also reminded him that the letter indicated that all flammable liquids would be in cabinets. The cabinets would be required to be on site prior to the inspection per Troy Cobbley request.
|
FIRE-Final Inspection | 5/2/2011 | 5/2/2011 | 5/2/2011 | P | FAIL |
Troy Cobbley
|
|
|
Column protection has not been provided per IFC chapter 23 and NFPA 13 6.1.4.1. The commodity has been classified as up to IV but the density will provide for a class III per the chapter 16 table.
|
Issue PAID IN FULL permit | | | 4/21/2011 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 4/20/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/20/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 4/20/2011 | | DONE |
Tisha Gallop
|
|
|
called Joe Moulia and left vm permit is ready, fees and also that Occupancy permit Bld11-00752 is ready.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2011 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/11/2011 | | 4/19/2011 | | PASS |
Dan Stuart
|
|
|
Permit BLD11-00752 being issued to establish a certificate of occupancy for this new tenant.
|
Plan assigned to (DRS) | 4/7/2011 | | 4/19/2011 | | PASS |
Dan Stuart
|
|
|
|
Telephone call | | | 4/18/2011 | | DONE |
|
|
|
Returned call to Bob, Structural Concepts Eng. 1-###-#### concerning Mygrant Glass Inc. BLD11-00671. Question on information for new storage racks have been satisfied. The only outstanding item before permit can be issued is obtaining a new cwertificate of occupancy for the new tenant. Need to determine if any changes made which would then be a tenant improvement app and plans for work to be done or if no change than a completed application to establish a certificate of occupancy with an existing floor plan layour and room use is needed to prepare a permit to determine requirements for issuing a new C.O.
|
1st review completed | | | 4/11/2011 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - FIRE | 4/8/2011 | | 4/11/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans.
|
Plan resubmittals requested | | | 4/8/2011 | | DONE |
|
|
|
Resubmittal of completed Project Start Up For Special Inspection form required. Copy of plan review to applicant and engineer.
|
Plan Reviewer's activity | | | 4/8/2011 | | DONE |
|
|
|
Sent e-mail to applicant Joe Moulia with copy to Michael Mygrant for need to obtain a certificate of occupancy for new tenant. Referenced then to PDS on line Docs & forms to download and complete approriate application, checklist, cert of value, design professioanl of record, contractor license. etc. before the permit can be issued the tenant is required to obtain a certificate of occupancy.
|
Routing - PLAN CHECK | 4/7/2011 | | 4/8/2011 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. copy of plan review e-mailed to Engineer Bob Sharif & applicant Joe Moulia. Plans routed to fire code analyst.
|
Pending Assignment by JCB | 4/6/2011 | | 4/7/2011 | | DONE |
Jason Blais
|
|
|
|
Application received | | 4/6/2011 | 4/6/2011 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 4/6/2011 | | PASS |
|
|
|
OK to submit application.
|
Plans ACCEPTED BY PLAN TECH | | | 4/6/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/6/2011 | | DONE |
Tisha Gallop
|
|
|
|