Second Notice | | 9/18/2011 | 9/22/2011 | | DONE |
|
|
|
faxed 9/22/11
|
First Notice | | 9/5/2011 | 9/8/2011 | | DONE |
|
|
|
|
BLD-Final | 8/26/2011 | 8/26/2011 | 8/26/2011 | P | PASS |
Dave Hannah
|
|
|
Please call 20min prior if possible--Gill Phone #: ###-#### ok for perm occ
|
Permanent Occupancy | | | 8/26/2011 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/15/2011 | 6/15/2011 | 6/15/2011 | P | PASS |
Forrest France
|
|
|
Fire life safety final passed. Existing rated corridor to be maintained or provide QR type sprinklers throughout the floor level per IBC 2009.
|
BLD-Final | 6/8/2011 | 6/9/2011 | 6/9/2011 | P | PART |
Dave Hannah
|
|
|
call when on way//Gail Phone #: ###-#### ok for temp occ need to see if sidelights need to be rated or if corrador is rated or not becouse of fire sprinkler
|
FIRE-Final Inspection | 6/8/2011 | 6/9/2011 | 6/9/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Conference | 6/3/2011 | 6/3/2011 | 6/3/2011 | P | DONE |
Forrest France
|
|
|
Discussion with contractor regarding items for fire life safety final including door hardware, ceiling cover, existing duct detectors and project related fire sprinkler permit.
|
BLD-Framing/Rough-in | 6/2/2011 | 6/2/2011 | 6/3/2011 | P | PART |
Dave Hannah
|
|
|
ceiling grid only call first Gil ###-####
|
BLD-Framing/Rough-in | 5/31/2011 | 5/31/2011 | 5/31/2011 | P | NR |
Dave Hannah
|
|
|
Gil - ceiling grid - please call 1/2 hr prior so he can meet you there Phone #: ###-#### talked with gil and ceiling crew ok to install borders
|
BLD-Framing/Rough-in | 5/6/2011 | 5/6/2011 | 5/6/2011 | P | PASS |
Dave Hannah
|
|
|
gil - please call 1/2 hr prior so he can meet you there Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/4/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/27/2011 | | DONE |
Tim L. Woodard
|
|
|
Recieved minor door location changes. Issued plans.
|
Routing - PLAN CHECK | 4/27/2011 | | 4/27/2011 | | PASS |
Tim L. Woodard
|
|
|
Approved with redlines. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 4/27/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 4/27/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/27/2011 | | DONE |
|
|
|
|
Telephone call | | | 4/27/2011 | | DONE |
|
|
|
4-27-11 called William permit ready and fee given Also need GC ///DLD
|
Plan assigned to (TLW) | 4/11/2011 | | 4/27/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 4/19/2011 | | 4/26/2011 | | FAIL |
Tim L. Woodard
|
|
|
Need correction of door manuvering clearances. TLW
|
1st review completed | | | 4/26/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Routing PW Sewer Rating | 4/19/2011 | | 4/19/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 4/11/2011 | | 4/19/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 4/18/2011 | | 4/18/2011 | | PASS |
April Wing
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/11/2011 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/11/2011 | | DONE |
|
|
|
4-11-11 ok per Tim Woodard to take in as a level 2
|
Application received | | 4/11/2011 | | | |
|
|
|
|