BLD-Final | 10/5/2011 | 10/6/2011 | 10/6/2011 | A | PASS |
Dave Hannah
|
|
|
Call for access---Bruce Phone #: ###-####
|
DOC - Permit Finaled | 10/6/2011 | 10/6/2011 | 10/6/2011 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Grading Inspection | 10/6/2011 | 10/6/2011 | 10/6/2011 | A | DONE |
Terry Records
|
|
|
Final grading and drainage approved
|
BLD-Energy code compliance | 7/29/2011 | 7/29/2011 | 7/29/2011 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 7/27/2011 | 7/28/2011 | 7/29/2011 | P | PASS |
Dave Hannah
|
|
|
bruce Phone #: ###-####
|
BLD-Framing/Rough-in | 7/25/2011 | 7/27/2011 | 7/27/2011 | A | PART |
Dave Hannah
|
|
|
bruce Phone #: ###-#### ok to cover ext all but for the second floor at kitchen window area also need double trimmer at same window
|
BLD-Other | 7/12/2011 | 7/13/2011 | 7/13/2011 | A | FAIL |
Dave Hannah
|
|
|
structural steel & fire rated eaves//Bruce Wood Phone #: ###-#### eaves ok but shear failed steel colunm base ok to cover
|
BLD-Foundation | 6/7/2011 | 6/7/2011 | 6/7/2011 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 6/7/2011 | 6/7/2011 | 6/7/2011 | P | PASS |
Dave Hannah
|
|
|
wes Phone #: ###-####
|
BLD-Footing | 5/24/2011 | 5/24/2011 | 5/25/2011 | P | PASS |
Dave Hannah
|
|
|
st after lunch pouring footings at 1:30---Wes Phone #: ###-####
|
PubWorks Subgrade Approval | 5/25/2011 | 5/25/2011 | 5/25/2011 | | DONE |
Terry Records
|
|
|
footing subgrade approved by the geotechnical engineer
|
Inspection Record Card- Bld | | | 5/11/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/11/2011 | | DONE |
|
|
|
|
Telephone call | | | 5/11/2011 | | DONE |
|
|
|
5-11-11 called Steve left message permit ready and fee given ///dld
|
Issue PAID IN FULL permit | | | 5/11/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CDM) | 4/11/2011 | 4/11/2011 | 5/10/2011 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 5/10/2011 | | |
|
|
|
5-10-11 received 2 new sets of plans & 1 engineering calc sent to Carl M.
|
Routing - PLAN CHECK | 5/10/2011 | | 5/10/2011 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 5/10/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/10/2011 | | |
|
|
|
|
Routing - PLAN CHECK | 4/28/2011 | | 5/3/2011 | | FAIL |
Mike Jordan
|
|
|
All sheets related to engineering are required to be stamped. Incorrect codes referenced. Plan resubmittal is required. E-mailed and called steve hanson on 5-3-11. CDM.
|
1st review completed | | | 5/3/2011 | | FAIL |
|
|
|
|
Case Summary (BLD) | | | 5/3/2011 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/11/2011 | 4/14/2011 | 4/29/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 4/28/2011 | | 4/28/2011 | | PASS |
David Moser
|
|
|
approved as redlined, move house over 1 foot so right side eave does not extend more than 2' into setback
|
Routing PW Grading-Hillside | 4/27/2011 | | 4/27/2011 | | PASS |
Terry Records
|
|
|
Approved as Category 3 with conditions of approval in letter attached to the plans and this case
|
Routing - MECHANICAL | 4/21/2011 | | 4/21/2011 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 4/19/2011 | | 4/20/2011 | | PASS |
Scott Arellano
|
|
|
BFD has required all buildings within Boulder heights subdivision number (1) to be fire sprinklered in accordance with NFPA 13D. See subdivision plat note #19.
|
Routing - Erosion and Sediment | | | 4/19/2011 | | PASS |
Steven Webb
|
|
|
ESC11-00197 plan approved with the attached connditions.
|
Routing - MECHANICAL | 4/15/2011 | | 4/19/2011 | | FAIL |
Troy James
|
|
|
emailed corrections to designer
|
Routing - PLANNING | 4/15/2011 | | 4/15/2011 | | FAIL |
David Moser
|
|
|
Failed: Requires Cat I Hillside Approval as per public works comments
|
Routing - PUBLIC WORKS | 4/15/2011 | | 4/15/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS GRADING | | | 4/14/2011 | | FAIL |
Terry Records
|
|
|
Needs Category 1 hillside application
|
Routing - Addressing | 4/11/2011 | | 4/14/2011 | | PASS |
Terry Records
|
|
|
|
Application received | | 4/11/2011 | 4/11/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/11/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 4/11/2011 | | PASS |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/11/2011 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 4/21/2011 | | | | |
Carl D Madsen
|
|
|
Carl Madsen
|