Second Notice | | 8/4/2011 | 8/11/2011 | | DONE |
Barbara Stitt
|
|
|
|
First Notice | | 7/10/2011 | 7/25/2011 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 6/30/2011 | | DONE |
Tisha Gallop
|
|
|
permit was already finaled and reopened to modify plans. The modification was approved in the field by the building inspector 450 on 6/29/11 and another inspection is not required.
|
Reopen Permit (ISS) | | | 6/30/2011 | | DONE |
Tisha Gallop
|
|
|
reopen permit to route to TLW for field plan mod.
|
Routing - PLAN CHECK | 6/30/2011 | | 6/30/2011 | | PASS |
Tim L. Woodard
|
|
|
Field inspector Mike Jordan approved existing restroom to remain without remode. Existing restroom complied with ICC/Ansi 117.1-1998. Architect resubmitted a 8 1/2 by 11 inch as built plan of that area. The as built was sent to records to be archieved. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 6/30/2011 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 6/29/2011 | 6/29/2011 | 6/29/2011 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. ok for prerm. occ.
|
FIRE-Final Inspection | 6/24/2011 | 6/27/2011 | 6/27/2011 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed.
|
BLD-Framing/Rough-in | 6/7/2011 | 6/8/2011 | 6/8/2011 | A | PART |
Mike Jordan
|
|
|
T-grid ceiling inspection please-Jeff Rightler Phone #: ###-####. Difussers need to be wired. Will check on final. Ok to drop ceiling tile.
|
BLD-Other | 6/7/2011 | 6/7/2011 | 6/7/2011 | P | NR |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Needs mechanical and sprinkler rough ins.
|
BLD-Framing/Rough-in | 5/27/2011 | 5/31/2011 | 5/31/2011 | P | PASS |
Mike Jordan
|
|
|
jeff Phone #: ###-####> Interior steel stud walls only. No grid.
|
BLD-Other | 5/23/2011 | 5/24/2011 | 5/24/2011 | P | DONE |
Mike Jordan
|
|
|
ADA requirements inspection please-Jeff Phone #: ###-####. Contractors wants to leave existing restroom. Told contractor to resubmit plan mod. to plan review for approval.
|
Issue PAID IN FULL permit | | | 5/16/2011 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 5/3/2011 | | 5/3/2011 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 5/3/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 5/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 5/3/2011 | | DONE |
|
|
|
5-3-11 called Patrick left message with Chris permit ready and fee given ///dld
|
Permit Ready to Issue | | | 5/3/2011 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 4/12/2011 | | 5/3/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 4/29/2011 | | DONE |
Tisha Gallop
|
|
|
received response and three copies of plan sheets A1, A3; taken to Tim Woodard.
|
1st review completed | | | 4/27/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 4/14/2011 | | 4/27/2011 | | FAIL |
Tim L. Woodard
|
|
|
Refer to plan review report. Tim Woodard
|
Routing - PUBLIC WORKS | 4/12/2011 | | 4/14/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 4/14/2011 | | 4/14/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 4/13/2011 | | 4/13/2011 | | PASS |
April Wing
|
|
|
|
Application received | | 4/12/2011 | 4/12/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/12/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 4/12/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/12/2011 | | DONE |
Barbara Stitt
|
|
|
|