Permit Information
Permit NumberBLD11-00760
StatusFinaled
Name RA SCHULTZ AND COMPANY
Site Address 251 E FRONT ST Unit: 205
Project NameOne Front Street Ste # 205
Customer Number 
ePlanReviewNo
Description
(SENATOR CRAPO – One Front Street – Ste # 205) Permit is to remodel an existing 2,150 square foot office tenant by expanding 535 square feet into the adjacent tenant space. Approval contingent upon adhering to the approved plans on file and plan review report. Work to include: [installation / demolition of interior partition walls to create a larger office, larger work room, large conference room, and a server closet] and finishes in compliance with chapter 8 of the 2009 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW** 8-24-11 FINAL CERT OF VALUE PER GC $ 34,249.00 ///DLD
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 8/4/20118/16/2011 DONE
First Notice 7/25/20117/25/2011 DONE
BLD-Final7/14/20117/15/20117/15/2011PPASS
DetailsDave Hannah
Jack Phone #: ###-####
FIRE-Final Inspection7/14/20117/15/20117/15/2011APASS
DetailsForrest France
Noted correction items verified for completion. Fire life safety passed.
Permanent Occupancy UNPAID FEE  7/15/2011 DONE
DetailsChristina Prado
FIRE-Final Inspection7/14/20117/14/20117/14/2011PFAIL
DetailsForrest France
Need project related fire sprinkler permit final request, adjust exit sign directionals as discussed, door hardware at the server room should be reversed.
FIRE-Final Inspection7/11/20117/11/20117/11/2011APART
DetailsForrest France
Pending project related alarm permit work. Overhead fire sprinkler work okay for cover.
FIRE-Conference7/8/20117/8/20117/8/2011PDONE
DetailsForrest France
Regarding exit signage.
BLD-Framing/Rough-in6/10/20116/10/20116/10/2011PPASS
DetailsDave Hannah
Matt Phone #: ###-####
Issue PAID IN FULL permit  5/18/2011 DONE
DetailsChristina Prado
Plan assigned to (TLW)4/14/2011 4/28/2011 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK4/14/2011 4/28/2011 PASS
DetailsTim L. Woodard
Tim Woodard
1st review completed  4/28/2011 DONE
DetailsTim L. Woodard
Routing - PUBLIC WORKS4/28/2011 4/28/2011 PASS
DetailsConnie Baumgartner
Case Summary (BLD)  4/28/2011 DONE
DetailsTim L. Woodard
Routing - Addressing4/28/2011 4/28/2011 PASS
DetailsTerry Records
Routing PW Sewer Rating4/28/2011 4/28/2011 PASS
DetailsConnie Baumgartner
Routing - PLAN CHECK4/28/2011 4/28/2011 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  4/28/2011 DONE
DetailsTim L. Woodard
Print Occupancy Form  4/28/2011 DONE
Permit Ready to Issue  4/28/2011 DONE
Telephone call  4/28/2011 DONE
4-28-11 called Peter Rockwell permit ready and fee given ///dld
Plan resubmittals received  4/20/2011 DONE
DetailsTisha Gallop
received transmittal and two copies of plan sheet A-1.1; taken to Tim Woodard.
Application received 4/14/20114/14/2011 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  4/14/2011 DONE
DetailsBarbara Stitt
Intake Approval  4/14/2011 PASS
DetailsTim L. Woodard
Recd Pcfee & Taken To Pln CK  4/14/2011  
DetailsBarbara Stitt