BLD-Final | 6/30/2011 | 7/1/2011 | 7/1/2011 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
DOC - Permit Finaled | 7/1/2011 | 7/1/2011 | 7/1/2011 | P | PASS |
Mike Jordan
|
|
|
All issues were resolved. Residential certificate of occupancy was issued.
|
BLD-Final | 6/30/2011 | 6/30/2011 | 6/30/2011 | P | FAIL |
Mike Jordan
|
|
|
Provide blower door test results and post. Step from bacdoor to patio is 9". Needs to provide step or landing.
|
BLD-Final | 6/29/2011 | 6/30/2011 | 6/30/2011 | A | NR |
Mike Jordan
|
|
|
steve - please call for access Phone #: ###-####. Needs mech. and elec. finals.
|
BLD-Conference | 6/14/2011 | 6/14/2011 | 6/14/2011 | P | DONE |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 5/31/2011 | 6/1/2011 | 6/1/2011 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 5/31/2011 | 6/1/2011 | 6/1/2011 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 5/26/2011 | 5/27/2011 | 5/27/2011 | A | FAIL |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Provide fireblocking at all arches. Install exterior weather membrane. correction notice posted. Ok to insulate.
|
Plan resubmittals received | | | 5/23/2011 | | PASS |
|
|
|
revised manual j, changed location of return air ducting
|
BLD-Footing | 5/2/2011 | 5/2/2011 | 5/2/2011 | P | PASS |
Mike Jordan
|
|
|
LITO Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/29/2011 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 4/27/2011 | | |
|
|
|
|
Plan assigned to (CDM) | 4/15/2011 | 4/15/2011 | 4/27/2011 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 4/19/2011 | | 4/27/2011 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 4/27/2011 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/27/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2011 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/27/2011 | | DONE |
|
|
|
|
Telephone call | | | 4/27/2011 | | DONE |
Christina Prado
|
|
|
Called Steve to advise permit is ready for pick up. Gave fees due and advised RP is expired and must be resolved prior ro permit issuance
|
Permit Ready to Issue | | | 4/27/2011 | | DONE |
Christina Prado
|
|
|
|
Routing - MECHANICAL | 4/18/2011 | | 4/19/2011 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/14/2011 | 4/19/2011 | 4/18/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 4/18/2011 | | 4/18/2011 | | PASS |
Colleen T Carroll
|
|
|
Setbacks as per CUP06-11
|
Routing - Addressing | 4/15/2011 | | 4/18/2011 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | | | 4/18/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 4/14/2011 | 4/15/2011 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 4/15/2011 | | PASS |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/15/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/15/2011 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 4/14/2011 | | FAIL |
Tisha Gallop
|
|
|
|