Second Notice | | 8/4/2011 | 8/16/2011 | | DONE |
|
|
|
|
First Notice | | 7/30/2011 | 7/25/2011 | | DONE |
|
|
|
|
Permanent Occupancy | | | 7/20/2011 | | DONE |
|
|
|
|
Permanent Occupancy | | | 6/30/2011 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 6/1/2011 | 6/1/2011 | 6/1/2011 | P | PART |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Ok for temp occ. Will be ok for perm occ once plumbing finals.
|
Temporary Occupancy UNPAID FEE | | | 6/1/2011 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 5/31/2011 | 5/31/2011 | 5/31/2011 | P | FAIL |
Mike Jordan
|
|
|
jim - late afternoon please Phone #: ###-####. Install all ada signage, also no grid inspection.
|
FIRE-Final Inspection | 5/31/2011 | 5/31/2011 | 5/31/2011 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed.
|
FIRE-Conference | 5/31/2011 | 5/31/2011 | 5/31/2011 | A | DONE |
Forrest France
|
|
|
Discussion with contractor regarding items for final including repair two exit sign/EM lights, post max. occupant load sign, post PFE with current tag, add one exit sign per plan at restroom hall, test EM lights at grid ceilings, provide verification fire sprinkler system is current with an annual inspection.
|
BLD-Framing/Rough-in | 5/12/2011 | 5/12/2011 | 5/12/2011 | A | PART |
Mike Jordan
|
|
|
Phone #: 5413312871 >> Inspection requested via mobile web by jim wellman. Interior steel stud framed walls only, no grid and pending elec. inspection. Also needs to provide engineering showing that the existing roof trusses can support the additional load on them fro the additional framing. Also noted that plans call for seperated uses, and notes 1hr. fire walls on either side. New wall on vanilla finish was not inspected as a 1hr. fire wall. Either provide UL for new wa;;, remove one side for proper inspection or resubmit plans to plan review for non seperated use. Correction notice was issued.
|
Telephone call | | | 5/12/2011 | | DONE |
Sam Zahorka
|
|
|
Spoke with the contractor Jim Wellman and the architect Jim Marsh. Verified 1-hour Fire barrier occupancy separation walls were approved under shell permits BLD11-00487 and BLD11-00488. Requested and received allowable building area calculation from the architect in accordance with IBC section 503.1 and 508.3.2 for Non-separated occupancies. Called the inpector Mike Jordan and shared information.
|
OVERRIDE | | | 5/11/2011 | | |
|
|
|
|
Telephone call | | | 5/11/2011 | | DONE |
Tisha Gallop
|
|
|
called James Marsh and left vm that permit is ready, fees and GC (Wellman Const) on hold until receive final values for Bld10-01321 &Bld10-01726 (see Tisha).
|
Issue PAID IN FULL permit | | | 5/11/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 5/9/2011 | | 5/11/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached review.
|
Plan assigned to (SRZ) | 4/18/2011 | | 5/11/2011 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 5/11/2011 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/11/2011 | | 5/11/2011 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/11/2011 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 5/11/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/11/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 4/20/2011 | | 5/9/2011 | | PASS |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 5/9/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLUMBING | 4/19/2011 | | 4/20/2011 | | PASS |
Bill VanDegrift
|
|
|
Hose reel requires minimum PVB backflow
Per plans and 2003 UPC
|
Routing - PUBLIC WORKS | 4/18/2011 | | 4/19/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 4/19/2011 | | 4/19/2011 | | PASS |
Walt Baumgartner
|
|
|
West Boise sewer district, no grease abatement required at this time.
|
Routing PW Sewer Rating | 4/19/2011 | | 4/19/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Plan Reviewer's activity | | | 4/18/2011 | | DONE |
Jason Blais
|
|
|
Emailed applicant and architect representative to have them contact ACHD to evaluate if any additional impact fees are required. Written verification from ACHD will need to be provided to our Permit Counter prior to building permit issuance.
|
Pending Assignment by JCB | 4/15/2011 | | 4/18/2011 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/15/2011 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/15/2011 | | DONE |
Christina Prado
|
|
|
|
Application received | | 4/15/2011 | | | |
|
|
|
|