Permit Information
Permit NumberBLD11-00777
StatusFinaled
Name WELLMAN CONSTRUCTION
Site Address 8184 W OVERLAND RD
Project NameU-SWIRL FROZEN YOGURT
Customer Number 
ePlanReviewNo
Description
(U-SWIRL FROZEN YOGURT) Remodel to a 2,000 sq. ft. space changing occupancy from retail to assembly frozen yogurt shop per approved plans. The previous vanilla finish permit was done under (BLD11-00487). Work to include: selective demo work per plans; construct new non-bearing interior wall partitions, new service counters/fixtures, public seating; relocation of existing lighting and HVAC diffusers; fire sprinkler work, new mechanical, new plumbing, and new electrical work; related interior finishes in compliance with chapter 8 of the 2009 IBC. All work per the approved plans, attached plan review report, and all other reviewing agencies approvals. A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is fully fire sprinklered for area increase. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 8/4/20118/16/2011 DONE
First Notice 7/30/20117/25/2011 DONE
Permanent Occupancy  7/20/2011 DONE
Permanent Occupancy  6/30/2011 DONE
DetailsBarbara Stitt
BLD-Final6/1/20116/1/20116/1/2011PPART
DetailsMike Jordan
Jim Phone #: ###-####. Ok for temp occ. Will be ok for perm occ once plumbing finals.
Temporary Occupancy UNPAID FEE  6/1/2011 DONE
DetailsTisha Gallop
BLD-Final5/31/20115/31/20115/31/2011PFAIL
DetailsMike Jordan
jim - late afternoon please Phone #: ###-####. Install all ada signage, also no grid inspection.
FIRE-Final Inspection5/31/20115/31/20115/31/2011PPASS
DetailsForrest France
Fire life safety inspection passed.
FIRE-Conference5/31/20115/31/20115/31/2011ADONE
DetailsForrest France
Discussion with contractor regarding items for final including repair two exit sign/EM lights, post max. occupant load sign, post PFE with current tag, add one exit sign per plan at restroom hall, test EM lights at grid ceilings, provide verification fire sprinkler system is current with an annual inspection.
BLD-Framing/Rough-in5/12/20115/12/20115/12/2011APART
DetailsMike Jordan
Phone #: 5413312871 >> Inspection requested via mobile web by jim wellman. Interior steel stud framed walls only, no grid and pending elec. inspection. Also needs to provide engineering showing that the existing roof trusses can support the additional load on them fro the additional framing. Also noted that plans call for seperated uses, and notes 1hr. fire walls on either side. New wall on vanilla finish was not inspected as a 1hr. fire wall. Either provide UL for new wa;;, remove one side for proper inspection or resubmit plans to plan review for non seperated use. Correction notice was issued.
Telephone call  5/12/2011 DONE
DetailsSam Zahorka
Spoke with the contractor Jim Wellman and the architect Jim Marsh. Verified 1-hour Fire barrier occupancy separation walls were approved under shell permits BLD11-00487 and BLD11-00488. Requested and received allowable building area calculation from the architect in accordance with IBC section 503.1 and 508.3.2 for Non-separated occupancies. Called the inpector Mike Jordan and shared information.
OVERRIDE  5/11/2011  
Telephone call  5/11/2011 DONE
DetailsTisha Gallop
called James Marsh and left vm that permit is ready, fees and GC (Wellman Const) on hold until receive final values for Bld10-01321 &Bld10-01726 (see Tisha).
Issue PAID IN FULL permit  5/11/2011 DONE
DetailsTisha Gallop
Routing - FIRE5/9/2011 5/11/2011 PASS
DetailsTim Frost
Please, see attached review.
Plan assigned to (SRZ)4/18/2011 5/11/2011 PASS
DetailsSam Zahorka
1st review completed  5/11/2011 DONE
Routing - PLAN CHECK5/11/2011 5/11/2011 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  5/11/2011 DONE
DetailsSam Zahorka
Print Occupancy Form  5/11/2011 DONE
Permit Ready to Issue  5/11/2011 DONE
DetailsTisha Gallop
Routing - PLAN CHECK4/20/2011 5/9/2011 PASS
DetailsSam Zahorka
Case Summary (BLD)  5/9/2011 DONE
DetailsSam Zahorka
Routing - PLUMBING4/19/2011 4/20/2011 PASS
DetailsBill VanDegrift
Hose reel requires minimum PVB backflow
Per plans and 2003 UPC
Routing - PUBLIC WORKS4/18/2011 4/19/2011 PASS
DetailsConnie Baumgartner
Routing PW Environmental4/19/2011 4/19/2011 PASS
DetailsWalt Baumgartner
West Boise sewer district, no grease abatement required at this time.
Routing PW Sewer Rating4/19/2011 4/19/2011 PASS
DetailsConnie Baumgartner
Plan Reviewer's activity  4/18/2011 DONE
DetailsJason Blais
Emailed applicant and architect representative to have them contact ACHD to evaluate if any additional impact fees are required. Written verification from ACHD will need to be provided to our Permit Counter prior to building permit issuance.
Pending Assignment by JCB4/15/2011 4/18/2011 DONE
DetailsJason Blais
Plans ACCEPTED BY PLAN TECH  4/15/2011 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  4/15/2011 DONE
DetailsChristina Prado
Application received 4/15/2011