Permit Information
Permit NumberBLD11-00783
StatusFinaled
Name ST LUKES REGIONAL MEDICAL CENTER LT
Site Address 100 E IDAHO ST
Project NameST LUKES MSTI 1ST FLR
Customer Number 
ePlanReviewNo
Description
(ST. LUKES - MSTI)(1ST FLR PEDS & WAITING REMODEL) This building is fully sprinklered. Perform select demolition as indicated on plans. Scope of work includes installation of a new exterior exit door directly from the Reception / Waiting Lobby to the Children's outdoor courtyard; construct new partial height interior non-bearing walls with access / exit doors, to separate the existing 1st floor lobby into a reception/waiting area, the elevator lobby area and the vestibule entry area; installation of a glass wall on the second floor balcony, behind the existing guardrail to the bottom of existing bulkhead above and from top of bulkhead to fit the slope of existing vaulted steel frame glass roof, separating the 1st & 2nd floor from the lobby for improved environmental control. Construct interior NB wall with windows and door assembly to remodel the existing waiting room to become additional chemo treatment areas and a nutrition bar area. An existing 2-hour fire barrier wall, used as a 2-hour horizontal exit, located as indicated on the plans, shall be maintained. Install a new set of double doors across the west end of the corridor to create a Children Center Suite, providing two required exits from new suite while maintaining other required exits serving the 1st floor. Modify the electrical, mechanical, plumbing, fire sprinkler and alarm systems for tenant needs and code compliance. NOTE: Separate applications, plans and permits are required for the fire sprinkler and the alarm modifications before any work on the system begins, as regulated by the fire department. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance/Occupancy  2/3/2012 DONE
DetailsBarbara Stitt
DOC - L/C Approved  2/3/2012 DONE
DetailsBarbara Stitt
BLD-Final1/27/20121/30/20121/30/2012APASS
DetailsDave Hannah
Daryl Phone #: ###-####
FIRE-Final Inspection1/26/20121/26/20121/26/2012PPASS
DetailsForrest France
Fire life safety completed satisfactory.
FIRE-Alarm Testing1/23/20121/23/20121/23/2012APART
DetailsForrest France
See project related fire alarm permit activity notes for items remaining.
FIRE-Final Inspection1/9/20121/9/20121/9/2012APART
DetailsForrest France
Project related fire sprinkler permit finaled, fire alarm test pending.
BLD-Other12/2/201112/5/201112/5/2011APASS
DetailsDave Hannah
daryl - ceiling inspection Phone #: ###-####
BLD-Framing/Rough-in11/10/201111/10/201111/10/2011PPASS
DetailsTom Arcoraci
Darrel-before 3 please Phone #: ###-####
BLD-Conference10/17/201110/18/201110/18/2011APART
DetailsDave Hannah
Daryl Phone #: ###-#### ok to move into new area and start second phase
FIRE-Conference10/4/201110/5/201110/5/2011ADONE
DetailsForrest France
On site conference regarding remodel schedule, related fire alarm and sprinkler trade permit work, life safety items.
BLD-Framing/Rough-in7/21/20117/22/20117/22/2011APASS
DetailsDave Hannah
daryl Phone #: ###-####
Inspection Record Card- Bld  5/26/2011 DONE
Permit Ready to Issue  5/26/2011 DONE
DetailsTisha Gallop
Telephone call  5/26/2011 DONE
DetailsTisha Gallop
Called Dana Kauffman and told him permit is ready.
Issue & PRINT to be Invoiced  5/26/2011 DONE
DetailsTisha Gallop
Plan assigned to (DRS)4/20/2011 5/25/2011 PASS
DetailsDan Stuart
Routing - FIRE5/19/2011 5/25/2011 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  5/25/2011 FAIL
Failed Plan Check
Routing - PLAN CHECK5/25/2011 5/25/2011 PASS
DetailsDan Stuart
Resubmittals added to plans. Plans okay to route to permit desk to issue permit.
Plan resubmittals received  5/25/2011 DONE
New mechanical compliance certificate and checklist for current 2009 IECC provided and added to plans.
PLANS/APPL TAKEN TO FRONT DESK  5/25/2011 PASS
Plan resubmittals requested  5/19/2011 DONE
Copy of plan review emailed to architect.
Routing - PLAN CHECK4/22/2011 5/19/2011 FAIL
DetailsDan Stuart
Resubmittal required. Copy of plan review e-mailed to architect. Routing plans to fire code plan analyst for review.
Routing - Design Review4/21/2011 4/22/2011 PASS
DetailsSarah Schafer
Sarah Schafer
Routing PW Sewer Rating4/21/2011 4/21/2011 PASS
DetailsConnie Baumgartner
Routing - PLUMBING4/21/2011 4/21/2011 PASS
DetailsBill VanDegrift
Per plans and 2003 UPC
Routing - PUBLIC WORKS4/20/2011 4/21/2011 PASS
DetailsConnie Baumgartner
Pending Assignment by JCB4/19/2011 4/20/2011 DONE
DetailsJason Blais
Routing - Addressing4/20/2011 4/20/2011 PASS
DetailsTerry Records
Plans ACCEPTED BY PLAN TECH  4/19/2011 DONE
ok per John Menard to take in as a level 3
Recd Pcfee & Taken To Pln CK  4/19/2011 DONE
Application received 4/18/2011