BLD-Final | 9/19/2011 | 9/20/2011 | 9/20/2011 | A | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####
|
DOC - Permit Finaled | 9/20/2011 | 9/20/2011 | 9/20/2011 | P | PASS |
Mike Jordan
|
|
|
All issues were resolved. Residential certificate of occupancy was issued.
|
BLD-Final | 9/7/2011 | 9/8/2011 | 9/8/2011 | A | FAIL |
Mike Jordan
|
|
|
adam Phone #: ###-####. Open mech. permit, Provide CO2 detector outside masterbedroom, provide energy cert, also needs to complete final grading.
|
BLD-Energy code compliance | 7/15/2011 | 7/18/2011 | 7/18/2011 | A | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####
|
BLD-Framing/Rough-in | 7/14/2011 | 7/15/2011 | 7/15/2011 | A | PASS |
Mike Jordan
|
|
|
ADAM Phone #: ###-####
|
BLD-Energy code compliance | 7/15/2011 | 7/15/2011 | 7/15/2011 | A | PASS |
Mike Jordan
|
|
|
ADAM Phone #: ###-####
|
BLD-Framing/Rough-in | 7/13/2011 | 7/13/2011 | 7/13/2011 | A | FAIL |
Mike Jordan
|
|
|
ADAM Phone #: ###-####. Fireblock area at coffered ceilings at main enterane. Provide the additional straps at garage as shown for portal frame holdown. Correction notice was posted. ok to insulate.
|
BLD-Framing/Rough-in | 7/7/2011 | 7/7/2011 | 7/7/2011 | P | NR |
Mike Jordan
|
|
|
josh Phone #: ###-####. Needs to complete air seal package prior to framing inspection.
|
Plan resubmittals received | | | 6/21/2011 | | DONE |
|
|
|
manual j resubmittal because different mechanical contractor doing the work. Needed to resubmitt because of different equipment.
|
Routing - MECHANICAL | 6/21/2011 | | 6/21/2011 | | PASS |
Troy James
|
|
|
|
BLD-Foundation | 6/7/2011 | 6/10/2011 | 6/10/2011 | A | PART |
Mike Jordan
|
|
|
BILL Phone #: ###-####
|
BLD-Footing | 6/8/2011 | 6/9/2011 | 6/9/2011 | A | PART |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 6/7/2011 | 6/8/2011 | 6/8/2011 | P | NR |
Mike Jordan
|
|
|
BILL Phone #: ###-####. No one on site, no forms have been constructed.
|
Issue PAID IN FULL permit | | | 5/24/2011 | | DONE |
|
|
|
|
OVERRIDE | | | 5/12/2011 | | |
|
|
|
|
Telephone call | | | 5/12/2011 | | DONE |
Christina Prado
|
|
|
Called Abram to let know permit is ready and advised on fees due
|
Inspection Record Card- Bld | | | 5/12/2011 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 5/12/2011 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 4/27/2011 | 4/27/2011 | 5/11/2011 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 5/2/2011 | | 5/11/2011 | | PASS |
Carl D Madsen
|
|
|
Carl Madsen
|
Case Summary (BLD) | | | 5/11/2011 | | DONE |
|
|
|
|
1st review completed | | | 5/11/2011 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/27/2011 | 5/2/2011 | 5/3/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | | | 5/2/2011 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/28/2011 | | 4/29/2011 | | PASS |
Susan Riggs
|
|
|
|
Routing - Addressing | | | 4/28/2011 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 4/28/2011 | | 4/28/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 4/27/2011 | 4/27/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/27/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 4/27/2011 | | PASS |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/27/2011 | | DONE |
Barbara Stitt
|
|
|
|