BLD-Final | 2/29/2012 | 3/1/2012 | 3/1/2012 | A | PASS |
Mike Jordan
|
|
|
steve - please call for access Phone #: ###-####
|
DOC - Permit Finaled | 3/1/2012 | 3/1/2012 | 3/1/2012 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 2/28/2012 | 2/29/2012 | 2/29/2012 | P | NR |
Mike Jordan
|
|
|
steve - please call 1/2 hr prior Phone #: ###-####
|
BLD-Energy code compliance | 1/25/2012 | 1/25/2012 | 1/25/2012 | P | PASS |
Mike Jordan
|
|
|
Steve-as late as possible please Phone #: ###-####
|
BLD-Framing/Rough-in | 1/24/2012 | 1/24/2012 | 1/24/2012 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. OK to insulate.
|
BLD-Framing/Rough-in | 1/23/2012 | 1/23/2012 | 1/23/2012 | P | NR |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Needs to complete airseal pack.
|
BLD-Foundation | 12/21/2011 | 12/23/2011 | 12/27/2011 | A | PASS |
Jim Sly
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 12/21/2011 | 12/22/2011 | 12/22/2011 | P | PASS |
Jim Sly
|
|
|
Bill Phone #: ###-####
|
OVERRIDE | | | 12/21/2011 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/21/2011 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 12/21/2011 | | DONE |
Christina Prado
|
|
|
called and gave Steve fees due
|
Permit Ready to Issue | | | 12/21/2011 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 4/29/2011 | 4/29/2011 | 12/20/2011 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 12/7/2011 | | 12/20/2011 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 12/20/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2011 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/20/2011 | | DONE |
|
|
|
|
Routing - PLANNING | 12/6/2011 | | 12/7/2011 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - MECHANICAL | 12/7/2011 | | 12/7/2011 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 12/6/2011 | | DONE |
Tisha Gallop
|
|
|
received full new set of plans, mechanical manual and reduced site plan. Routed to Planning, mechanical, plan check. Per Carl M. never did plan review on previous plans.
|
Route to Impact Fee Review | 4/29/2011 | 5/4/2011 | 7/7/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 5/9/2011 | | 5/13/2011 | | FAIL |
Carl D Madsen
|
|
|
Failed pending redisign of the structure to meet planning requirements. CDM
|
1st review completed | | | 5/13/2011 | | FAIL |
|
|
|
Failed pending redisign of the structure to meet planning requirements.
|
Routing - MECHANICAL | 5/3/2011 | | 5/9/2011 | | FAIL |
Troy James
|
|
|
no review, plans failed planning
|
Routing - PUBLIC WORKS | 5/2/2011 | | 5/3/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 4/29/2011 | | 5/2/2011 | | PASS |
Terry Records
|
|
|
|
Application received | | 4/29/2011 | 4/29/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/29/2011 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 4/29/2011 | | PASS |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/29/2011 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 5/3/2011 | | | | FAIL |
Colleen T Carroll
|
|
|
Does not meet front or west side setbacks. Left message 5/3/11
|