BLD-Aging Inspection | 9/26/2013 | 10/1/2013 | 10/1/2013 | A | FAIL |
Tony Young
|
|
|
|
DOC - Permit Finaled | 10/1/2013 | 10/1/2013 | 10/1/2013 | P | PASS |
Tony Young
|
|
|
done
|
BLD-Final | 8/26/2011 | 8/26/2011 | 8/29/2011 | P | NR |
Tony Young
|
|
|
chris Phone #: ###-####,, needs trades 1st
|
BLD-Energy code compliance | 7/19/2011 | 7/20/2011 | 7/20/2011 | A | PASS |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 7/13/2011 | 7/14/2011 | 7/14/2011 | A | PASS |
Tony Young
|
|
|
CHRIS Phone #: ###-####,, ok to insulate,, will have some double shear
|
BLD-Framing/Rough-in | 7/12/2011 | 7/13/2011 | 7/13/2011 | A | CANC |
Tony Young
|
|
|
CHRIS Phone #: ###-####,, rescheduled
|
BLD-Framing/Rough-in | 6/22/2011 | 6/22/2011 | 6/22/2011 | P | NR |
Tony Young
|
|
|
chris - shear wall inspection Phone #: ###-####,, need to have engineer give ok as built,, may add 2 windows,, not nailed per plan now
|
BLD-Foundation | 6/13/2011 | 6/13/2011 | 6/13/2011 | P | NR |
Tony Young
|
|
|
Cal Phone #: ###-####
|
BLD-Footing | 6/10/2011 | 6/10/2011 | 6/13/2011 | P | PART |
Tony Young
|
|
|
Cal Phone #: ###-####,, no rebar yet...
|
BLD-Footing | 5/27/2011 | 5/27/2011 | 5/31/2011 | P | NR |
Tony Young
|
|
|
Cal Phone #: ###-####
|
PubWorks Subgrade Approval | 5/24/2011 | 5/24/2011 | 5/24/2011 | | DONE |
Terry Records
|
|
|
Footing subgrade has been approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 5/10/2011 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 5/9/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/9/2011 | | DONE |
|
|
|
|
Telephone call | | | 5/9/2011 | | DONE |
|
|
|
5-9-11 called Chris permit ready and fee given ///dld
|
Plan assigned to (PEP) | 5/2/2011 | 5/2/2011 | 5/6/2011 | | PASS |
Perry Paine
|
|
|
|
Routing Walk-In (BLD) | 4/29/2011 | 4/29/2011 | 5/6/2011 | P | DONE |
Perry Paine
|
|
|
|
Routing - MECHANICAL | 5/5/2011 | | 5/6/2011 | | PASS |
Troy James
|
|
|
|
Case Summary (BLD) | | | 5/6/2011 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/6/2011 | | |
|
|
|
|
1st review completed | | | 5/6/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/6/2011 | | DONE |
|
|
|
|
Routing - MECHANICAL | 5/2/2011 | | 5/5/2011 | | FAIL |
Troy James
|
|
|
talked with chance at wester heating about correction that need to be made.
|
Routing - MECHANICAL | 5/2/2011 | | 5/2/2011 | | FAIL |
Troy James
|
|
|
DHW Report WALK - IN
emailed corrections to western heating
|
Routing Walk-In (PW Hillside) | 4/29/2011 | 4/29/2011 | 4/29/2011 | P | PASS |
David Moser
|
|
|
Footing subgrade must be approved by the applicants geotechnical engineer prior to scheduleding footing inspection
|
Routing Walk-In (Zoning) | 4/29/2011 | 4/29/2011 | 4/29/2011 | P | PASS |
Colleen T Carroll
|
|
|
|
Application received | | 4/29/2011 | | | |
|
|
|
|