Third Notice | | 1/22/2012 | 1/17/2012 | | DONE |
|
|
|
This permit finaled on the web by Brandon Byington
|
Second Notice | | 1/13/2012 | 1/17/2012 | | DONE |
|
|
|
|
First Notice | | 12/31/2011 | 1/3/2012 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/21/2011 | 12/21/2011 | 12/21/2011 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 12/21/2011 | 12/21/2011 | 12/21/2011 | A | PASS |
Tom Arcoraci
|
|
|
Call for access Phone #: 9413192 >> Inspection requested via mobile web by Cicel
|
Permanent Occupancy | | | 12/21/2011 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 12/1/2011 | 12/1/2011 | 12/1/2011 | P | PART |
Troy Cobbley
|
|
|
The lab area life safety is passed.
|
CHANGE STATUS TO (ISS) | | | 9/23/2011 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 9/23/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (DRS) | 8/18/2011 | 8/18/2011 | 9/21/2011 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLAN CHECK | 9/8/2011 | | 9/21/2011 | | PASS |
Dan Stuart
|
|
|
Door hardware schedule requested on 9/6/11 received from architect today. Plans to permit desk to issue.
|
Plan resubmittals received | | | 9/21/2011 | | DONE |
|
|
|
Met with Sam Burrows to review doors and door hardware for Stereotaxis Lab plan mod.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2011 | | PASS |
|
|
|
|
Print Occupancy Form | | | 9/21/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/21/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 9/21/2011 | | DONE |
Barbara Stitt
|
|
|
Called Brandon and told him that permit is ready & fees due on 9-21-11 @ 3:20pm//BAS
|
Telephone call | | | 9/20/2011 | | DONE |
|
|
|
Left voice message for Sam Burrows to call me. The door hardware submittal have not yet been provided. Wondering what the hold up has been?
|
Routing - FIRE | 9/7/2011 | | 9/8/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 9/2/2011 | | 9/7/2011 | | FAIL |
Dan Stuart
|
|
|
Plans routed to fire code analyst for review.
|
Telephone call | | | 9/6/2011 | | DONE |
|
|
|
Called Sam Burrows to see if he had received my message of 9/2/11. Sam was still out of the office until the afternoon.
|
Telephone call | | | 9/6/2011 | | DONE |
|
|
|
Sam Burrows returned my call this afternoon. We discussed concerns and what is needed for plan review. Sam has instrcuted the dorr hardware supplier to provide a current list of proposed door hardware. As soon as Sam receives the list he will call to set up an appointment so we can review exiting and the hardware code compliance.
|
Plan resubmittals requested | | | 9/2/2011 | | FAIL |
|
|
|
Called and left voice message for Sam Burrows to provide door hardware schedule.
|
Routing - PLAN CHECK | 8/18/2011 | | 9/2/2011 | | FAIL |
Dan Stuart
|
|
|
Dan Stuart
9/2/11 - Submitted plan modification did not include sufficient information on maintaining the required egress / access system and the door hardware schedule for the new fire-rated doors. Talked with Sam Burrows. He will provide missing data as soon as he receives the door hardware schedule from the supplier.
|
Telephone call | | | 9/2/2011 | | DONE |
|
|
|
Plan Modification changed fire rating of corridor to 1-hour and added a 2-hour fire barrier wall between the Stereotaxis lab T.I. and the remained of the third floor as required by State of Idaho H&W Facilities Permits. Door hardware schedule required to show code compliance for access/egress between areas and at the fire walls for closers. Existing doors from Lab into rated corridor need to indicate code compliance for fire rating and hardware. Left Message for Sam Burrows to call me when he gets back to the office.
|
Plan Modification Accepted | | | 8/18/2011 | | |
|
|
|
Plan modification accepted for the upgraded of the corridor around stereotaxi's lab to be 8'-0" wide and separate the lab from the rest of the floor with a 2 hour wall and 90 min doors. Sheets A0.1, A2.0, A2.1, A2.1F, A3.0, A7.0, A7.1, M1.1, M1.2, M1.3, M2.1, M2.2, M2.3, E0.0, E2.2D, E2.2F, E2.2L, E2.2M, E2.2P, E2.2S, E2.3, E3.0, E4.0 submitted for review with a new certificate of value
|
BLD-Wall cover | 7/22/2011 | 7/22/2011 | 7/22/2011 | P | DONE |
Tom Arcoraci
|
|
|
|
BLD-Conference | 7/20/2011 | 7/21/2011 | 7/21/2011 | P | PASS |
Tom Arcoraci
|
|
|
|
Issue PAID IN FULL permit | | | 6/16/2011 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 6/15/2011 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/15/2011 | | 6/15/2011 | | PASS |
Dan Stuart
|
|
|
To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/15/2011 | | PASS |
|
|
|
|
Print Occupancy Form | | | 6/15/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/15/2011 | | DONE |
|
|
|
|
Telephone call | | | 6/15/2011 | | DONE |
|
|
|
6-15-11 called Sam Burrows permit ready and fee given Also need GC ///dld
|
Plan assigned to (DRS) | 5/4/2011 | | 6/15/2011 | | PASS |
Dan Stuart
|
|
|
|
Routing - FIRE | 5/13/2011 | | 6/15/2011 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans.
|
Routing - PLAN CHECK | 5/11/2011 | | 6/13/2011 | | PASS |
Dan Stuart
|
|
|
No resubmittals required. Routing to fire code analyst for review. Copoy of report e-mailed to architect Sam Burrows for his records and notification of review completion.
|
Routing - PLUMBING | 5/9/2011 | | 5/11/2011 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 5/4/2011 | | 5/9/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 5/6/2011 | | 5/6/2011 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 5/3/2011 | | 5/4/2011 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/3/2011 | | |
|
|
|
ok per Tim Woodard for level 3 intake
|
Recd Pcfee & Taken To Pln CK | | | 5/3/2011 | | |
|
|
|
|
FIRE-Final Inspection | 12/21/2011 | 12/21/2011 | | A | |
|
|
|
As early as possible Phone #: 9413192 >> Inspection requested via mobile web by Cecil
|
Application received | | 5/3/2011 | | | |
|
|
|
|