BLD-Final | 8/25/2011 | 8/26/2011 | 8/26/2011 | P | PASS |
Jim Storey
|
|
|
Please call Deven so he can meet you onsite. Phone #: ###-#### >> Inspection requested via web by nate hutton
|
DOC - Permit Finaled | 8/26/2011 | 8/26/2011 | 8/26/2011 | P | PASS |
Jim Storey
|
|
|
|
Issue PAID IN FULL permit | | | 5/24/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (TLW) | 5/3/2011 | | 5/9/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 5/9/2011 | | 5/9/2011 | | PASS |
Tim L. Woodard
|
|
|
Architect sent a pdf showing the egress paths. The doors in question are only serving an occupant load of about 5 occupants. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 5/9/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Inspection Record Card- Bld | | | 5/9/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/9/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 5/9/2011 | | DONE |
Barbara Stitt
|
|
|
Called Peter and told him that permit is ready & fees due on 5-9-11 @ 3:30pm BAS
|
Routing - PLAN CHECK | 5/3/2011 | | 5/6/2011 | | FAIL |
Tim L. Woodard
|
|
|
Called Justin at Glancey Rockwell and he indicated he would get back with me on the door swing of door 101-2. It appears as if it is swinging the wrong way. TLW
|
1st review completed | | | 5/6/2011 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | 5/3/2011 | 5/3/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/3/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/3/2011 | | DONE |
Tisha Gallop
|
|
|
|