BLD-Final | 10/24/2011 | 10/25/2011 | 10/25/2011 | A | PASS |
Mike Jordan
|
|
|
adam - please call for access Phone #: ###-####
|
DOC - Permit Finaled | 10/25/2011 | 10/25/2011 | 10/25/2011 | P | PASS |
Mike Jordan
|
|
|
Residential certificate of occupancy was issued.
|
BLD-Energy code compliance | 9/7/2011 | 9/8/2011 | 9/8/2011 | A | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####
|
BLD-Framing/Rough-in | 8/31/2011 | 9/1/2011 | 9/1/2011 | A | PASS |
Mike Jordan
|
|
|
adam Phone #: ###-####. All issues have been resolved . Ok to insulate.
|
BLD-Framing/Rough-in | 8/31/2011 | 8/31/2011 | 8/31/2011 | P | FAIL |
Mike Jordan
|
|
|
Adam Phone #: ###-####. Com plete encapsulation of knee walls on bonus room trusses, Complete work on PFH framing. Correction notice posted.
|
BLD-Framing/Rough-in | 8/24/2011 | 8/25/2011 | 8/25/2011 | A | FAIL |
Mike Jordan
|
|
|
Adam Phone #: ###-####. Provide portal framing at garage and den as per detail 5 on sheet A5.1 on approved plans, knee wall on bonus room trusses need to be encapsulated on all six sides. Correction notice posted. Do not insulate.
|
BLD-Framing/Rough-in | 8/23/2011 | 8/24/2011 | 8/24/2011 | A | NR |
Mike Jordan
|
|
|
adam Phone #: ###-####. Airseal package not completed.
|
BLD-Footing | 7/20/2011 | 7/20/2011 | 7/20/2011 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 7/19/2011 | 7/20/2011 | 7/20/2011 | A | CANC |
Mike Jordan
|
|
|
bill Phone #: ###-####. moved to pm.
|
BLD-Footing | 7/14/2011 | 7/15/2011 | 7/15/2011 | P | CANC |
Mike Jordan
|
|
|
BILL Phone #: ###-####-Contractor called in to called @ 11:57//BAS
|
BLD-Foundation | 7/12/2011 | 7/14/2011 | 7/14/2011 | P | CANC |
Mike Jordan
|
|
|
bill Phone #: ###-####
|
BLD-Footing | 7/12/2011 | 7/13/2011 | 7/14/2011 | P | NR |
Mike Jordan
|
|
|
bill Phone #: ###-####. Needs to locate pins for property lines.
|
Issue PAID IN FULL permit | | | 7/12/2011 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 6/2/2011 | | |
|
|
|
|
Telephone call | | | 6/2/2011 | | DONE |
Tisha Gallop
|
|
|
called Eaglewood Homes and left vm for Abram that permit is ready and fees.
|
Inspection Record Card- Bld | | | 6/2/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/2/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 5/11/2011 | 5/11/2011 | 6/1/2011 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 6/1/2011 | | 6/1/2011 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 6/1/2011 | | 6/1/2011 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/1/2011 | | |
|
|
|
|
Routing - PLAN CHECK | 5/17/2011 | | 5/23/2011 | | FAIL |
Carl D Madsen
|
|
|
Failed pending Mechanical 5-23-11 CDM
|
1st review completed | | | 5/23/2011 | | FAIL |
|
|
|
Failed pend mechanical resubmittals.
|
Case Summary (BLD) | | | 5/23/2011 | | DONE |
|
|
|
|
Routing - MECHANICAL | 5/12/2011 | | 5/17/2011 | | FAIL |
Troy James
|
|
|
emailed corrections to northwest heating
|
Route to Impact Fee Review | 5/10/2011 | 5/13/2011 | 5/13/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 5/11/2011 | | 5/12/2011 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 5/12/2011 | | 5/12/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 5/12/2011 | | 5/12/2011 | | PASS |
Colleen T Carroll
|
|
|
Approved as redlined, driveway shall be setback 3 feet from side property line. R-1C setbacks as per SS
|
Intake Approval | | | 5/11/2011 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/11/2011 | | DONE |
|
|
|
|
Application received | | 5/10/2011 | | | |
|
|
|
|