Permit for the construction of a 8,234 sq. ft., three story (basement 692 sq. ft., second story 6,893 sq. ft., third story 1,341 sq. ft.) with 5 bedrooms, 5 full bathrooms, 3 half bathrooms, approximately 1,119 sq. ft. of covered patio/porch and a 2,589 sq. ft. attached garage per the approved plans, plan review report, any notations and the attached engineering. Fire Sprinklers are required for this residence; per Boise Fire department Subdivision Plat note #13.A letter from the applicant’s geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at 384-3946. A-1 zoning and setbacks per planning. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/10/20127/10/20127/20/2012PDONE
DetailsTony Young
bob Phone #: ###-####
BLD-Final7/18/20127/19/20127/19/2012PPASS
DetailsTony Young
bob Phone #: ###-####
DOC - Permit Finaled7/19/20127/19/20127/19/2012PPASS
DetailsTony Young
c of o issued
BLD-Final7/9/20127/10/20127/10/2012APART
DetailsTony Young
bob Phone #: ###-####,, all ok,, but need guardrail on deck stairs to meet 4" at top
BLD-Grading Inspection7/6/20127/6/20127/6/2012PDONE
DetailsTerry Records
BLD-Conference5/24/20125/25/20125/25/2012APASS
DetailsTony Young
bob Phone #: ###-####,, handrail ?s
Routing - FIRE4/18/2012 4/20/2012 PASS
DetailsScott Arellano
Plan assigned to (CDM)4/12/20124/12/20124/18/2012 PASS
DetailsCarl D Madsen
Routing - PLAN CHECK  4/18/2012 PASS
DetailsCarl D Madsen
Plan resubmittals received  4/18/2012 DONE
DetailsScott Arellano
Recieved resubmitted plans showing adequate Fire Department vehicle access roadways to accomodate turnaround; as requested by the Fire Marshal. Plans are approved.
Routing - PLAN CHECK4/18/2012 4/18/2012 PASS
DetailsScott Arellano
Plans for FD vehicle turnaround are approved.
PLANS/APPL TAKEN TO FRONT DESK  4/18/2012  
CHANGE STATUS TO (ISS)  4/18/2012 DONE
DetailsChristina Prado
Routing - PUBLIC WORKS GRADING4/12/2012 4/17/2012 PASS
DetailsTerry Records
BLD-Footing4/13/20124/16/20124/16/2012PPART
DetailsTony Young
Bob Phone #: ###-####,, retaing wall,, in progress
Plan resubmittals received  4/12/2012 DONE
DetailsChristina Prado
Received three sets of plans marked C2.0, C2.1, C3.0 & C4.0. Routed plans to Terry Records. Fire & Plan Check for further review
BLD-Conference1/27/20121/30/20121/30/2012APASS
DetailsTony Young
bob Phone #: ###-####,,, soffits ok
BLD-Conference12/30/20111/4/20121/5/2012APART
DetailsTony Young
Bob Phone #: ###-####,, check on soffits.. can lights in soffits wrapped ok,, 2 layers
BLD-Energy code compliance12/30/201112/30/201112/30/2011PPASS
DetailsTony Young
Bob Phone #: ###-####
BLD-Energy code compliance12/29/201112/30/201112/30/2011ANR
DetailsTony Young
Bob Phone #: ###-####
BLD-Energy code compliance12/27/201112/28/201112/29/2011PNR
DetailsTony Young
BLD-Framing/Rough-in12/22/201112/23/201112/27/2011PPASS
DetailsTony Young
Bob Phone #: ###-####
BLD-Framing/Rough-in12/21/201112/22/201112/23/2011PPART
DetailsTony Young
Bob Phone #: ###-####,,, ok to insulate,,, need sprinkler final approval...
BLD-Framing/Rough-in12/21/201112/21/201112/21/2011PPART
DetailsTony Young
Bob Phone #: ###-####,, c/n,, see Bob,,,, need sprinkler r/in,,, ok to insulate walls
BLD-Conference12/13/201112/14/201112/21/2011APART
DetailsTony Young
Bob Phone #: ###-####,, frame conf walk through
BLD-Framing/Rough-in12/13/201112/13/201112/13/2011PPART
DetailsTony Young
Bob Phone #: ###-####,,,pending approval of the electrical ok for the soffits,,, ok to start the 2 layers of rock on the soffits,,, light boxes done,, pending ele.
BLD-Wall Bracing11/18/201111/21/201111/21/2011APART
DetailsTony Young
shear wall..Bob Phone #: ###-####,,, exterior shear ok
BLD-Other11/18/201111/18/201111/18/2011PPART
DetailsTony Young
shear wall..Bob Phone #: ###-####,,, most exterior ok to cover,, marked some areas of re- do
BLD-Other11/10/201111/10/201111/10/2011PPART
DetailsTony Young
bob - shear inspection Phone #: ###-####,, floors ok to cover,, general conference
BLD-Foundation8/29/20118/30/20118/30/2011APART
DetailsTony Young
bill Phone #: ###-####,, pier point load columns,, work in progress,, ok to pour when ready
BLD-Foundation8/25/20118/29/20118/29/2011ANR
DetailsTony Young
bill Phone #: ###-####
BLD-Foundation8/23/20118/25/20118/25/2011APART
DetailsTony Young
bill Phone #: ###-####,, planter boxes,,
BLD-Foundation8/19/20118/23/20118/23/2011PPART
DetailsTony Young
bill Phone #: ###-####,, interior and porch ftgs ok
BLD-Footing8/19/20118/22/20118/22/2011PNR
DetailsDave Hannah
bill Phone #: ###-####
BLD-Foundation8/15/20118/15/20118/15/2011PPASS
DetailsTony Young
foundation steel insp//Bill Phone #: ###-####,, house walls ok
BLD-Footing8/3/20118/4/20118/4/2011APART
DetailsTony Young
bill Phone #: ###-####,, house footings,, work in progress,, ok to pour when ready,,
BLD-Footing8/3/20118/3/20118/3/2011PNR
DetailsTony Young
bill Phone #: ###-####,, needs soils report for house area
BLD-Footing8/1/20118/3/20118/3/2011ANR
DetailsTony Young
bill Phone #: ###-####
PubWorks Subgrade Approval8/3/20118/3/20118/3/2011 DONE
DetailsTerry Records
Footing subgrade for main level approved by the geotechnical engineer.
BLD-Foundation7/21/20117/22/20117/22/2011APART
DetailsTony Young
bill Phone #: ###-####,, basement walls work in progress,, ok to pour when ready
BLD-Footing7/19/20117/19/20117/19/2011PPART
DetailsTony Young
bill Phone #: ###-####
basement ftgs ok
PubWorks Subgrade Approval7/14/20117/14/20117/14/2011 PART
DetailsTerry Records
subgrade for basement footings only approved by the geotechnical engineer
Issue PAID IN FULL permit  7/7/2011 DONE
DetailsTisha Gallop
Plan assigned to (CDM) 5/27/20117/5/2011 DONE
DetailsCarl D Madsen
Routing - PLAN CHECK  7/5/2011 PASS
DetailsCarl D Madsen
Routing - PLANNING7/1/2011 7/5/2011 PASS
DetailsJoshua Johnson
PLANS/APPL TAKEN TO FRONT DESK  7/5/2011  
Inspection Record Card- Bld  7/5/2011 DONE
Telephone call  7/5/2011 DONE
DetailsChristina Prado
Called and spoke with Brian, advised fees due
Permit Ready to Issue  7/5/2011 DONE
DetailsChristina Prado
Case Summary (BLD)  7/1/2011 DONE
Routing PW Grading-Hillside6/29/2011 6/29/2011 PASS
DetailsTerry Records
Plan resubmittals received  6/24/2011  
Received 2 copies of 2 of 14 (foundation plan) to reflect change in civils-taken to carl Madsen's desk
Routing - PLAN CHECK6/10/2011 6/21/2011 PASS
DetailsCarl D Madsen
1st review completed  6/21/2011 FAIL
Failed pending approval of the hillside application. 6-21-11 CDM
Routing - MECHANICAL6/17/2011 6/17/2011 PASS
DetailsTroy James
Plan resubmittals received  6/16/2011 DONE
DetailsChristina Prado
Received two sets of new site plan and larger manual d as requested by Troy. Routed for additional review
Routing - MECHANICAL6/3/2011 6/14/2011 FAIL
DetailsTroy James
waiting for larger manual d design
Route to Impact Fee Review5/27/20116/2/20116/10/2011 PASS
DetailsCindy M. Gould
Fire Sprinkers are required; per Boise Fire Department. Refer to subdivision plat note #13 and SUB04-00056.
Routing - FIRE6/9/2011 6/10/2011 PASS
DetailsScott Arellano
Fire sprinklers are requried; per subdivision plat note #13. Refer to SUB04-00056 Fire Comments.
Routing - Erosion and Sediment6/9/2011 6/9/2011 PASS
DetailsSteven Webb
ESC plan is approved according to the ESC plan and ESC permit conditions. ESC11-00322
Routing - PLANNING6/3/2011 6/3/2011 FAIL
DetailsDavid Moser
Need hillside development permit for retaining wall
Routing - PUBLIC WORKS  6/3/2011 PASS
DetailsConnie Baumgartner
Routing - Addressing5/27/2011 6/2/2011 PASS
DetailsTerry Records
Routing PW Grading-Hillside  6/2/2011 FAIL
DetailsTerry Records
6 foot high retainig wall needs Hillside Development application approved.
Plans ACCEPTED BY PLAN TECH  5/27/2011 DONE
DetailsChristina Prado
Intake Approval  5/27/2011 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  5/27/2011 DONE
DetailsChristina Prado
Application received 5/27/2011