Case Summary (BLD) | | | 1/23/2013 | | DONE |
|
|
|
|
Third Notice | | 5/31/2012 | 5/30/2012 | | DONE |
|
|
|
|
Third Notice | | 5/2/2012 | 5/17/2012 | | DONE |
|
|
|
faxed to GC
|
Third Notice | | 4/3/2012 | 4/18/2012 | | DONE |
|
|
|
faxed to GC
|
Second Notice | | 3/25/2012 | 3/29/2012 | | DONE |
|
|
|
|
First Notice | | 3/4/2012 | 3/15/2012 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/23/2012 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 2/14/2012 | 2/14/2012 | 2/14/2012 | A | PASS |
Forrest France
|
|
|
|
BLD-Final | 1/4/2012 | 1/4/2012 | 1/4/2012 | P | PASS |
Dave Hannah
|
|
|
Entry doors are now installed. Thanks! Phone #: ###-#### >> Inspection requested via web by Todd Weltner ok for perm occ
|
BLD-Final | 9/7/2011 | 9/7/2011 | 9/7/2011 | P | PART |
Dave Hannah
|
|
|
Todd Phone #: ###-#### ok for temp occ need to check front door after its installed
|
FIRE-Final Inspection | 9/7/2011 | 9/7/2011 | 9/7/2011 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Framing/Rough-in | 7/27/2011 | 7/27/2011 | 8/3/2011 | P | PASS |
Dave Hannah
|
|
|
todd - late afternoon please Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/15/2011 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 5/27/2011 | | 7/7/2011 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 7/6/2011 | | 7/7/2011 | | DONE |
Carl Westfall
|
|
|
Prepared drawings for issuance.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/7/2011 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/7/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/7/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 7/7/2011 | | DONE |
Tisha Gallop
|
|
|
called Tom Houston (applicant) and left vm that permit is ready, fees, need GC/RCE/form, and ACHD. Called Katie Butler (arch.rep.) and told her permit is ready, fees and need GC/RCE/form and ACHD since occupant load increased.
|
Routing - FIRE | 7/2/2011 | | 7/6/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached review.
|
Routing - PLAN CHECK | 6/17/2011 | | 7/2/2011 | | PASS |
Carl Westfall
|
|
|
Drawings approved after 1st complete review. "Red line" notes added to the drawings.
|
Plan resubmittals received | | | 6/29/2011 | | DONE |
|
|
|
received 1 response and 2 copies of sheets G0.1,A2.1,A2.2,A6.1,A8.1,A10.1,MO.1,M2.1,E0.1,E1.1
|
Routing - FIRE | 6/15/2011 | 6/15/2011 | 6/17/2011 | | FAIL |
Scott Arellano
|
|
|
Full review will be completed when IBC issues have been resolved.
|
1st review completed | | | 6/17/2011 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/15/2011 | 6/20/2011 | 6/16/2011 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - PLAN CHECK | 6/2/2011 | | 6/15/2011 | | FAIL |
Carl Westfall
|
|
|
Could not continue the IBC plan review because there were too many issues. Sent an E-mail to the Architect and his representative explaining what the issues were and asking for a resolution.
|
Routing - PUBLIC WORKS | 5/27/2011 | | 6/2/2011 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLANNING | 6/2/2011 | | 6/2/2011 | | PASS |
Scott Spjute
|
|
|
Scott Spjute
|
Routing PW Sewer Rating | 6/2/2011 | | 6/2/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 6/1/2011 | | 6/1/2011 | | PASS |
April Wing
|
|
|
|
Application received | | 5/27/2011 | 5/27/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/27/2011 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/27/2011 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 5/27/2011 | | PASS |
Tim L. Woodard
|
|
|
|
Pending Assignment by JCB | 5/27/2011 | | 5/27/2011 | | DONE |
Jason Blais
|
|
|
|