BLD-Final | 10/10/2011 | 10/11/2011 | 10/11/2011 | A | PASS |
Jim Sly
|
|
|
cody Phone #: ###-#### C/C issued
|
DOC - Permit Finaled | 10/11/2011 | 10/11/2011 | 10/11/2011 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 10/5/2011 | 10/6/2011 | 10/6/2011 | A | NR |
Jim Sly
|
|
|
RYAN Phone #: ###-#### Need Mech, Mech F/P, Electr finals and copy of Foam/seal inspection and approval or Blower door test approval.
|
BLD-Energy code compliance | 8/12/2011 | 8/15/2011 | 8/15/2011 | A | PASS |
Jim Sly
|
|
|
ryan Phone #: ###-####
|
BLD-Framing/Rough-in | 8/12/2011 | 8/12/2011 | 8/12/2011 | P | PART |
Jim Sly
|
|
|
Cody phone ###-#### ###-#### Misc. corr....OK to insulate
|
BLD-Framing/Rough-in | 8/11/2011 | 8/12/2011 | 8/12/2011 | A | CANC |
Jim Sly
|
|
|
Ryan or ###-#### for Cody Phone #: ###-#### Re-sched....
|
BLD-Conference | 8/11/2011 | 8/12/2011 | 8/12/2011 | A | CANC |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 8/9/2011 | 8/11/2011 | 8/11/2011 | A | NR |
Jim Sly
|
|
|
Ryan Phone #: ###-#### Need to meet Contr and Framer at jobsite.
|
BLD-Footing | 6/27/2011 | 6/28/2011 | 6/28/2011 | P | PART |
Jim Sly
|
|
|
bill Phone #: ###-#### Advised concrete contractor of Engineering required for tall wing walls at garage. Engineering shows special bolts for hold downs and rebar specific for hold down area. Contractor working on this area. Advised to talk to Engineer and owner of Concrete Co. prior to pour.
|
BLD-Conference | 6/27/2011 | 6/28/2011 | 6/28/2011 | A | CANC |
Jim Sly
|
|
|
|
BLD-Footing | 6/24/2011 | 6/27/2011 | 6/27/2011 | P | PASS |
Jim Sly
|
|
|
Bill Phone #: ###-####
|
OVERRIDE | | | 6/24/2011 | | |
|
|
|
|
Telephone call | | | 6/24/2011 | | DONE |
Tisha Gallop
|
|
|
called Cody and left vm permit is ready and fees.
|
Issue PAID IN FULL permit | | | 6/24/2011 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 6/24/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/24/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 6/1/2011 | 6/1/2011 | 6/23/2011 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 6/23/2011 | | |
|
|
|
Received 2 copies of sheet 6 and 7 of 12 taken and added to plans at Carl Madsen's desk
|
Case Summary (BLD) | | | 6/23/2011 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/23/2011 | | 6/23/2011 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/2011 | | |
|
|
|
|
Routing - PLAN CHECK | 6/22/2011 | | 6/22/2011 | | FAIL |
Carl D Madsen
|
|
|
Resubmittals are required to be on plan sized sheets. Called and E-Mailed Cody at Solitude Homes. 6-22-11 CDM
|
Plan resubmittals received | | | 6/20/2011 | | DONE |
|
|
|
received 1beam over rv door taken to Carl M.
|
Plan resubmittals received | | | 6/17/2011 | | |
Barbara Stitt
|
|
|
Received 1 copy of typical roof overbuild detail package-stamped and put with plans on Carl Madsen desk
|
Route to Impact Fee Review | 6/1/2011 | 6/6/2011 | 6/16/2011 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 6/13/2011 | | 6/14/2011 | | PASS |
Joshua Johnson
|
|
|
|
1st review completed | | | 6/13/2011 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 6/8/2011 | | 6/13/2011 | | FAIL |
Carl D Madsen
|
|
|
Resubmitals required. 6-13-11 CDM
|
Routing - MECHANICAL | 6/24/2011 | | 6/9/2011 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 6/6/2011 | | 6/8/2011 | | FAIL |
Troy James
|
|
|
emailed corrections to idahohvac
|
Plan resubmittals received | | | 6/7/2011 | | |
|
|
|
Received 2 copies of site plan and attached to plans- will need to go back to planning for review.
|
Routing - PUBLIC WORKS | | | 6/3/2011 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 6/1/2011 | | 6/2/2011 | | PASS |
Terry Records
|
|
|
|
Intake Approval | | | 6/1/2011 | | PASS |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/1/2011 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | 5/31/2011 | 5/31/2011 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 5/31/2011 | | FAIL |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/31/2011 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLANNING | 6/3/2011 | | | | FAIL |
|
|
|
Circular Driveway and drive aisle setback do not conform to code
|
Routing - PLAN CHECK | 6/14/2011 | | | | |
Carl D Madsen
|
|
|
|